MahaRERA Property Intelligence · Pune
P52100008711 · promoter Om Developers Project
| MahaRERA registration | P52100008711 |
| Registered on | 19 Aug 2017 |
| Promoter-declared completion | 30 Sep 2024 |
| Current status | Certificate Signed |
| Against today | about 22 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Om Developers Project is the promoter of record on 29 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Building E | 1 | G+13 | 31 Jan 2022 |
| Building F | 1 | G+13 | 31 Jan 2022 |
| Building H | 1 | G+13 | 30 Jul 2020 |
17 complaints are on the MahaRERA record for this project, with orders passed in 17. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000258951 | 02/06/2023 | shirish govind sukhatme vs M/S Om Developer | order passed |
| CC005000000043631 | 06/12/2019 | Barun Kumar Singh vs Atul Ratnakar Mahashabde | order passed |
| CC005000000053901 | 12/01/2020 | Shripad Vijay Katkamwar vs Mr. Atul Ratnakar Mahashabde | order passed |
| CC005000000075122 | 10/06/2021 | Ravi Pant vs Devendra Arvind Awati | order passed |
| CC005000000085413 | 01/04/2021 | Vinay Vasant Bhalerao vs Tropica Phase II ThroughMr. Devendra Awati | order passed |
| CC005000000085421 | 18/04/2021 | Girish Gautam Kate vs Devendra Arvind Awati | order passed |
| CC005000000085681 | 17/01/2022 | Manish Kumar vs Devendra Arvind Awati | order passed |
| CC005000000085667 | 11/06/2021 | Prasad Nandkumar Pagar vs Devendra Arvind Awati | order passed |
| CC005000000106435 | 26/01/2022 | Charudatta Jagannath Andhare vs Atul Ratnakar Mahashabde, Devendra Arvind Awati (M/S OM developers) | order passed |
| CC005000000106441 | 05/03/2022 | Suhas Deshmukh vs Ravishankar Shashikant Sahasrabuddhe | order passed |
| CC005000000106507 | 19/01/2022 | Himanshu Gambhire vs OM Developer Through Promoter Mr. Atul Mahashabde | order passed |
| CC005000000106665 | 08/03/2022 | Rupesh Dhule vs Devendra Awati, Atul Mahashabhde | order passed |
| CC005000000106667 | 08/03/2022 | Srikakolapu Venkata Mohana Krishna vs Devendra Awati, Atul Mahashabde | order passed |
| CC005000000106855 | 28/03/2022 | Lalit Rade vs Atul Ratnakar Mahashabde | order passed |
| CC005000000279839 | 10/12/2023 | Navnath Vitthal Bhise vs Mr. Devendra Arvind Awati | order passed |
| CC005000000279942 | 25/12/2023 | SUNIL SHANKARRAO BANDAL vs DEVENDRA ARVIND AWATI | order passed |
| CC005000000289971 | 29/12/2023 | Nikhil Anil Golande vs Devendra Auti | order passed |
The promoter has declared 3 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Karande Court | 1366 | 2015 | Pending For Evidence |
| Bhosale Court | 2246 | 2014 | Hearing Before Charge |
| Paldewar Court | 994 | 2012 | Argument On Exhibit |
The promoter has had the MahaRERA completion deadline formally extended 5 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Sep 2024 | 30 Jul 2022 | DUE TO COVID SUFFER FINACIAL CRUNCH AND NO NEW BOOKING . |
| 30 Sep 2024 | 31 Jul 2023 | WE ARE UNABLE TO COMPLETE WHITEN SAID TIME PERIOD ,BECAUSE COVID EFFECT ON OUR PROJECT & TODAYS LABOUR COST ,MATERIEL COST RISE .SO PLEASE EXTENSION OUR RERA COMPLETION DATE. |
| 30 Sep 2024 | 31 Jul 2021 | DUE TO PANDAMIC LABOUR SHORTAGE WE COULD NOT ACHIEVE COMPLETION STAGE. OUT OF 3 BUILDINGS WE HAVE COMPLETED ONE BUILDING i.e.H Building.Applying for completion. We have completed r |
| 30 Sep 2024 | 30 Apr 2022 | DUE TO PANDAMIC LABOUR SHORTAGE WE COULD NOT ACHIEVE COMPLETION STAGE. OUT OF 3 BUILDINGS WE HAVE COMPLETED ONE BUILDING i.e.H Building.Applying for completion. We have completed r |
| 30 Sep 2024 | 30 Sep 2024 | SOME OUR FINANCIAL ISSUE BECAUSE WE ARE CLOSED IIFL CONSTRUCTION LOAN & CUSTOMER BOOKING ARE VERY DOWN THERE IS WE ARE UNABLE COMPLETE OUR PROJECT. |
Located at Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by 18 DP road and S No 58-2, to the south by 18 DP Road and S No 56-2 and 54, to the east by S No 59 and 53 and 56-2 and to the west by 58-1 part and 57-1B part and 56-1A part. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 7 km |
| Baner–Balewadi belt | 11 km |
| Pune Junction / city centre | 20 km |
| Pune Int'l Airport (Lohegaon) | 21 km |
| Kharadi / EON IT Park | 25 km |
| Magarpatta / Hadapsar IT | 25 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Tropica Phase II?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Om Developers Project Ravet is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026