Bangalore/Project record

K-RERA · the public record

Adarsh Welkin Park Phase 1

Anekal · Akarshak Realty

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

78%construction reportedQ1 2026 filing
20units not bookedof 832 · Q1 2026 filing
31 Dec 2027declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2BHK
7
3BHK
721
1BHK
1
2.5BHK
103

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

13.7registered acres

60.8registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/020923/006223

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2027
Land area55,408 sq m (13.7 acres)
Homes registered832
Tower/wing entries2
Unit mix7 × 2BHK, 721 × 3BHK, 1 × 1BHK, 103 × 2.5BHK

In context

Density60.8 homes per acre
Density in context30th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units832Total inventory registered with K-RERA.
Official carpet area92,675 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area174,881 sqmUseful scale context when comparing density and project cost.
Registered land area55,408 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.246Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)832Separate filed counts; these categories may overlap and are not added together.
Covered-parking field832Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberNM /A.S/Use this to match the sanctioned drawing set shown by the builder.
Plan approval date23-03-2022
Project start date01-07-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2BHK71%75 sqm
3BHK72187%115 sqm
1BHK10%61 sqm
2.5BHK10312%90 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block 22531231268.45 m
Block 52552052068.45 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 832 official flat/unit rows, matching the 832 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK72275.4-117.0 sqm23.4-35.4 sqm722
2.5 BHK10385.3-92.4 sqm25.3-27.0 sqm103
2 BHK675.4 sqm23.3-23.4 sqm6
1 BHK161.6 sqm17.9 sqm1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block 552061.6-117.0 sqm17.9-35.4 sqm520
Block 231275.4-117.0 sqm23.3-35.4 sqm312
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-001Block 203 BHK115.7 sqm34.8 sqm1
A-002Block 203 BHK117.0 sqm35.4 sqm1
A-003Block 203 BHK115.7 sqm34.7 sqm1
A-004Block 203 BHK110.7 sqm33.5 sqm1
B-001Block 203 BHK115.7 sqm34.7 sqm1
B-002Block 203 BHK117.0 sqm35.3 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 1 litigation case on record

  • Suit for partition — Senior Civil Judge at Anekal (2019)

⚠ 5 of 45 compliance document slots are filed as under process / not yet usable: Electricity Permission Letter, Certificate from Registered Engineer indicating the structural safety of the building, Proforma For Sale Deed, Approval/NOC under section 109 of KLR Act 1961, Approval/NOC under section 14 of the KTCP Act.

13 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Santosh N Ajjannavar vs Akarshak Realty Private LimitedI need your assistance in restoring the lock-in period to 15 months, as this was communicated to me both verbally and in the initial agreement document.AUTHORITY01/09/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved19-12-2019Gattahalli-II Water NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved01-07-2020gattihalli 2 CFE.pdf
KSPCB- MOEF (Above 50 Acres)Approved13-06-2019Ghattahalli 2 EC-SEIAA.pdf
KPTCL- BESCOMApproved01-02-2020BESCOM.pdf
Fire and SafetyApproved06-09-2019Fire NOC.pdf
Airport Authority of IndiaApproved23-05-2020AAI.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantMahesh Bs2209452008Bengaluru Urban, Karnataka - 560078
EngineerG H BasavarajuSE-188/2015-161983Bengaluru Urban, Karnataka - 560001
ArchitectK.AnjaliCOA/2004/327672004Bengaluru Urban, Karnataka - 560025
ContractorAdarsh developers-1988Bengaluru Urban, Karnataka - 560025

Builder track record

RERA filing

Akarshak Realty has 3 other K-RERA-registered projects in our records (average reported construction progress 14%). 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹570.69 Cr collected from buyers, ₹565.25 Cr withdrawn from the project's escrow account.

Construction progress62% → 78% (+16 pts)
Units sold/booked as registered812/832 (98%)
Buyer collections in available QPRs₹1,532.97 Cr
Escrow withdrawals in available QPRs₹1,517.79 Cr (0.99x collections)
  • 98% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • Construction progress moved from 62% to 78% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹67.4 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank Residency road Branch, Bangalore IFSC Code : ICIC0007429 Pin Code : 560025. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Electronic City4 km
Bellandur–Marathahalli belt7 km
Whitefield IT hub13 km
MG Road / city centre15 km
Outer Ring Road / Manyata21 km
Kempegowda Int'l Airport37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Akarshak Realty.
Akarshak Realty has 4 projects registered in Bangalore.
5 complaints on the K-RERA register against Akarshak Realty in Bangalore.

Other projects by this builder in Bangalore

Adarsh Forest Glen
On track · 21% built
Adarsh Welkin Park Phase 2
On track · 7% built · 21% sold

Other RERA-registered projects in Gattahalli

Major developers building in Gattahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.