MahaRERA Property Intelligence · Pune

SKY TOWERS

P52100050531 · TALEGAON DABHADE · promoter Riddhisiddhi Developers

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP52100050531
Registered on21 Apr 2023
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Riddhisiddhi Developers is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SKY TOWERS1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at TALEGAON DABHADE, PLOT NO-2, CTS NO-1820 Satyakamal colony Talegaon Dabhade, Mawal, Pune, 410507. Per the filed land record, the plot is bounded to the north by CTS NO-1821 PLOT NO-58, to the south by TALEGAON CHAKAN ROAD, to the east by CTS NO- 1819 PLOT NO-3 and to the west by COLONY ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/s. Riddhisiddhi Developers is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by M/s. Riddhisiddhi Developers

M/s. Riddhisiddhi Developers
FlaggedPune
M/s. Riddhisiddhi Developers
FlaggedPune

Other RERA-registered projects in Talegaon Dabhade

Real Dream Homes Wing C AND D
possession by Jul 2026 · Real Buildcon Builders AND Developers
ECO City
possession by Aug 2026 · Namrata Promoters AND Builders
Luxuria
possession by Aug 2026 · Prammukh Associates
Arunoday Classic A Wing
possession by Sep 2026 · Kedar Harishchandra Khandge
Hillcrest
possession by Oct 2026 · Swapnashilp Buildcon
Greendale ENA
possession by Dec 2026 · M/s. Karpe Construction Company

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

SKY Tree Tower
possession by Jan 2027 · Kiran Buildcon
SKY Twins
declared completion Dec 2020 · Ravinanda Landmarks Unit3
SKY View
declared completion Jun 2018 · Harpale Associates
SKY View PH 1
declared completion Dec 2018 · M D Constructions
SKY View Residency
possession by Feb 2028 · Mangesh Vasant Gundal
SKY Villas
declared completion Jun 2026 · Malhar Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026