94%construction reportedQ1 2026 filing
186units not bookedof 394 · Q1 2026 filing
30 Nov 2025declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Nov 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Flats of 3BHK
394

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

4.4registered acres

89.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/300622/005028

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 November 2025
Land area17,729 sq m (4.4 acres)
Homes registered394
Tower/wing entries2
Unit mix394 × Flats of 3BHK

In context

Density89.9 homes per acre
Density in context70th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units394Total inventory registered with K-RERA.
Official carpet area39,087 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area83,029 sqmUseful scale context when comparing density and project cost.
Registered land area17,729 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.2Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)394Separate filed counts; these categories may overlap and are not added together.
Covered-parking field458Separate filed counts; these categories may overlap and are not added together.
Open-parking field31Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBDA/Na.Ma/Aa.Sa/Aa.Aa-1/Ta.Sa-4/Pu/25/2021-22Use this to match the sanctioned drawing set shown by the builder.
Plan approval date03-03-2022
Project start date06-05-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Flats of 3BHK394100%39,087 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
WING A2619719782.9 m
WING B2619719782.9 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 394 official flat/unit rows, matching the 394 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK39494.8-104.1 sqm42.3-45.7 sqm394

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
WING A19794.8-104.1 sqm42.3-45.7 sqm197
WING B19794.8-104.1 sqm42.3-45.7 sqm197
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
WA - 101WING A13 BHK104.1 sqm45.7 sqm1
WA - 102WING A13 BHK100.7 sqm45.6 sqm1
WA - 103WING A13 BHK94.8 sqm42.3 sqm1
WA - 104WING A13 BHK101.7 sqm45.5 sqm1
WA - 105WING A13 BHK101.7 sqm45.5 sqm1
WA - 106WING A13 BHK94.8 sqm42.3 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

19 of 45 compliance document slots are filed as Not Applicable; the remaining 26 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)Not found in catalog
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved06-01-20221 Bandapura water NOC (Grama Panchayath).pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved09-03-20222 KSPCB - CFE.pdf
KSPCB- MOEF (Above 50 Acres)Approved07-10-20213 State Environmental Impact Assessment Authority_0001.pdf
KPTCL- BESCOMApproved12-01-20225 Bandapura- Bescom Noc.pdf
Fire and SafetyApproved11-02-20227 FIRE NOC-(Bren OMR)Bandapura.pdf
Airport Authority of IndiaApproved11-11-20219 Bren Corporation Bandapura Airport NOC.pdf
BSNL/Telecommunication DepartmentApproved17-02-202210 Bandapura BSNL NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantAmit Someshwar Padaki2250952010Bengaluru Urban, Karnataka - 560004
EngineerSterling Engineering Consultancy Services Pvt LtdBCCL/BL-3.6/SE-0103/21-221978Bengaluru Urban, Karnataka - 560025
ArchitectThomas AssociatesBCC/BL-3.6 A-972/2001-021992Bengaluru Urban, Karnataka - 560001
ContractorBREN CORPORATION PRIVATE LIMITED-2012Bengaluru Urban, Karnataka - 560001

Builder track record

RERA filing

Bren Corporation has 12 other K-RERA-registered projects in our records (average reported construction progress 44%). 6 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹28.28 Cr collected from buyers, ₹19.79 Cr withdrawn from the project's escrow account.

Construction progress79% → 94% (+15 pts)
Units sold/booked as registered208/394 (53%)
Buyer collections in available QPRs₹56.74 Cr
Escrow withdrawals in available QPRs₹39.72 Cr (0.70x collections)
  • Construction progress moved from 79% to 94% across the filed QPR window.
  • The builder has drawn 0.70x of buyer collections from escrow (about 70% of the ₹57 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹41.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC RICHMOND ROAD IFSC Code : HDFC0000523 Pin Code : 560025. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub8 km
Bellandur–Marathahalli belt13 km
Outer Ring Road / Manyata13 km
MG Road / city centre16 km
Kempegowda Int'l Airport18 km
Electronic City23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Bren Corporation. View Bren Corporation's full track record →
Bren Corporation has 13 projects registered in Bangalore, 2 completed, 1 past RERA deadline.
1 complaints on the K-RERA register against Bren Corporation in Bangalore.

Buyer reviews · MouthShut

★☆☆☆☆ 1.0/5

88 reviews for Bren Corporation in Bangalore
Read 88 reviews on MouthShut →

Other projects by this builder in Bangalore

Bren Cosmo
Filing overdue · 100% built
Bren Ananta
Due soon · 8% built · 6% sold
Bren Avaana
On track · 13% built · 17% sold

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Bren Aspera?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026