MahaRERA Property Intelligence · Pune

Varad Shubharambha

P52100020816 · behind ISKCON Temple · promoter Dnyaneshwar Sarode

Certificate SignedDue 30 Oct 2020

Delivery & Registration

MahaRERA registrationP52100020816
Registered on10 May 2019
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Dnyaneshwar Sarode is the promoter of record on 39 projects, of which 6 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Varad Shubharambh1G+431 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at behind ISKCON Temple, katraj kondhwa road, Haveli, Pune, 411048. Per the filed land record, the plot is bounded to the north by sr no 50 Part, to the south by sr no 50 part, to the east by Sr no 50 part and to the west by Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~42 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Baner–Balewadi belt42 km
Hinjewadi Rajiv Gandhi IT Park43 km
Pune Junction / city centre47 km
Magarpatta / Hadapsar IT51 km
Kharadi / EON IT Park54 km
Pune Int'l Airport (Lohegaon)55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kondhwa Bk

Alcon Signare
possession by Jul 2026 · Alcon Builders
Vrundavan Residency
possession by Sep 2026 · Gangai Developers
Krushna Chayya
possession by Sep 2026 · Shree Mahalaxmi Builder AND Developars
Majestic Pride
possession by Oct 2026 · Anwar Mahmoo Shaikh
Krishna Kunj
possession by Nov 2026 · Bace India Developers
THE Latitude - D
possession by Dec 2026 · Ahura Builders

Major developers building in Kondhwa Bk

Other RERA-registered projects in Pune

Varad Sukriti
declared completion Apr 2019 · Neha Dream Homes LLP
Varad Tanusha
declared completion May 2025 · Varad Associates
Varad Vastu
declared completion Dec 2017 · Sharad Kharade
Varad Vihar
declared completion Dec 2019 · Shree Developers
Varad Vinayak
declared completion Dec 2019 · Aditya Laxmikant Joshi
Varad Vinayak Residency
possession by Mar 2027 · Ajay Balkrishna Shahane

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026