Pune/Project record

MahaRERA · the public record

Mont Vert Velocity

Pashan · Niraj Kumar Associates Pvt Ltd

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100001973

Delivery and registration

When is the project declared for completion?

Mont Vert Velocity is registered with MahaRERA as P52100001973 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100001973
Registered on31 Jul 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Mont Vert Velocity record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Niraj Kumar Associates is the promoter of record on 35 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

35projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Mont Vert Velocity in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Mont Vert Velocity1G+1331 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019The major obstacle faced was as a result of changes in DC rules in PMC. The new DC rules for Pune came into effect in Dec 2016 however it is a well-known fact that there was an unc

Location, Land & Connectivity

Located at Pashan, Baner-Pashan Link Rd, Haveli, Pune, 411021. Per the filed land record, the plot is bounded to the north by CTS No 1623 pt, to the south by CTS 1182 pt and 1183 pt, to the east by Part S No 140 HN 1A and to the west by S No 130. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt2 km
Hinjewadi Rajiv Gandhi IT Park8 km
Pune Junction / city centre9 km
Pune Int'l Airport (Lohegaon)14 km
Magarpatta / Hadapsar IT15 km
Kharadi / EON IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Niraj Kumar Associates Pvt Ltd is the promoter on 7 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Niraj Kumar Associates Pvt Ltd

Niraj Kumar Associates Pvt Ltd
FlaggedPune
Niraj Kumar Associates Pvt Ltd
FlaggedPune
Niraj Kumar Associates Pvt Ltd
FlaggedPune

Other RERA-registered projects in Bavdhan

Purva Aspire
possession by Sep 2026 · Puravankara Limited
Marvel Selva Ridge Villa 6, 9, 11, 12
Developer in insolvency (NCLT) · possession by Dec 2026 · Marvel Omega Builders PVT LTD
Reelicon Fairy Bell
possession by Dec 2026 · Reelicon Red Homes Private Limited
Green Mint
possession by Dec 2026 · Sunil Vishwanath Salunke
Neelanchal Phase I
Not filing quarterly progress reports · possession by Dec 2026 · Pinnacle Vastunirman Pvt. Ltd
Neelanchal Phase II
possession by Dec 2026 · Pinnacle Vastunirman Pvt. Ltd

Major developers building in Bavdhan

Other RERA-registered projects in Pune

Mont Vert Vesta
declared completion Dec 2019 · Mont Vert Estates
Mont Vert Yolo
declared completion Dec 2022 · Mont Vert Elegance
Montage
possession by Dec 2026 · Golden Kalash Housing LLP
Montaire
possession by Dec 2029 · Atrium Landmarks LLP
Monte Karla
possession by Dec 2029 · Goodbrick Realty Private Limited
Montreal - A-B-C-D
possession by Dec 2027 · Charholi Infrastructure LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026