30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014555

Delivery and registration

When is the project declared for completion?

Urban Park is registered with MahaRERA as P52100014555 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014555
Registered on12 Dec 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Urban Park record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Urban Developers is the promoter of record on 98 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

98projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Urban Park in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Urban Park1G+1431 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Kirkatwadi, Nandoshi Road, Pune City, Pune, 411024. Per the filed land record, the plot is bounded to the north by GAT NO 332 PART 333 PART, to the south by GAT NO 333 PART, to the east by GAT NO 331 and to the west by 15 M WIDE PROPOSED ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Junction / city centre13 km
Baner–Balewadi belt13 km
Magarpatta / Hadapsar IT16 km
Hinjewadi Rajiv Gandhi IT Park18 km
Kharadi / EON IT Park20 km
Pune Int'l Airport (Lohegaon)21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kirkatwadi

Malhar Heights
possession by Sep 2026 · Ganesh Shrirang Khengre
Skyi Star City Phase IV
possession by Mar 2027 · Skyi Property Ventures LLP
Chaitrangan Phase II
possession by May 2027 · Dedge Housing Development LLP
Skyi Star City Phase VII
possession by May 2027 · Skyi Property Ventures LLP
Skyi City Centre
possession by Jun 2027 · Skyi Property Ventures LLP
Laxmi Puram
possession by Sep 2027 · Not Available

Other RERA-registered projects in Pune

Urban Reviva
possession by Dec 2027 · M/s Urban Cityscapes LLP
Urban Skyline Phase II
possession by Dec 2027 · M/s Urban Space Creators
Urbanbrick Castle
declared completion Dec 2025 · Urbanbrick Developers LLP
Urbanbrick Castle Phase 2
possession by Dec 2028 · Urbanbrick Developers LLP
Urbanbrick Vista PH-1
possession by Dec 2030 · Mohar Omkar Associates LLP
Urbanbrick Vista PH-2
possession by Dec 2030 · Mohar Omkar Associates LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026