Pune/Project record

MahaRERA · the public record

VISION 7 - PHASE I

pune · SHREE VISION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

110units filed as unsoldInventory · 13 September 2026
30 Jan 2027declared completionMahaRERA registration · read 12 Jul 2026
203registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100005128

Delivery and registration

When is the project declared for completion?

VISION 7 - PHASE I is registered with MahaRERA as P52100005128 and the promoter has declared completion for 30 Jan 2027.

30 Jan 2027

declared completion

4months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100005128
Registered on09 Aug 2017
Promoter-declared completion30 Jan 2027
Current statusCertificate Signed
Against today4 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VISION 7 - PHASE I record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Shree Vision is the promoter of record on 180 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

180projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In VISION 7 - PHASE I, 93 of 203 homes filed with MahaRERA are recorded as sold or booked, about 46%, and 110 remain available.

46%sold

93 of 203 homes

₹45.38 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹20.97 Cr (about 46%) is recorded as collected and ₹24.41 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 93 registered agreements, the effective carpet rate is ₹16,930/sqft, with eight in ten falling between ₹13,040 and ₹28,674 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 93 homes carry one, and 110 of the 203 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
SHOP-124277 sqftRs 42.00 lakh typical, over Rs 39.00 lakh to Rs 95.06 lakh9 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In VISION 7 - PHASE I, 74 of the 110 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 109 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 203 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Vision 7 - Phase I1G+5203-

Unit mix on the filing: 203 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

10 complaints are on the MahaRERA record for VISION 7 - PHASE I, with orders passed in 9 of them.

10complaints

9with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000027995130/12/2023Gajanan Govindwar vs Rajeshkumar naupatlal Saklaorder passed
CC00500000034086204/05/2024Praveen Kumar Verma vs Rajeshkumar Naupatlal Saklaorder passed
CC1240019123/09/2024Pramila Balasaheb Avhad vs SHREE VISIONorder passed
CC1240042416/10/2024SACHIN SHARAD SALVE vs SHREE VISIONorder passed
CC1240036707/10/2024Pramila Balasaheb Avhad vs SHREE VISIONorder passed
CC1240036907/10/2024Pramila Balasaheb Avhad vs SHREE VISIONorder passed
CC1250033030/01/2025PRAMILA DILIP BAMBALE vs SHREE VISIONorder passed
CC1250256125/07/2025Rekha Sanjay Bansal vs SHREE VISIONorder passed
CC1260007205/01/2026Swapnil Ashokrao Ishware vs SHREE VISIONorder passed
CC1260280514/05/2026SHREE VISION vs SUNIL HOTCHAND RAMWANIpending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
District And Sessions Courtcommercial suit/ 01/20262026Ongoing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jul 2020Constructions of the project is almost complete but common area and facilities are under development which we will complete within 12 months.
30 Jul 202029 Jan 2023Project is completed to the tune of 75%, almost 73% of the allottees have given their consent for extension of the project.
29 Jan 202330 Jan 2025We have already completed the floors which we have sold/allotted to allottee(s)/Customer(s), we have already in-warded the application for NOC(s) from Drainage and Fire in respecti
30 Jan 202530 Jan 2027The project has encountered unforeseen challenges that have significantly impacted its timeline and progress. These challenges include: 1. Severe Labor Shortage: o The project ha

Location, Land & Connectivity

Located at pune, pune, Pune City, Pune, 411027. Per the filed land record, the plot is bounded to the north by Jarvani Society, to the south by 18 mtr wide road, to the east by Sai Platinum Society and to the west by 18 mtr wide road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre2 km
Magarpatta / Hadapsar IT5 km
Kharadi / EON IT Park8 km
Pune Int'l Airport (Lohegaon)9 km
Baner–Balewadi belt12 km
Hinjewadi Rajiv Gandhi IT Park17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pimple Nilakh

Sai Neel
possession by Sep 2026 · Vishal Anil Khairnar
Marigold Calendula
possession by Sep 2026 · Audumbar Homes LLP
Sai Aura
possession by Sep 2026 · WJV Landmarks LLP
Sky 2 Cosmos
possession by Oct 2026 · Emperos Properties
Vimal Twin Tower A Wing
possession by Oct 2026 · Kate Promoters & Developers
Yashoda Heights
possession by Nov 2026 · Paras Shivajirao Dhore

Major developers building in Pimple Nilakh

Other RERA-registered projects in Pune

Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE
Vision Altia
possession by Dec 2026 · Vision Creative Buildcon LLP
Vision Boulevard - Phase I
declared completion Mar 2018 · Vision Homes Project
Vision Boulevard - Phase II
declared completion Jun 2022 · Vision Home Project
Vision Classic
declared completion Dec 2025 · M K Developers
Vision Ekaan
possession by Dec 2027 · Vision Creative Spaces

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026