Pune/Project record

MahaRERA · the public record

Sopan Baug

Pune · Archienova Creations

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100006339

Delivery and registration

When is the project declared for completion?

Sopan Baug is registered with MahaRERA as P52100006339 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100006339
Registered on14 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sopan Baug record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sopan Baug in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Wing A1G+431 Jul 2019
Wing B1G+431 Jul 2019

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for Sopan Baug, with orders passed in 4 of them.

4complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000011686931/03/2022Atul Harishchandra Yelbhar vs Archienova Creationsorder passed
CC00500000011687531/03/2022Atul Harishchandra Yelbhar vs Archienova Creationaorder passed
CC00500000012711618/05/2022Thaksen Bankhile vs Archienova Creationsorder passed
CC00500000012711818/05/2022Thaksen Bankhile vs Archie Nova Creationsorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2025Due to market recession and Covid -19 situation we were not able to achieve expected numbers in sales. Also due to lockdown conditions and loss of business, the customers were not

Location, Land & Connectivity

Located at Ambegaon, Pune, 410503. Per the filed land record, the plot is bounded to the north by 131, to the south by 166, to the east by 131 and to the west by 130. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~51 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)48 km
Kharadi / EON IT Park51 km
Hinjewadi Rajiv Gandhi IT Park53 km
Baner–Balewadi belt54 km
Pune Junction / city centre55 km
Magarpatta / Hadapsar IT55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Manchar

Sairaj
possession by Dec 2026 · Laxmideep Infrastructures
Lalbag Villa
possession by Feb 2027 · Reliable Properties
Kokane Rich Heights
possession by Mar 2027 · N K Builders
Anandi Malhar
possession by Dec 2027 · Reliable Constructions
BSP Plaza
possession by Dec 2027 · BSP Builders AND Developers
Saffron Villas
possession by Jan 2028 · Nupur Landmarks Private Limited

Other RERA-registered projects in Pune

Soujanya Sahakari Griha Rachana Sanstha Maryadit
possession by Jan 2027 · Hublikar Aurora Constructions LLP
Soumitra
possession by Dec 2028 · Urban Realty
Sourabh Co-Op Hsg.soc-Redevelopment
declared completion Oct 2020 · Vikas Gopal Kulkarni
SP House
possession by Apr 2027 · SP Estates
SP Platinum
declared completion Dec 2021 · S.p.developers
SP Residency Phase III
declared completion Jun 2024 · Supra Warehousing Private Limited

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.