K-RERA · the public record
Brigade Horizon
Bengaluru South · Brigade Enterprises
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Promoter-reported construction
K-RERA quarterly filings · Q3 2025 to Q1 2026
declared completion
31 Dec 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
5.0registered acres
74.4registered units per acre
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project · Prestige Park Grove
A larger advertised area. Almost the same carpet area.
In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.
This illustrates the report format. These findings concern the named sample, not this project.
Read the sample report ↗
The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/310/PR/190722/005086
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
In context
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered units | 372 | Total inventory registered with K-RERA. |
| Official carpet area | 24,942 sqm | Regulator-disclosed project-level carpet area, not vision-derived room sums. |
| Official built-up area | 54,625 sqm | Useful scale context when comparing density and project cost. |
| Registered land area | 20,234 sqm | The land area attached to this K-RERA registration. |
| Sanctioned FAR/FSI | 1.859 | Higher FAR generally means a denser vertical build, subject to site layout and open-space design. |
| Registered tower/wing entries | 18 | Official tower/wing count in the K-RERA detail page. |
| Parking total (reconciled) | 347 | Separate filed counts; these categories may overlap and are not added together. |
| Covered-parking field | 388 | Separate filed counts; these categories may overlap and are not added together. |
| Open-parking field | 14 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Approved plan number | BDA/NM/AS/AA-3/TS-2/D/04/2022-23 | Use this to match the sanctioned drawing set shown by the builder. |
| Plan approval date | 23-05-2022 | |
| Project start date | 24-06-2022 |
Official inventory & towers
RERA filingK-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| TYPE-4 (2 Bedroom + 2 Toilet) | 161 | 43% | 62 sqm |
| TYPE-10 (3 Bedroom + 2 Toilet) | 16 | 4% | 85 sqm |
| TYPE-3 (2 Bedroom + 2 Toilet) | 10 | 3% | 59 sqm |
| TYPE-15 (4 Bedroom + 3 Toilet) | 2 | 1% | 154 sqm |
| TYPE-14 (3 Bedroom + 2 Toilet) | 2 | 1% | 92 sqm |
| TYPE-2 (2 Bedroom+ 2 Toilet) | 29 | 8% | 59 sqm |
| TYPE-1 (1 Bedroom+ 1 Toilet) | 50 | 13% | 38 sqm |
| TYPE-5 (2 Bedroom + 2 Toilet) | 7 | 2% | 62 sqm |
| TYPE-6 (3 Bedroom + 2 Toilet) | 32 | 9% | 86 sqm |
| TYPE-13 (3 Bedroom + 2 Toilet) | 4 | 1% | 92 sqm |
| TYPE-11 (3 Bedroom + 2 Toilet) | 1 | 0% | 85 sqm |
| TYPE-9 (3 Bedroom + 2 Toilet) | 2 | 1% | 85 sqm |
| TYPE-8 (3 Bedroom + 2 Toilet) | 1 | 0% | 85 sqm |
| TYPE-7 (3 Bedroom + 2 Toilet) | 49 | 13% | 85 sqm |
| TYPE-17 (4 Bedroom + 3 Toilet) | 2 | 1% | 160 sqm |
| TYPE-12 (3 Bedroom + 2 Toilet) | 2 | 1% | 85 sqm |
| TYPE-16 (4 Bedroom + 3 Toilet) | 2 | 1% | 154 sqm |
Registered tower / wing summary
| Tower/wing | Floors | Units | Parking | Height |
|---|---|---|---|---|
| Tower A | 9 | 35 | 35 | 29.4 m |
| Tower B | 9 | 34 | 34 | 29.4 m |
| Tower C | 3 | 14 | 14 | 15 m |
| Tower D | 3 | 13 | 13 | 15 m |
| Tower E | 4 | 19 | 19 | 15 m |
| Tower F | 4 | 12 | 12 | 15 m |
| Tower G | 4 | 20 | 20 | 15 m |
| Tower H | 4 | 25 | 20 | 15 m |
Showing first 8 of 18 tower/wing rows.
Official unit register
RERA filingK-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 372 official flat/unit rows, matching the 372 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.
By unit type
| Unit type | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| 2 BHK | 207 | 58.8-62.2 sqm | 51.8-54.4 sqm | 207 |
| 3 BHK | 109 | 85.1-92.1 sqm | 53.0-75.3 sqm | 109 |
| 1 BHK | 50 | 38.5 sqm | 31.4 sqm | 27 (23 with 0) |
| 4 BHK | 6 | 154.2-160.3 sqm | 96.0-118.5 sqm | 6 |
By tower / wing
| Tower/wing | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| Tower A | 35 | 85.1-160.3 sqm | 53.0-118.5 sqm | 35 |
| Tower B | 34 | 85.1-160.3 sqm | 53.0-118.5 sqm | 34 |
| Tower P | 27 | 38.5-62.2 sqm | 31.4-54.4 sqm | 22 (5 with 0) |
| Tower H | 25 | 38.5-62.2 sqm | 31.4-54.4 sqm | 20 (5 with 0) |
| Tower K | 25 | 38.5-62.2 sqm | 31.4-54.4 sqm | 20 (5 with 0) |
| Tower N | 21 | 38.5-62.2 sqm | 31.4-54.4 sqm | 19 (2 with 0) |
| Tower G | 20 | 58.8-62.2 sqm | 51.8-54.4 sqm | 20 |
| Tower J | 20 | 58.8-62.2 sqm | 51.8-54.4 sqm | 20 |
| Tower L | 20 | 38.5-62.2 sqm | 31.4-54.4 sqm | 18 (2 with 0) |
| Tower O | 20 | 58.8-62.2 sqm | 51.8-54.4 sqm | 20 |
| Tower R | 20 | 58.8-62.2 sqm | 51.8-54.4 sqm | 20 |
| Tower E | 19 | 85.1 sqm | 75.3 sqm | 19 |
Showing first 12 of 18 tower/wing groups.
