SP RESIDENCY PHASE III

Hadapsar · Supra Warehousing Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

0units filed as unsoldInventory · 17 September 2026
15 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
112registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

15 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100015190

Delivery and registration

When is the project declared for completion?

SP RESIDENCY PHASE III is registered with MahaRERA as P52100015190 and the promoter has declared completion for 15 Jun 2024.

15 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100015190
Registered on07 Feb 2018
Promoter-declared completion15 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SP RESIDENCY PHASE III record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Supra Warehousing is the promoter of record on 13 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

13projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In SP RESIDENCY PHASE III, 112 of 112 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 remain available.

100%sold

112 of 112 homes

₹70.66 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹66.13 Cr (about 94%) is recorded as collected and ₹4.54 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 112 registered agreements, the effective carpet rate is ₹8,177/sqft, with eight in ten falling between ₹7,639 and ₹8,483 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 112 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Every home in SP RESIDENCY PHASE III is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 112 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 112 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19 and 112 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
B1 - Wing 1 and Wing 21G+1911215 Jun 2021

Unit mix on the filing: 112 residential.

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for SP RESIDENCY PHASE III, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000025914919/07/2023Amol Sambhaji Phadke vs SUPRA WAREHOUSING PRIVATE LIMITED THROUGH DIRECTOR SUNITA KHANNA AND OTHERSorder passed
CC00500000025925408/08/2023KOMAL KUMBHARE vs PHENOMENON DEVELOPERS PVT LTDpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered15 Jun 2023We are hereby submitting following documents for consideration of the Authority: (a) Commencement Certificate issued by PMRDA is enclosed under Tab No. 1 i.e., "Copy of the perm
15 Jun 202315 Jun 2024Dear Sir/ Madam, Please find enclosed herewith the MahaRERA order (Refer Tab No.2, Resolution of the Association of Allottees) along with our application for extension in "Form

Location, Land & Connectivity

Located at Hadapsar , Pune Saswad Road, Mumbai City, Mumbai City, 412308. Per the filed land record, the plot is bounded to the north by Shiv Road Phursungi Army Welfare Housing Org, to the south by SP Infocity IT ITES SEZ BLD 4, to the east by SP Infocity IT ITES SEZ and to the west by Survey No 208 Satyapuram Society Pune Saswad Rd. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Magarpatta / Hadapsar IT4 km
Kharadi / EON IT Park7 km
Pune Junction / city centre9 km
Pune Int'l Airport (Lohegaon)11 km
Baner–Balewadi belt20 km
Hinjewadi Rajiv Gandhi IT Park25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Fursungi

Casalino Towers Phase 3
possession by Oct 2026 · Sai Siddhi Promoters & Builders
Green Hive Plus Wing A4
possession by Dec 2026 · Ram India Shelters
THE Mpire Building E
possession by Dec 2026 · AGN Venture
Vandan Vihar
possession by Jun 2027 · GVN Developers PVT LTD
AGS Complex
possession by Sep 2027 · AGS Properties
Pacific Tower
possession by Sep 2027 · Chaitanya Developers

Major developers building in Fursungi

Other RERA-registered projects in Pune

Space 31
possession by Dec 2028 · Shaqiab ALI Taufiq ALI Sayed
Space Icon
declared completion Apr 2025 · Space Developers
Space Paramount Tower
possession by Apr 2027 · Azhar Zuber Shaikh
Spacia
declared completion Jun 2023 · MM Housing
Spandan
possession by Oct 2026 · Evolve Infra
Spar Accentures
possession by Dec 2033 · Spar Accentures

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026