Triveni Trikaya Phase-1

Tulapur · Sai Balaji Group

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100016958

Delivery and registration

When is the project declared for completion?

Triveni Trikaya Phase-1 is registered with MahaRERA as P52100016958 and the promoter has declared completion for 30 Sep 2025.

30 Sep 2025

declared completion

12months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100016958
Registered on25 Jun 2018
Promoter-declared completion30 Sep 2025
Current statusCertificate Signed
Against todayabout 12 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Triveni Trikaya Phase-1 record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Triveni Trikaya Phase-1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
Wing A21G+9-
Wing B31G+8-
Wing B41G+8-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Triveni Trikaya Phase-1, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000027988424/12/2023Priya Rajkumar Santoshi vs Anup Manik Agarwalorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2025THE PROJECT IS NEARLY COMPLETED ABOUT 95% . TO COMPLETE REMAINING CONSTRUCTION OF THE SAID PROJECT WE NEED EXTENSION TILL DATE 30/09/2025.

Location, Land & Connectivity

Located at Tulapur, Tulapur, Pune City, Pune, 412216. Per the filed land record, the plot is bounded to the north by Amenity Space, to the south by Gat No 513P 515P 516P 525P, to the east by 12 Mtr Wide Internal Road and to the west by Gat No 526. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)12 km
Kharadi / EON IT Park14 km
Magarpatta / Hadapsar IT18 km
Pune Junction / city centre20 km
Baner–Balewadi belt26 km
Hinjewadi Rajiv Gandhi IT Park28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Lonikand

AUM Aangan
Deregistered by MahaRERA · possession by Dec 2026 · Kamdhenu Spaces LLP
Green City
possession by Dec 2026 · Not Available
OXY Flora Phase 3
possession by Dec 2026 · Yogesh Developers
Tulsi Villa
possession by Dec 2026 · Vinod Chandrakant Magar ( Prop. Yashoda
Tulsi Villa
possession by Dec 2026 · MR Rajendra Narayan Kand (yashoda Proper
Suburbia Estate Phase 1
possession by Feb 2027 · SSG Realty AND Infra LLP

Other RERA-registered projects in Pune

Tropez Business Center - Commercial Phase
declared completion Dec 2025 · Mont Vert Associates
Tropica Phase II
declared completion Sep 2024 · Om Developers Project Ravet
Tropica Phase III
declared completion Jul 2022 · Om Developers Project Ravet
Trove
declared completion Sep 2024 · Kalash Properties
TRU Meadows D
possession by Mar 2028 · FAB Five Realty LLP
Trump World Center Pune
possession by Dec 2031 · Enbrick Properties LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026