VIRAJ HEIGHTS

DHANORI · VENKATESH DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Aug 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Aug 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100026384

Delivery and registration

When is the project declared for completion?

VIRAJ HEIGHTS is registered with MahaRERA as P52100026384 and the promoter has declared completion for 31 Aug 2023.

31 Aug 2023

declared completion

37months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100026384
Registered on16 Sep 2020
Promoter-declared completion31 Aug 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VIRAJ HEIGHTS record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Venkatesh Developers is the promoter of record on 161 projects registered with MahaRERA, 27 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

161projects

registered with MahaRERA

27flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VIRAJ HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
VIRAJ HEIGHTS1G+1131 Aug 2023

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for VIRAJ HEIGHTS, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1240002704/09/2024Rajesh Durgadas Nadkarni vs VENKATESH DEVELOPERSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2023Due to Covid 19 Situation We are not able to do Civil Work During the F.Y. 2020-2021 and part year of F.Y. 2021-2022. Thus we kindly request you to extend our project date completi

Location, Land & Connectivity

Located at DHANORI, DHANORI ROAD, Pune City, Pune, 411015. Per the filed land record, the plot is bounded to the north by S NO 20 PART AND 24 METER ROAD, to the south by S NO 20 PART, to the east by S NO 20 PART and to the west by S NO 20 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park34 km
Baner–Balewadi belt34 km
Pune Junction / city centre41 km
Magarpatta / Hadapsar IT45 km
Pune Int'l Airport (Lohegaon)48 km
Kharadi / EON IT Park48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Venkatesh Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Dhanori

Murli Manohar Heights
possession by Sep 2026 · Padmanabh Associates
Yash Grecia- E Wing
possession by Sep 2026 · Akshay Enterprises
Aaiji Crystal Phase I
possession by Oct 2026 · Aaiji Developers
Aaiji Crystal Phase II
possession by Oct 2026 · Aaiji Developers
Galaxy Co-Operative Housing Society Ltd
possession by Oct 2026 · Yash Developers
Austin
possession by Dec 2026 · Krishna Venture Skyscraper LLP

Major developers building in Dhanori

Other RERA-registered projects in Pune

Viraj Sequoia
declared completion Dec 2023 · Sequoia Realty LLP
Virtu
declared completion Jun 2026 · THE Excellaa
Vishal Apartment
declared completion Dec 2025 · Vijay Shankar Inamdar
Vishal Capital
declared completion Jun 2023 · Mahendra Mayaram Pardeshi
Vishal Complex E Wing
possession by Mar 2027 · Vishal Chordiya Constructions Private Li
Vishal Heights
declared completion Dec 2023 · Balaji Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026