THE HERITAGE

P52100024130 · NIBM · promoter Noble Homes

Certificate SignedDue 31 Jul 2023

Delivery & Registration

MahaRERA registrationP52100024130
Registered on21 Jan 2020
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Noble Homes is the promoter of record on 20 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
A1G+831 Dec 2021
B1G+831 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202231 Jul 2023Due to Some unavoidable health and financial issues, we request you to kindly grant extension upto 31/07/2023.

Location, Land & Connectivity

Located at NIBM, NIBM ROAD, Pune City, Pune, 411048. Per the filed land record, the plot is bounded to the north by BY SR NO 4A, to the south by 15 MTRS DP ROAD, to the east by SR NO4A-1A-1-17 and to the west by SR NO 4A-1A-1-19. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kondhwa Bk

Alcon Signare
possession by Jul 2026 · Alcon Builders
Vrundavan Residency
possession by Sep 2026 · Gangai Developers
Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kunj
possession by Nov 2026 · Bace India Developers
THE Latitude - D
possession by Dec 2026 · Ahura Builders

Major developers building in Kondhwa Bk

Other RERA-registered projects in Pune

The Heritage Heights
declared completion Dec 2025 · 2KV Builders AND Developers LLP
THE High Gates
possession by Dec 2026 · PR Associates
THE Hill Side
declared completion Jul 2023 · Manisha Vijay Bajare
The Hillfront
possession by Nov 2026 · Hublikar Constructions
THE Horizon
possession by Dec 2029 · Empire Developers
THE House OF Lords
declared completion May 2019 · THE House OF Lords

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.