Developer RERA record

Bren Corporation

Bren Corporation has 13 RERA-registered projects: 4 projects under construction, Bengaluru averaging 49% construction; 8 projects past their declared completion date. All figures are the developer's own regulator filings.

Flagged
Delivery signal
4
Under construction
1
Completed / delivered
8
Past declared date
21%
Bengaluru inventory booked
1
RERA complaints filed

Under construction

Under construction — 4 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

Bengaluru: 1.0/5 ★☆☆☆☆ (88 MouthShut reviews)

ProjectCityProgress / possession
BREN IMPERIA GRANDEBengaluru22%
BREN AVAANABengaluru12%
BREN PARK CITYBengaluru12%
BREN ANANTABengaluru7%
Considering a specific Bren Corporation project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (1)click to expand
ProjectCityStatus
BREN COSMOBengaluru100% built
Past declared date (8)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
BREN EDGEWATERSBengaluru2018-12
BREN CHAMPIONS SQUAREBengaluru2020-09
BREN STARLIGHTBengaluru2020-03
BREN IMPERIABengaluru2020-09
BREN NORTHERN LIGHTSBengaluru2022-06
BREN ZAHARABengaluru2023-07
BREN ASPERA (90.0% built)Bengaluru2025-11
SOHO BY BREN (99.0% built)Bengaluru2025-11

RERA complaints & orders

Regulatory record

1 total complaints filed — below average for builders of this scale (16th percentile).

1
Karnataka RERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Bren Corporation's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.