Show sample official unit rows
| Unit | Tower | Floor | Type | Carpet | UDS | Parking |
|---|---|---|---|---|---|---|
| A 0004 | Tower A | 0 | 3 BHK | 85.1 sqm | 53.6 sqm | 1 |
| A 0101 | Tower A | 1 | 3 BHK | 85.8 sqm | 53.0 sqm | 1 |
| A 0102 | Tower A | 1 | 3 BHK | 85.8 sqm | 53.0 sqm | 1 |
| A 0103 | Tower A | 1 | 3 BHK | 85.1 sqm | 53.6 sqm | 1 |
| A 0104 | Tower A | 1 | 3 BHK | 85.1 sqm | 53.6 sqm | 1 |
| A 0201 | Tower A | 2 | 3 BHK | 85.8 sqm | 53.0 sqm | 1 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
16 of 45 compliance document slots are filed as Not Applicable; the remaining 29 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
Complaints on this project's K-RERA page (21 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/190802/0003774 02-08-2019 | Project delay compensation & Veracity of the agreement & Brochure while booking | Brigade Panorama (another project by this promoter) | DISPOSED AO |
| CMP/190915/0004196 15-09-2019 | Waiting period more than 1.5 years, amenities built on kharab land, Club house not as per agreement | Brigade Panorama (another project by this promoter) | DISPOSED AO |
| CMP/190920/0004245 20-09-2019 | Delay in paying the Delay Compensation | Brigade Panorama (another project by this promoter) | DISPOSED AO |
| CMP/200211/0005414 11-02-2020 | Brigade group not given the compensation as per RERA and changes in the layout plan | Brigade Panorama (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/200513/0005880 13-05-2020 | Refund of amount due to delay in registration/handover | Brigade Panorama (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/201130/0007159 30-11-2020 | Brigade has backed out of delay compensation payment after earlier assuring to pay the same | Brigade Panorama (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/210212/0007498 12-02-2021 | Recovery of delay compensation, rental loss & Property tax amount with Interest for 6 years of delay caused by builder to deliver possession of flat | Plumeria Lifestyle at Brigade Meadows (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/210512/0007948 12-05-2021 | BUILDER NOT ALLOWING INSPECTION OF OUR APARTMENT | Brigade Buena Vista-Phase 2 (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Statutory approval status
RERA filingClean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.
4 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|---|---|---|
| Water supply and sewage board | Approved | 07-09-2021 | Brigade Horizon Water NOC.pdf |
| KSPCB- PCB (10 Acres to 125 Acres) | Approved | 23-02-2018 | Brigade Horizon CFE.pdf |
| KSPCB- MOEF (Above 50 Acres) | Approved | 19-02-2018 | Brigade Horizon SEIAA.pdf |
| KPTCL- BESCOM | Approved | 29-11-2021 | Brigade Horizon BESCOM NOC1.pdf |
| Fire and Safety | Approved | 01-07-2021 | Brigade Horizon Fire NOC.pdf |
| Airport Authority of India | Approved | 16-07-2021 | AAI NOC Horizon 1 Acre.pdf |
Project team & certifications
RERA filingK-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Chartered accountant | R. Srinivasan | 28986 | 2000 | Bengaluru Urban, Karnataka - 560003 |
| Engineer | BASE Engineering Services | BCC/BL-3.6/SE-166/2014-15 | 2007 | Bengaluru Urban, Karnataka - 560003 |
| Architect | Mindspace Architects | BCC/BL-3.6/A-2981/2019-20 | 2004 | Bengaluru Urban, Karnataka - 560094 |
| Contractor | Contractor not finalized | - | 1986 | Bengaluru Urban, Karnataka - 560055 |
Builder track record
RERA filingBrigade has 60 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Brigade Enterprises”) (average reported construction progress 68%). 31 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filingLatest quarterly filing (2026-Q1): ₹11.44 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.
| Construction progress | 100% → 100% (+0 pts) |
| Units sold/booked as registered | 368/372 (99%) |
| Buyer collections in available QPRs | ₹35.25 Cr |
- 99% of registered units are shown as sold/booked, but no completion certificate is on file yet.
- The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.
- The builder has drawn 0.00x of buyer collections from escrow (about 0% of the ₹35 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
Declared construction cost ÷ registered units averages to ₹30.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.
RERA 70% project account is on file: KOTAK MAHINDRA BANK M.G Road IFSC Code : KKBK0008066 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| MG Road / city centre | 19 km |
| Electronic City | 23 km |
| Outer Ring Road / Manyata | 25 km |
| Bellandur–Marathahalli belt | 26 km |
| Whitefield IT hub | 33 km |
| Kempegowda Int'l Airport | 44 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.