Pune/Project record

MahaRERA · the public record

VARAD COMPLEX

PUNE · Suprabhat Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

82units filed as unsoldInventory · 17 September 2026
28 Feb 2028declared completionMahaRERA registration · read 12 Jul 2026
92registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Feb 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100029105

Delivery and registration

When is the project declared for completion?

VARAD COMPLEX is registered with MahaRERA as P52100029105 and the promoter has declared completion for 28 Feb 2028.

28 Feb 2028

declared completion

17months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100029105
Registered on26 Apr 2021
Promoter-declared completion28 Feb 2028
Current statusCertificate Signed
Against today17 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VARAD COMPLEX record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Suprabhat Constructions is the promoter of record on 6 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In VARAD COMPLEX, ₹6.21 Cr of a declared ₹11.00 Cr estimated project cost is reported as incurred, about 56.4%, as at the last certified filing with MahaRERA.

56.4%

₹6.21 Cr

of ₹11.00 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In VARAD COMPLEX, 5 of 88 homes filed with MahaRERA are recorded as sold or booked, about 6%, and 83 remain available.

6%sold

5 of 88 homes

₹1.76 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹1.41 Cr (about 80%) is recorded as collected and ₹35.63 Lakh as receivable. The project registers 92 homes in total, while this sold/unsold inventory filing covers 88 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 5 registered agreements, the effective carpet rate is ₹8,463/sqft, with eight in ten falling between ₹7,949 and ₹8,838 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 4 reserved.

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 6 homes carry one, and 82 of the 92 are recorded unsold. Since we started watching this ledger, 1 home has moved out of the unsold list, most recently on 09 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
101448 sqftRs 8,463 a sq ft typical, over Rs 7,949 to Rs 8,5945 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In VARAD COMPLEX, 44 of the 82 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 81 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 92 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING A WING A AND B1G+43228 Feb 2028
AMENITY BUILDING1G+4428 Feb 2028
BUILDING B1G+43228 Feb 2028
BUILDING C1G+42428 Feb 2028

Unit mix on the filing: 88 residential and 4 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for VARAD COMPLEX, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250259928/07/2025Subhash Bansilal Late vs UGAM REALITY LLPorder passed
CC1250260028/07/2025Subhash Bansilal Late vs UGAM REALITY LLPorder passed

Location, Land & Connectivity

Located at PUNE, DHAYARI, Pune City, Pune, 411041. Per the filed land record, the plot is bounded to the north by BY ROAD AND PROPERTY OF NIVRUTI BENKAR, to the south by BY PROPERTY OF DNYANOBA KISAN BENKAR, to the east by S NO 5-6 S NO 5-8 and to the west by S NO 2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8271 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park8271 km
Baner–Balewadi belt8275 km
Pune Junction / city centre8285 km
Magarpatta / Hadapsar IT8290 km
Pune Int'l Airport (Lohegaon)8290 km
Kharadi / EON IT Park8292 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhayari

Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Majestique Swapnangan Wing A And Wing B
possession by Sep 2026 · Majestique Horizon LLP
Tridal Samruddhi
possession by Sep 2026 · M/s. Tridal Associates
Vasant Vihar A Wing
possession by Sep 2026 · A R Developers
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Navjyot Abha Phase II B And D
Not filing quarterly progress reports · possession by Dec 2026 · Sumeru Buildcon Private Limited

Major developers building in Dhayari

Other RERA-registered projects in Pune

Varad Dwarka
possession by Dec 2028 · Varad Realty
Varad Heights
possession by Dec 2027 · Sachin Vijay Gadhave
Varad Phase II
declared completion Jan 2020 · M/s. Jadhav Builders AND Developers
Varad Residency
declared completion Jan 2021 · Vrushali Vijay Deshmukh
Varad Residency
declared completion May 2022 · Shriram Properties
Varad Residency
declared completion Sep 2026 · Vilas Bhagaji Arekar

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026