Pune/Project record

MahaRERA · the public record

SUKHAKARTA RESIDENCY

Pune · R B TARTE BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

24 Jan 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

24 Jan 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013443

Delivery and registration

When is the project declared for completion?

SUKHAKARTA RESIDENCY is registered with MahaRERA as P52100013443 and the promoter has declared completion for 24 Jan 2019.

24 Jan 2019

declared completion

92months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013443
Registered on07 Oct 2017
Promoter-declared completion24 Jan 2019
Current statusCertificate Signed
Against todayabout 92 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SUKHAKARTA RESIDENCY record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Tarte Builders is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SUKHAKARTA RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
A1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered24 Jan 2019Part Completion Application done for the existing project and the adjourning plot of the existing building is on paper working for amulcumtion process we are in planning to develop

Location, Land & Connectivity

Located at Haveli, Pune, 411035. Per the filed land record, the plot is bounded to the north by BY PROPERTY OF TARACHAND TARTE, to the south by BY PROPERTY OF SHANKAR TARTE, to the east by BY ROAD and to the west by BY PROPERTY OF PRABHAKAR KUTE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)122 km
Kharadi / EON IT Park126 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Akurdi

Pentagon Business HUB
possession by Sep 2026 · Cosmic Infrastructure
Mantra Meraki Phase 5
possession by Dec 2026 · Mantra Residential Akurdi Private Limite
Mantra Meraki Phase 6
possession by Dec 2026 · Mantra Residential Akurdi Private Limite
ONE Platinum
possession by Dec 2026 · Matrix Developers
Vasant Estella
possession by Dec 2026 · Shrikrishna Wonder Properties
Navkar Vishwa
possession by Mar 2027 · Abhay Popatlal Dhoka

Other RERA-registered projects in Pune

Sukhakarta Residency
possession by Jun 2027 · Sanjay Raipure
Sukhmani Niwas
declared completion Mar 2024 · M/S Preetam Associates
Sukhshanti Villas
possession by Dec 2030 · Yashant Ventures
Sukhwani Ambar
possession by Jun 2027 · Sukhwani Developers
Sukhwani Artize
possession by Dec 2028 · Sukhwani Buildtech
Sukhwani Celaeno
possession by Dec 2029 · Sukhwani Property Developers Through Pro

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026