Hastipuram

Bibvewadi · Balaji Builders

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100078256

Delivery and registration

When is the project declared for completion?

Hastipuram is registered with MahaRERA as P52100078256 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100078256
Registered on29 Nov 2024
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Hastipuram record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Construction

How much construction cost has been reported?

In Hastipuram, ₹7.35 Cr of a declared ₹28.34 Cr estimated project cost is reported as incurred, about 25.9%, as at the last certified filing with MahaRERA.

25.9%

₹7.35 Cr

of ₹28.34 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Hastipuram in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
A Wing1G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Bibvewadi, CTS No. 843, S No 669/1A & 669/1B, Haveli, Pune, 411037. Per the filed land record, the plot is bounded to the north by Survey No669 Part, to the south by Survey No671 Part, to the east by 36 M W D P Road and to the west by Survey No669 part andInternal Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre7 km
Magarpatta / Hadapsar IT8 km
Kharadi / EON IT Park12 km
Baner–Balewadi belt14 km
Pune Int'l Airport (Lohegaon)14 km
Hinjewadi Rajiv Gandhi IT Park19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Balaji Builders is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Balaji Builders project & its RERA track record →

Other flagged projects by Balaji Builders

Balaji Builders
Past its declared completion datePune

Other RERA-registered projects in Bibwewadi

Osian Navkar
possession by Sep 2026 · Osian Realty
ONE Prabhat
possession by Oct 2026 · S Square Reality LLP
Aura Divine
possession by Dec 2026 · Ranawat Realtors
Suyog Navkaar Phase I
possession by Dec 2026 · Suyog Development Corporation Unit 12 LL
Hill Town A B AND C Wing
possession by Dec 2026 · Hill Town Constructions
Osian Divino
possession by Dec 2026 · Osian Realty

Major developers building in Bibwewadi

Other RERA-registered projects in Pune

Hatimi Hills Phase I Building D
declared completion Dec 2025 · Pyramid Infrastructure
Hatimi Hills Phase II Building E
declared completion Jun 2024 · Pyramid Infrastructure
Hatimi Plaza
declared completion Dec 2024 · Pyramid Infrastructure
Haute Capital
possession by Jan 2027 · Sujay Shirish Bhansali
Hazel View
declared completion Nov 2020 · Shiv Associates
Heera Mansion
possession by Dec 2026 · Ambalal And Sons

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026