MahaRERA Property Intelligence · Pune

TOWN CENTRAL

P52100007390 · NEAR CENTRAL BUILDING · promoter Vaibhav Construction

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP52100007390
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vaibhav Construction is the promoter of record on 60 projects, of which 8 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
TOWN CENTRAL1G+408 Mar 2021

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000009610709/10/2021Prathamesh Ravindra Jadhav vs Nikhil Dattatray Sawantorder passed
CC00500000009612312/10/2021Sarala Ravindra Jadhav vs Nikhil Dattatray Sawantorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202131 Dec 2020We had already applied for part completion certificate with the local body (DAUND MUNCIPAL COUNCIL) ON 27/06/2019 AND AGAIN ON 27/12/2019. On our consistent follow up local body ha
30 Dec 202131 Dec 2020Following are reasons for project delay 1. Delay in execution of R.C.C. work due to differences with contractor regarding payment schedule, faulty workmanship and overall late per

Location, Land & Connectivity

Located at NEAR CENTRAL BUILDING, JANTA COLONY RAILWAY STATION ROAD, Daund, Pune, 413801. Per the filed land record, the plot is bounded to the north by BY CTS NO 2598-8-1 PART, to the south by BY CTS NO 2598 PART ST SEBESTIAN SCHOOL, to the east by By Adjacent Road and to the west by BY CTS NO 2598-7-2-3-4. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~68 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park68 km
Magarpatta / Hadapsar IT69 km
Pune Int'l Airport (Lohegaon)71 km
Pune Junction / city centre75 km
Baner–Balewadi belt85 km
Hinjewadi Rajiv Gandhi IT Park90 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vaibhav Construction is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Daund

Shri Ashtavinayak Park
possession by Oct 2026 · Ajay Builders AND Associates Daund
K K Sundarban Building H
possession by Dec 2026 · K K Developers
Pahal Apartment
possession by Dec 2026 · Prerana Construction
Sai Capital
Not filing quarterly progress reports · possession by May 2027 · Satish Deepak Thorat
R City
possession by Mar 2028 · Reva Construction AND Developers
Vijayraj Apartment
possession by Mar 2028 · S.n. Developers

Major developers building in Daund

Other RERA-registered projects in Pune

Town Square
possession by Sep 2026 · Krupasindhu Developers
Townscapes
possession by Dec 2026 · Gruha Navnirman Housing
Trade Park Phase1
declared completion Dec 2021 · VTP Mohite Associates
Trademark Life
declared completion Dec 2018 · NEW Front Prabhavee Ventures
Tradeparkb
declared completion Jun 2026 · VTP Mohite Associates
Tradeville
declared completion Dec 2023 · Royal Tradville

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026