Bangalore/Project record

K-RERA · the public record

BREN IMPERIA GRANDE

Bengaluru East · BREN CORPORATION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

27%construction reportedQ1 2026 filing
274units not bookedof 327 · Q1 2026 filing
31 Oct 2027declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Oct 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

4 BHK
168
5 BHK
80
EWS
79

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

12.0registered acres

27.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/030524/006842

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 October 2027
Land area48,544 sq m (12.0 acres)
Homes registered327
Tower/wing entries3
Unit mix168 × 4 BHK, 80 × 5 BHK, 79 × EWS

In context

Density27.3 homes per acre
Density in context9th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units327Total inventory registered with K-RERA.
Official carpet area39,221 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area81,415 sqmUseful scale context when comparing density and project cost.
Registered land area48,544 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.2Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)323Separate filed counts; these categories may overlap and are not added together.
Covered-parking field323Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Dir/JDNORTH/0071/22-23Use this to match the sanctioned drawing set shown by the builder.
Plan approval date15-04-2024
Project start date15-04-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK16851%23,628 sqm
5 BHK8024%13,099 sqm
EWS7924%2,495 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
WING 120797567.78 m
WING 22114514567.78 m
WING 32110310367.78 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 327 official flat/unit rows, matching the 327 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4 BHK168140.0-141.3 sqm57.7-58.7 sqm168
5 BHK80163.7-163.8 sqm69.0-70.3 sqm80
EWS7930.5-36.1 sqm13.8-17.4 sqm79

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
WING 2145140.0-163.7 sqm57.7-69.0 sqm145
WING 3103140.0-163.8 sqm57.7-70.3 sqm103
WING 17930.5-36.1 sqm13.8-17.4 sqm79
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
WA - 401WING 14EWS30.5 sqm13.8 sqm1
WA - 402WING 14EWS30.5 sqm13.8 sqm1
WA - 501WING 15EWS30.5 sqm13.8 sqm1
WA - 502WING 15EWS30.5 sqm13.8 sqm1
WA - 503WING 15EWS30.5 sqm13.8 sqm1
WA - 504WING 15EWS30.5 sqm13.8 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 1 of 40 compliance document slots are filed as under process / not yet usable: Certificate from Chartered Account.

12 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200217/0005469
17-02-2020
Failed to deliver the Flat as per AgreementBREN STARLIGHT (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved12-10-20221 BWSSB NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved26-06-20242 KSPCB CFO Haraluru.pdf
KSPCB- MOEF (Above 50 Acres)Approved11-08-20223 Environmental (SEIAA NOC).pdf
KPTCL- BESCOMApproved03-01-20225 Bescom NOC.pdf
Fire and SafetyApproved09-11-20227 Fire NOC.pdf
Airport Authority of IndiaApproved27-12-20219 Airport NOC.pdf
BSNL/Telecommunication DepartmentApproved17-01-202210 BSNL NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantAmit Someshwar Padaki2250952010Bengaluru Urban, Karnataka - 560004
EngineerSRI N N NAGENDRA KUMARBCCL/BL-3.6/SE-0103/21-221978Bengaluru Urban, Karnataka - 560025
ArchitectGayathri & Namith ArchitectsCA/91/139121995Bengaluru Urban, Karnataka - 560047
ContractorBren Corporation Private Limited-2012Bengaluru Urban, Karnataka - 560001

Builder track record

RERA filing

Bren Corporation has 12 other K-RERA-registered projects in our records (average reported construction progress 55%). 7 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹5.29 Cr collected from buyers, ₹3.70 Cr withdrawn from the project's escrow account.

Construction progress19% → 27% (+8 pts)
Units sold/booked as registered53/327 (16%)
Buyer collections in available QPRs₹21.88 Cr
Escrow withdrawals in available QPRs₹15.32 Cr (0.70x collections)
  • Construction progress moved from 19% to 27% across the filed QPR window.
  • The builder has drawn 0.70x of buyer collections from escrow (about 70% of the ₹22 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹68.4 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Kasturba Road, Bangalore IFSC Code : HDFC0000009 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bellandur–Marathahalli belt4 km
Electronic City7 km
MG Road / city centre10 km
Whitefield IT hub11 km
Outer Ring Road / Manyata16 km
Kempegowda Int'l Airport33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Bren Corporation. View Bren Corporation's full track record →
Bren Corporation has 13 projects registered in Bangalore, 2 completed, 1 past RERA deadline.
1 complaints on the K-RERA register against Bren Corporation in Bangalore.

Buyer reviews · MouthShut

★☆☆☆☆ 1.0/5

88 reviews for Bren Corporation in Bangalore
Read 88 reviews on MouthShut →

Other projects by this builder in Bangalore

Bren Aspera
Past deadline · 94% built · 53% sold
Bren Cosmo
Filing overdue · 100% built
Bren Ananta
Due soon · 8% built · 6% sold
Bren Avaana
On track · 13% built · 17% sold

Other RERA-registered projects in HSR Layout

Major developers building in HSR Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Bren Imperia Grande?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026