VISION BOULEVARD - Phase II

Pimple Saudagar · VISION HOME PROJECT

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100018670

Delivery and registration

When is the project declared for completion?

VISION BOULEVARD - Phase II is registered with MahaRERA as P52100018670 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100018670
Registered on27 Nov 2018
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VISION BOULEVARD - Phase II record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vision Home Project is the promoter of record on 180 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

180projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VISION BOULEVARD - Phase II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
F WING1G+631 Dec 2019
E WING1G+631 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022Project is almost complete but we require 12 months extension to get OC/CC, Kindly grant us extension.

Location, Land & Connectivity

Located at Pimple Saudagar, Pimpale Saudagar, Pune City, Pune, 411027. Per the filed land record, the plot is bounded to the north by 18 M WIDE ROAD, to the south by CTS 688, to the east by CTS NO 687 and to the west by CTS NO 646 647. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pimple Nilakh

Sai Neel
possession by Sep 2026 · Vishal Anil Khairnar
Marigold Calendula
possession by Sep 2026 · Audumbar Homes LLP
Sai Aura
possession by Sep 2026 · WJV Landmarks LLP
Sky 2 Cosmos
possession by Oct 2026 · Emperos Properties
Vimal Twin Tower A Wing
possession by Oct 2026 · Kate Promoters & Developers
Yashoda Heights
possession by Nov 2026 · Paras Shivajirao Dhore

Major developers building in Pimple Nilakh

Other RERA-registered projects in Pune

Vision Classic
declared completion Dec 2025 · M K Developers
Vision Ekaan
possession by Dec 2027 · Vision Creative Spaces
Vision Exotica
possession by Oct 2026 · Vision Avis Groups
Vision Exotica Phase-II
possession by Dec 2026 · Vision Avis Groups
Vision Flora
declared completion Apr 2026 · Siddhivinayak Namrata Developers
Vision Gallaria
declared completion Jul 2022 · Siddhivinayak Kohinoor Ventures

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026