Vishal Heights

P52100013728 · promoter Balaji Builders

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP52100013728
Registered on25 Oct 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Existing Structure1G+0-
Vishal Heighs A-wing1G+3-
Vishal Heights B-wing1G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202330 Dec 2022Due to Economical slow down in market flat and shops shall not booked by customer so the work has been stopped due to financial problem.

Location, Land & Connectivity

Located at Haveli, Pune, 411021. Per the filed land record, the plot is bounded to the north by Ramnagar Colony, to the south by Tapowan Society, to the east by NDA Road and to the west by Ramnagar Colony. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt4 km
Hinjewadi Rajiv Gandhi IT Park9 km
Pune Junction / city centre10 km
Magarpatta / Hadapsar IT16 km
Pune Int'l Airport (Lohegaon)16 km
Kharadi / EON IT Park17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Balaji Builders is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Balaji Builders

Other RERA-registered projects in Bavdhan

Window Cooperative Housing Society Limited 131/1
possession by Jul 2026 · Windows Co-Operative Housing Society Ltd
Rising Hills
possession by Aug 2026 · Not Available
Purva Aspire
possession by Sep 2026 · Puravankara Limited
Marvel Selva Ridge Villa 6, 9, 11, 12
Developer in insolvency (NCLT) · possession by Dec 2026 · Marvel Omega Builders PVT LTD
Reelicon Fairy Bell
possession by Dec 2026 · Reelicon Red Homes Private Limited
Green Mint
possession by Dec 2026 · Sunil Vishwanath Salunke

Major developers building in Bavdhan

Other RERA-registered projects in Pune

Vishal Leela Residency
declared completion Dec 2025 · Sopan Gahinaji Lanke
Vishal Vishwa Phase 2 - Building Number 1 AND 2
declared completion Dec 2020 · Vishal Constructions
Vishal Vishwa Phase 2 - Building Number 3
declared completion Dec 2021 · Vishal Constructions
Vishal Viviana
declared completion Dec 2022 · Vishal Realtors
Vishalata Nisarg
declared completion Feb 2025 · V. S. Bondre Developers (promoters &
Vishalleela Residency
possession by Mar 2027 · S.g.lanke Construction CO

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026