MahaRERA Property Intelligence · Pune

Skyone

P52100051663 · Sector No. 18 · promoter Skyller Group

Certificate SignedDue 30 Jun 2025

Delivery & Registration

MahaRERA registrationP52100051663
Registered on27 Jun 2023
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 13 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Skyone1G+330 Jun 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Sector No. 18, Plot No. 88, Haveli, Pune, 411019. Per the filed land record, the plot is bounded to the north by By plot number 55, to the south by By 10 meter road, to the east by By 12 meter road and to the west by By plot number 87. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chinchwad

THE Central Park Phase -I
possession by Dec 2026 · R Retail Ventures Private Limited
Manorama Heights
possession by Dec 2026 · Manali Bridgecast LLP
Palaash Aayush
possession by Jan 2027 · S P B Infra
THE Central Park Phase - II
possession by Jun 2027 · R Retail Ventures Private Limited
THE Central Park Phase - III
possession by Jun 2027 · R Retail Ventures Private Limited
Palaash Aayush Phase 2
possession by Dec 2027 · S P B Infra

Major developers building in Chinchwad

Other RERA-registered projects in Pune

Skyora
possession by Jun 2029 · Green Ladder Estates LLP
Skyra Evershine
possession by Mar 2027 · Anil Amolakchand Kankariya
Skyra Residency
declared completion Dec 2022 · Akshay Anil Kankariya
Skyreen
declared completion Oct 2024 · Nilima Prafulla Badhe
Skyrena
possession by Feb 2028 · M.D Developers
Skyrise
possession by Dec 2026 · Yashodha Buildcon

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026