BREN ANANTA

Bengaluru South · BREN CORPORATION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

8%construction reportedQ1 2026 filing
203units not bookedof 217 · Q1 2026 filing
31 Aug 2027declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Aug 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
213
2 BHK
1
2 BHK + Study room
2
1 BHK + Study room
1

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.3registered acres

66.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/060324/006694

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 August 2027
Land area13,253 sq m (3.3 acres)
Homes registered217
Tower/wing entries2
Unit mix213 × 3 BHK, 1 × 2 BHK, 2 × 2 BHK + Study room, 1 × 1 BHK + Study room

In context

Density66.3 homes per acre
Density in context34th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units217Total inventory registered with K-RERA.
Official carpet area20,543 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area34,496 sqmUseful scale context when comparing density and project cost.
Registered land area13,253 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.744Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)217Separate filed counts; these categories may overlap and are not added together.
Covered-parking field311Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberKa.Yo.Pra/Pra.Pra.Patra/61/2023-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date22-02-2024
Project start date28-02-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK21398%20,233 sqm
2 BHK10%79 sqm
2 BHK + Study room21%167 sqm
1 BHK + Study room10%64 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
TOWER12412212275.72 m
TOWER218959557.84 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 217 official flat/unit rows, matching the 217 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK21392.0-97.0 sqm48.8-51.0 sqm213
2 BHK + Study room283.5 sqm44.6 sqm2
1 BHK + Study room164.1 sqm35.4 sqm1
2 BHK178.7 sqm41.3 sqm1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
TOWER112278.7-97.0 sqm41.3-51.0 sqm122
TOWER29564.1-97.0 sqm35.4-51.0 sqm95
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A - 001TOWER103 BHK97.0 sqm51.0 sqm1
A - 002TOWER103 BHK97.0 sqm51.0 sqm1
A - 003TOWER102 BHK78.7 sqm41.3 sqm1
A - 004TOWER103 BHK92.0 sqm48.8 sqm1
A - 005TOWER102 BHK + Study room83.5 sqm44.6 sqm1
A - 101TOWER113 BHK97.0 sqm51.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

16 of 46 compliance document slots are filed as Not Applicable; the remaining 30 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved09-01-20241 Water NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved12-11-20202 KSPCB CFE NOC.pdf
KSPCB- MOEF (Above 50 Acres)Approved04-09-20203 Environmental Impact Assement Authority - NOC.pdf
KPTCL- BESCOMApproved09-02-20245 Bescom NOC.pdf
Fire and SafetyApproved27-11-20237 Fire NOC.pdf
Airport Authority of IndiaApproved09-10-20239 Airport NOC.pdf
BSNL/Telecommunication DepartmentApproved28-10-202010 BSNL NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantAmit Someshwar Padaki2250952010Bengaluru Urban, Karnataka - 560004
EngineerAmarnath R BoraiahBCC/BL-0325/2019-202010Bengaluru Urban, Karnataka - 560050
ArchitectLAKSHMI CRCA/2010/491962007Bengaluru Urban, Karnataka - 560001
ContractorBREN CORPORATION PRIVATE LIMITED-2012Bengaluru Urban, Karnataka - 560001

Builder track record

RERA filing

Bren Corporation has 12 other K-RERA-registered projects in our records (average reported construction progress 58%). 7 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.49 Cr collected from buyers, ₹0.34 Cr withdrawn from the project's escrow account.

Construction progress6% → 8% (+2 pts)
Units sold/booked as registered14/217 (6%)
Buyer collections in available QPRs₹3.02 Cr
Escrow withdrawals in available QPRs₹2.12 Cr (0.70x collections)
  • Construction progress moved from 6% to 8% across the filed QPR window.
  • The builder has drawn 0.70x of buyer collections from escrow (about 70% of the ₹3 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹56.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: INDUSIND BANK M. G. ROAD, BANGALORE IFSC Code : INDB0000008 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City16 km
MG Road / city centre20 km
Bellandur–Marathahalli belt23 km
Outer Ring Road / Manyata28 km
Whitefield IT hub31 km
Kempegowda Int'l Airport47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Bren Corporation. View Bren Corporation's full track record →
Bren Corporation has 13 projects registered in Bangalore, 2 completed, 1 past RERA deadline.
1 complaints on the K-RERA register against Bren Corporation in Bangalore.

Buyer reviews · MouthShut

★☆☆☆☆ 1.0/5

88 reviews for Bren Corporation in Bangalore
Read 88 reviews on MouthShut →

Other projects by this builder in Bangalore

Bren Aspera
Past deadline · 94% built · 53% sold
Bren Cosmo
Filing overdue · 100% built
Bren Avaana
On track · 13% built · 17% sold

Other RERA-registered projects in Saluhunose

Major developers building in Saluhunose

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.