Bangalore/Project record

K-RERA · the public record

ABISH VISTA

· ABISH BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28%construction reportedQ1 2026 filing
51units not bookedof 70 · Q1 2026 filing
70registered unitsK-RERA registration · read 16 Jul 2026

The record · free to read

Registration read 16 Jul 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Inventory & scale

What this registration contains.

3 BHK
70

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

0.5registered acres

131.2registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1257/334/PR/250825/008031

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Land area2,159 sq m (0.5 acres)
Homes registered70
Tower/wing entries1
Unit mix70 × 3 BHK

In context

Density131.2 homes per acre
Density in context86th percentile of 4882 projects in this register (median 82.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units70Total inventory registered with K-RERA.
Official carpet area6,525 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area14,560 sqmUseful scale context when comparing density and project cost.
Registered land area2,159 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI4.62Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)85Separate filed counts; these categories may overlap and are not added together.
Covered-parking field82Separate filed counts; these categories may overlap and are not added together.
Open-parking field3Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberE2/BA 4/2025-26 (204543)Use this to match the sanctioned drawing set shown by the builder.
Plan approval date29-07-2025
Project start date01-09-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK70100%6,525 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
ABISH VISTA14708544.99 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 70 official flat/unit rows, matching the 70 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK7086.6-99.0 sqm1.1-1.6 sqm70

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
ABISH VISTA7086.6-99.0 sqm1.1-1.6 sqm70
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101ABISH VISTA13 BHK92.5 sqm1.3 sqm1
102ABISH VISTA13 BHK96.6 sqm1.5 sqm1
103ABISH VISTA13 BHK95.1 sqm1.4 sqm1
104ABISH VISTA13 BHK87.0 sqm1.1 sqm1
105ABISH VISTA13 BHK86.6 sqm1.1 sqm1
201ABISH VISTA23 BHK92.5 sqm1.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 2 of 24 compliance document slots are filed as under process / not yet usable: Organization Structure, Brochure.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantMAHESH KUMAR2454662015Dakshina Kannada, Karnataka - 575008
EngineerDhanrajMNG/BL/11227/23-242023Dakshina Kannada, Karnataka - 574253
ArchitectSuprith AlvaCA/2006/382772006Bengaluru Urban, Karnataka - 575002
ContractorAbish Builders Private Limited-2013Dakshina Kannada, Karnataka - 575003

Builder track record

RERA filing

Abish Builders has 2 other K-RERA-registered projects in our records (average reported construction progress 3%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹5.15 Cr collected from buyers, ₹3.57 Cr withdrawn from the project's escrow account.

Construction progress8% → 28% (+20 pts)
Units sold/booked as registered19/70 (27%)
Buyer collections in available QPRs₹9.46 Cr
Escrow withdrawals in available QPRs₹6.65 Cr (0.70x collections)
  • Construction progress moved from 8% to 28% across the filed QPR window.
  • The builder has drawn 0.70x of buyer collections from escrow (about 70% of the ₹9 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹36.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: The South Canara District Central Co-operative Bank Ltd.. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~302 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
MG Road / city centre300 km
Outer Ring Road / Manyata302 km
Electronic City306 km
Bellandur–Marathahalli belt309 km
Kempegowda Int'l Airport313 km
Whitefield IT hub316 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Abish Builders.
Abish Builders has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Abish Evara
On track · 3% built · 0% sold
Abish Residency And Business Center
No filings

Other RERA-registered projects in J. P. Nagar

Major developers building in J. P. Nagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Abish Vista?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 16 Jul 2026