31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100017054

Delivery and registration

When is the project declared for completion?

UMA DARSHAN PHASE II is registered with MahaRERA as P52100017054 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100017054
Registered on05 Jul 2018
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for UMA DARSHAN PHASE II record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Vighnahar Developers is the promoter of record on 49 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

49projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for UMA DARSHAN PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
B1G+830 Jun 2022
C1G+930 Jun 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2025The current spread of Coronavirus disease (COVID-19) has created a serious impact on the social and economic life not only in the State of Uttar Pradesh but for whole of the count

Location, Land & Connectivity

Located at RAJGURUNAGAR, WADA ROAD, Khed, Pune, 410505. Per the filed land record, the plot is bounded to the north by MILKAT OF NARAYAN SANDBHOR, to the south by WADA ROAD, to the east by MILKAT OF SUNIL GHUMATKAR and to the west by 142 1 OF KALURAM SANDBHOR. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rajgurunagar

Kohinoor Heights
possession by Oct 2026 · Abbas Ayub Ansari
Shree Paradise
possession by Oct 2026 · Sunita Ashutosh Gosavi
Rajashri Apartments
possession by Oct 2026 · Omkar Sanjay Thigale
Classic Amrut
possession by Oct 2026 · Classic Infra
Mahalaxmi Heights
possession by Dec 2026 · Mahalaxmi Developers
Aryaa Dream Town
possession by Dec 2026 · Vini Builders AND Developers

Major developers building in Rajgurunagar

Other RERA-registered projects in Pune

Umakant Enclave
possession by Dec 2029 · Mayuresh Constructions
Umang Pride - Building C
declared completion Feb 2025 · Corolla Gulmohar
Umar Residency
declared completion May 2022 · Umar Builders AND Developers
Umashankar Prasad
possession by Feb 2028 · Ranjekar Realty LLP
UNI 89 Wing B
possession by Dec 2029 · Mundhwa Infra LLP
UNI 89 Wing C
possession by Dec 2029 · Mundhwa Infra LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026