Pune/Project record

MahaRERA · the public record

SUNAYA HEIGHTS

NEAR UNNATI DHAM KONDHWA BUDRUK · YASH CONSTRUCTION COMPANY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100020779

Delivery and registration

When is the project declared for completion?

SUNAYA HEIGHTS is registered with MahaRERA as P52100020779 and the promoter has declared completion for 31 Jul 2022.

31 Jul 2022

declared completion

50months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100020779
Registered on09 May 2019
Promoter-declared completion31 Jul 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SUNAYA HEIGHTS record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SUNAYA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SUNAYA HEIGHTS1G+531 Jul 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jan 2022The Project is completed in all aspects but occupancy certificate is yet to be issued. The Applicant had already applied for occupancy certificate and it is still in the process.

Location, Land & Connectivity

Located at NEAR UNNATI DHAM KONDHWA BUDRUK, VENKATESH CLASSIC LANE, Pune City, Pune, 411048. Per the filed land record, the plot is bounded to the north by SR NO 65, to the south by SR NO 66, to the east by SR NO 66 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT8 km
Pune Junction / city centre8 km
Kharadi / EON IT Park12 km
Pune Int'l Airport (Lohegaon)15 km
Baner–Balewadi belt16 km
Hinjewadi Rajiv Gandhi IT Park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Yash Construction Company is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Kondhwa Khurd

Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kapital
possession by Dec 2026 · Ostwal Realty
Akshardham Phase 2
possession by Dec 2026 · Shreyan Ventures
Clover Highlands
possession by Dec 2026 · Clover Developers Pvt Ltd
Hagawane Landmark
Not filing quarterly progress reports · possession by Dec 2026 · Santosh Subhash Hagawane

Major developers building in Kondhwa Khurd

Other RERA-registered projects in Pune

Sunbliss Villa
possession by Dec 2027 · Advika Enterprises
Sunbliss Villa
possession by Dec 2027 · Advika Enterprises
Sundar Shrushti
declared completion Sep 2020 · Ramling Land Developers LLP
Sundar Vihar
declared completion Dec 2023 · Ramling Land Developers LLP
Sunder Moti
declared completion Sep 2025 · Dilip Motilalji Chordia
Sunder Sanskruti Phase 4
possession by Dec 2026 · Suresh Dharmavat AND Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026