VENKATESH SKYDALE PHASE 1

P52100021836 · Hingane Khurd, Sinhagad Rd · promoter Shree Venkatesh Buildcon

Certificate SignedDue 30 Mar 2024

Delivery & Registration

MahaRERA registrationP52100021836
Registered on31 Jul 2019
Promoter-declared completion30 Mar 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Venkatesh Buildcon is the promoter of record on 146 projects, of which 26 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+26.

BuildingWingsFloorsDeclared completion
C BUILDING1G+2630 Mar 2024

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000010664515/03/2022Vijay Dhondopant Charolkar vs Venkatesh Buildcon Pvt. Ltdorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil3822021Pending

Location, Land & Connectivity

Located at Hingane Khurd, Sinhagad Rd, Sr No 20, Hissa No. 1, Plot H, Pune City, Pune, 411051. Per the filed land record, the plot is bounded to the north by Adjoining B Building, to the south by Adjoining Nala, to the east by 12 Mtr Internal Driveway and to the west by Internal Driveway adjoining Green Belt B Reservatn. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre7 km
Baner–Balewadi belt10 km
Magarpatta / Hadapsar IT11 km
Kharadi / EON IT Park14 km
Pune Int'l Airport (Lohegaon)15 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Venkatesh Buildcon is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Shree Venkatesh Buildcon project & its RERA track record →

Other flagged projects by Shree Venkatesh Buildcon

Shree Venkatesh Buildcon
FlaggedPune
Shree Venkatesh Buildcon
FlaggedPune
Shree Venkatesh Buildcon
FlaggedPune

Other RERA-registered projects in Hingane Khurd

Sai Ganesh Vihar D Wing
possession by Nov 2026 · Jayshree Developers
Aura Waters Phase -I
possession by Dec 2026 · Ranawat Properties
Sunder Srushti Wing D6
possession by Dec 2026 · Suresh Dharmavat AND Associates
Kanchan Heights
possession by Apr 2027 · Orbiz Estate
Venkatesh Skydale Phase 4
possession by Jun 2027 · Shree Venkatesh Buildcon
Park Life Wing C
possession by Mar 2028 · Kudale Patil AND Jadhav Ventures

Other RERA-registered projects in Pune

Venkatesh Skydale Phase 2
declared completion Dec 2025 · Shree Venkatesh Buildcon
Venkatesh Skydale Phase 3
declared completion Jun 2026 · Shree Venkatesh Buildcon
Venkatesh Skydale Phase 4
possession by Jun 2027 · Shree Venkatesh Buildcon
Venkatesh Skylife
possession by Mar 2029 · Shree Venkatesh Spaces
Venkatesh Skyline
possession by Dec 2028 · Bhagwati Enterprises
Venkatesh Solid
declared completion Jun 2026 · Abhishekh Sanjay Jagtap

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026