Bangalore/Project record

K-RERA · the public record

Assetz Marq Building 3 - Tower 6

Bengaluru East · Assetz Whitefield Homes

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2024declared completionK-RERA registration · read 20 Sep 2026
345registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Studio 1BHK 2BHK 3BHK 4BHK
345

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.9registered acres

120.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/201001/003626

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 September 2024
Land area11,575 sq m (2.9 acres)
Homes registered345
Tower/wing entries1
Unit mix345 × Studio 1BHK 2BHK 3BHK 4BHK

In context

Density120.6 homes per acre
Density in context94th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units345Total inventory registered with K-RERA.
Official carpet area33,530 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area11,575 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI0.51Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)366Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-10-2020

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Studio 1BHK 2BHK 3BHK 4BHK345100%33,530 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower 628345366-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 345 official flat/unit rows, matching the 345 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK28993.5-126.1 sqm38.1-64.3 sqm304
STUDIO4819.8-22.4 sqm8.1-9.0 sqm48
4BHK6146.8-149.8 sqm62.2-63.1 sqm12
1BHK254.3-57.8 sqm21.6-22.9 sqm2

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower 634519.8-149.8 sqm8.1-64.3 sqm366
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
L-021Tower 623BHK111.1 sqm48.2 sqm1
L-022Tower 623BHK111.0 sqm49.1 sqm1
L-023Tower 623BHK98.0 sqm44.4 sqm1
L-024Tower 62STUDIO22.4 sqm9.0 sqm1
L-025Tower 623BHK126.1 sqm64.3 sqm1
L-026Tower 623BHK93.5 sqm43.1 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

12 of 36 compliance document slots are filed as Not Applicable; the remaining 24 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Sep 2024 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Arun M vs Assetz Mark BuildingDirection to promoter to rectify the incomplete exterior plastering of M Block wall in the Chamber between L and M Block, ensuring compliance with construction standards at no cost to the allotteeAUTHORITY18/11/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectKhan Global Engineering Consultants Private Limited-20033790 7th Main, HAL II Stage Indiranagar
Structural engineerDesign Tree Service Consultants Pvt Ltd---

Builder track record

RERA filing

Assetz has 15 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Assetz Whitefield”) (average reported construction progress 80%). 11 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹53.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Richmond Road (IFSC HDFC0000523, a/c …2350). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub6 km
Bellandur–Marathahalli belt13 km
Outer Ring Road / Manyata15 km
MG Road / city centre18 km
Kempegowda Int'l Airport20 km
Electronic City23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Assetz Whitefield. View Assetz Whitefield's full track record →
Assetz Whitefield has 4 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

Assetz Marq Phase 3A
Filing overdue · 100% built · 100% sold
Assetz Marq Phase 3B
Filing overdue · 100% built · 100% sold
Assetz Marq Building 2 - Tower 5
No filings

Other RERA-registered projects in Kannamangala

Major developers building in Kannamangala

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Assetz Marq Building 3 - Tower 6?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026