Mumbai/Project record

MahaRERA · the public record

VIVA RAM NIWAS C.H.S.

Parel · VIVA ENTERPRISES LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jan 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900012295

Delivery and registration

When is the project declared for completion?

VIVA RAM NIWAS C.H.S. is registered with MahaRERA as P51900012295 and the promoter has declared completion for 31 Jan 2021.

31 Jan 2021

declared completion

68months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900012295
Registered on01 Sep 2017
Promoter-declared completion31 Jan 2021
Current statusCertificate Signed
Against todayabout 68 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VIVA RAM NIWAS C.H.S. record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Viva Enterprises Limited is the promoter of record on 58 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

58projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VIVA RAM NIWAS C.H.S. in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
VIVA RAM NIWAS CHS1G+12-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2020Procedure for obtaining the Occupancy Certificate is under process . Procedure for the same is the lengthy process and there are many requirement to be fulfilled. Enclosed Arch

Location, Land & Connectivity

Located at Parel, Borivali, Mumbai Suburban, 400012. Per the filed land record, the plot is bounded to the north by 6 MT ROAD, to the south by CS NO 61 74, to the east by CS NO 59 74 and to the west by 6 MT GANESH LANE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)123 km
Kharadi / EON IT Park126 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Parel

Inspire
possession by Sep 2026 · R K Constructions
K RAS Residency
possession by Sep 2026 · K RAS Group
Kinjal Pride
possession by Oct 2026 · Hi Rock Construction Pvt Ltd
Bhivawani Chawl
possession by Dec 2026 · MS Radhakrishna Developer
Bhoiwada Chandra Bhuvan CHS Ltd
possession by Dec 2026 · Avadhoot Techno Consultant And Engineers
Ruparel Jewel
possession by Dec 2026 · Renuka Realtors

Major developers building in Parel

Other RERA-registered projects in Mumbai City

Viyaara Altiora
possession by Dec 2029 · Structure Creators
Wadhan Industrial Estate
declared completion Dec 2018 · Ganesh Krupa Enterprises
Wadhwa Pristine
declared completion Dec 2024 · Wadhwa Group Holdings Private Limited
Waterfront Tower
declared completion Jul 2023 · Sea Kunal Corporation Pvt. Ltd.
Waterview
possession by Jun 2028 · Lodha Developers Limited
Western India Mill
declared completion Dec 2017 · Mhada

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026