MahaRERA Property Intelligence · Pune

YESAI PARK

P52100009994 · promoter Siddhivinayak Developers

Certificate SignedDue 31 Oct 2027

Delivery & Registration

MahaRERA registrationP52100009994
Registered on23 Aug 2017
Promoter-declared completion31 Oct 2027
Current statusCertificate Signed
Against today15 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Sales & Inventory

Of 204 homes filed with MahaRERA, 92 are sold/booked and 112 remain available (~45% sold) — selling steadily. Buyers have committed ₹12.81 Cr in agreement value so far. Of that, ₹12.12 Cr (~95%) is already collected, ₹69.13 Lakh receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 92 registered agreements, the effective carpet rate is ₹3,574/sqft (typical range ₹1,522–₹4,489) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

⚠ The inventory filing also declares: 3 reserved. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 207 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
F-AVDHUT1G+642-
D- SHRIPAD1G+735-
E-VALLABH1G+735-
AMENITY BLDG1G+23-
A - VISHNU1G+424-
B - HARI1G+432-
C - SHIV1G+436-

Unit mix on the filing: 207 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Oct 202731 Oct 2027Sanctioned plan was revised. Updated plan under process.

Location, Land & Connectivity

Located at YESAI PARK, Khed, Pune, 410505. Per the filed land record, the plot is bounded to the north by SANGAM GREEN PARK, to the south by AGRICULTURAL LAND 266, to the east by LAGHU ODHA and to the west by AGRICULTURAL LAND 265. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~36 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)32 km
Kharadi / EON IT Park36 km
Hinjewadi Rajiv Gandhi IT Park38 km
Pune Junction / city centre39 km
Baner–Balewadi belt39 km
Magarpatta / Hadapsar IT40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Siddhivinayak Developers is the promoter on 32 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Siddhivinayak Developers project & its RERA track record →

Other flagged projects by Siddhivinayak Developers

Siddhivinayak Developers
FlaggedPune
Siddhivinayak Developers
FlaggedPune
Siddhivinayak Developers
FlaggedPune
Siddhivinayak Developers
FlaggedPune
Siddhivinayak Developers
Not filing quarterly progress reportsPune
Siddhivinayak Developers
FlaggedPune

Other RERA-registered projects in Rajgurunagar

7 Sagar Plaza
possession by Aug 2026 · Sagar Kaluram Patole
Shree Paradise
possession by Oct 2026 · Sunita Ashutosh Gosavi
Rajashri Apartments
possession by Oct 2026 · Omkar Sanjay Thigale
Classic Amrut
possession by Oct 2026 · Classic Infra
Mahalaxmi Heights
possession by Dec 2026 · Mahalaxmi Developers
Aryaa Dream Town
possession by Dec 2026 · Vini Builders AND Developers

Other RERA-registered projects in Pune

Yin Yang
declared completion Dec 2020 · Proxima Creations
Yog Mudra
possession by Jun 2027 · Pawan Enterprises Through Madhukar Datta
Yog Sahakari Griha Rachna Sanstha Maryadit
declared completion Dec 2025 · Yog Sahakari Griha Rachana Sanstha Marya
Yogamrut
possession by Aug 2026 · Jay Ganesh Buildcon
Yoganand Park 2
declared completion Dec 2025 · Belvalkar Housing LLP
Yogashree At Nanded City
declared completion Jun 2023 · Nanded City Development & Constructi

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026