Pune/Project record

MahaRERA · the public record

PARK LANDMARK PHASE III

BIBWEWADI · Pride Purple Landmark LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100047206

Delivery and registration

When is the project declared for completion?

PARK LANDMARK PHASE III is registered with MahaRERA as P52100047206 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100047206
Registered on11 Oct 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARK LANDMARK PHASE III record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Pride Purple Landmark is the promoter of record on 23 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

23projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PARK LANDMARK PHASE III in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
PARK LANDMARK PHASE III C BUILDING1G+15-
PARK LANDMARK PHASE III D BUILDING1G+15-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BIBWEWADI, BIBWEWADI, Pune City, Pune, 411037. Per the filed land record, the plot is bounded to the north by PART OF SAME LAYOUT, to the south by PART OF SAME LAYOUT, to the east by PART OF SAME LAYOUT and to the west by PART OF SAME LAYOUT. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pride Purple Landmark LLP is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Bibwewadi

Osian Navkar
possession by Sep 2026 · Osian Realty
ONE Prabhat
possession by Oct 2026 · S Square Reality LLP
Aura Divine
possession by Dec 2026 · Ranawat Realtors
Suyog Navkaar Phase I
possession by Dec 2026 · Suyog Development Corporation Unit 12 LL
Hastipuram
possession by Dec 2026 · Balaji Builders
Hill Town A B AND C Wing
possession by Dec 2026 · Hill Town Constructions

Major developers building in Bibwewadi

Other RERA-registered projects in Pune

Park Life Wing C
possession by Mar 2028 · Kudale Patil AND Jadhav Ventures
Park Life Wing D
possession by Mar 2030 · Not Available
Park Marina Building B And C
declared completion Mar 2019 · Sujay Associates
Park Pebbles Phase I
possession by Jun 2030 · M/s Rainbow Purple Construction LLP
Park Titan
declared completion Jun 2026 · Pride Purple Infrastructure
Park Titan Phase II
declared completion Jun 2026 · Pride Purple Infrastructure

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026