21units filed as unsoldInventory · 18 September 2026
31 Jul 2027declared completionMahaRERA registration · read 12 Jul 2026
29registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100046523

Delivery and registration

When is the project declared for completion?

YASH NANDA is registered with MahaRERA as P52100046523 and the promoter has declared completion for 31 Jul 2027.

31 Jul 2027

declared completion

10months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100046523
Registered on10 Aug 2022
Promoter-declared completion31 Jul 2027
Current statusCertificate Signed
Against today10 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for YASH NANDA record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Construction

How much construction cost has been reported?

In YASH NANDA, ₹3.59 Cr of a declared ₹9.37 Cr estimated project cost is reported as incurred, about 38.3%, as at the last certified filing with MahaRERA.

38.3%

₹3.59 Cr

of ₹9.37 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In YASH NANDA, 8 of 29 homes filed with MahaRERA are recorded as sold or booked, about 28%, and 21 remain available.

28%sold

8 of 29 homes

₹1.29 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹55.30 Lakh (about 43%) is recorded as collected and ₹73.67 Lakh as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 8 registered agreements, the effective carpet rate is ₹3,795/sqft, with eight in ten falling between ₹3,000 and ₹9,157 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 11011,033 sqft (95.96 sqm)-
Floor 1102573 sqft (53.27 sqm)-
Floor 1Yashnanda640 sqft (59.43 sqm)-
Floor 22011,033 sqft (95.96 sqm)-
Floor 2202573 sqft (53.27 sqm)-
Floor 2203507 sqft (47.14 sqm)-
Floor 33011,693 sqft (157.31 sqm)-
Floor 3303341 sqft (31.69 sqm)-
Floor 3305340 sqft (31.55 sqm)-
Floor 44011,729 sqft (160.61 sqm)-
Floor 55011,729 sqft (160.61 sqm)-
Floor 66011,729 sqft (160.61 sqm)-
Floor 6603341 sqft (31.69 sqm)-
Floor 6604339 sqft (31.46 sqm)-
Floor 6605340 sqft (31.55 sqm)-
Ground/Floor 0Office656 sqft (60.92 sqm)-
Ground/Floor 0Shop 01592 sqft (55.03 sqm)-
Ground/Floor 0Shop 2296 sqft (27.5 sqm)-
Ground/Floor 0Shop 3471 sqft (43.79 sqm)-
Ground/Floor 0Shop 4454 sqft (42.15 sqm)-
Ground/Floor 0Shop 5398 sqft (37 sqm)-

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 8 homes carry one, and 21 of the 29 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
604339 sqftRs 31.01 lakh typical, over Rs 10.16 lakh to Rs 31.01 lakh3 filed on this stack, floors 3–5

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In YASH NANDA, 5 of the 21 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 20 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 29 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
YASH NANDA1G+729-

Unit mix on the filing: 22 residential and 7 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2027Revised sanction plan due to regulatory compliance and construction work in progress as per revised plan

Location, Land & Connectivity

Located at SHUKRAWAR PETH, SHUKRAWAR PETH, Haveli, Pune, 411002. Per the filed land record, the plot is bounded to the north by PUBLIC ROAD, to the south by PUBLIC LANE, to the east by CTS NUMBER 202 SHUKRAWAR PETH PUNE and to the west by PUBLIC ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre3 km
Magarpatta / Hadapsar IT7 km
Kharadi / EON IT Park10 km
Baner–Balewadi belt10 km
Pune Int'l Airport (Lohegaon)11 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shukrawar Peth

Kawal Arcade
possession by Sep 2026 · Sethi Greenscape Venture
Samasta Barajati Gujarathi Mahajan
possession by Sep 2026 · Shri Samasta Barajatis Gujrati Mahajan
Dhanlaxmi Market
possession by Dec 2026 · Dhanlaxmi Infra
Aakankssha Sanskruti
possession by Dec 2026 · Aakankssha Developer
Anand
possession by Dec 2026 · Lagoo Apte Properties Private Limited
Giriraj Residency
possession by Dec 2026 · Atul Constructions

Major developers building in Shukrawar Peth

Other RERA-registered projects in Pune

Yash Paradise
declared completion Jul 2023 · Sunita Dilip Rajput
Yash Residency Phase 2 A Wing
possession by Dec 2030 · Not Available
Yash Skyline
possession by Aug 2033 · Siddhivinayak Developers
Yash Twin Tower
declared completion Dec 2020 · Yash Infra City Realty Private Limited
Yash101
declared completion Mar 2021 · Vilas Javdekar Eco Homes
Yashada Business Zone
possession by Dec 2026 · Yashada Brothers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026