RERA Property Intelligence Report · Preview

GM AMBITIOUS ENCLAVE

Allam Infinite India · Anekal · K-RERA PRM/KA/RERA/1251/308/PR/180406/001467

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

2,359
Registered units
₹698.9 Cr
Est. construction cost
Units profiled
29
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units2,359Total inventory registered with K-RERA.
Registered land area41,889 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings6Official tower/wing count in the K-RERA detail page.
Parking disclosed2,224 total (109 open) — 0.94 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date04-04-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A114501456-
A214494449-
A314500455-
B114298298-
B214298298-
C14268268-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 2,359 official flat/unit rows, matching the 2,359 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK1,42046.5-49.8 sqm14.3-15.3 sqm1,420
3 BHK66959.8 sqm18.4 sqm669
1 BHK27030.2 sqm9.3 sqm0 (270 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A150130.2-59.8 sqm9.3-18.4 sqm411 (90 with 0)
A350030.2-59.8 sqm9.3-18.4 sqm410 (90 with 0)
A249430.2-59.8 sqm9.3-18.4 sqm404 (90 with 0)
B129846.5-59.8 sqm14.3-18.4 sqm298
B229846.5-59.8 sqm14.3-18.4 sqm298
C26846.5-59.8 sqm14.3-18.4 sqm268
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A10001A102 BHK49.8 sqm15.3 sqm1
A10002A102 BHK49.8 sqm15.3 sqm1
A10003A102 BHK49.8 sqm15.3 sqm1
A10004A102 BHK46.5 sqm14.3 sqm1
A10005A102 BHK46.5 sqm14.3 sqm1
A10006A102 BHK46.5 sqm14.3 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~532 sqft — compact homes (1–2BHK / studio territory), not compact stock. This is a large, multi-tower township — 2359 homes across 6 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 2,224 parking spaces for 2,359 homes (~0.9 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~15 sqm per home; across all 2,359 homes that is ~86% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 23 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Oct 2023, extended (Section 6 Extension) to 30 Jul 2025 — both dates have passed with no OC on file. The extension on file was granted on 25 Mar 2025 (K-RERA extension no. EX/PRM/KA/RERA/1251/308/PR/250325/001467) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (351 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Vishal P Bhat vs ALLAM INFINITE INDIA PVT LTDTo direct the developer to complete the project at the earliest and handover possession of the flat and to award delay interest on the sale consideration of Rs. 29,84,361/-AUTHORITY31/03/2026
Rahul A vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest. On completion of project the sale deed to be executed in my name.AUTHORITY31/03/2026
Sanjeev Kumar S vs Allam Infinite India Pvt LtdProject completion, obtain OC and handover the property. Seeking Delayed Interest. On completion of project the sale deed to be executed in my/our nameAUTHORITY31/03/2026
Naveen and Jayamani J M vs Allam Infinite india Pvt. Ltd.,Request for refund of principle, interest & compensationAUTHORITY30/10/2024
PABITRA KUMAR ROYCHOWDHURY vs M/s.Allam Infinite India Pvt Ltd & anotherTo complete the project ,obtain OC and handed over position to pay delay interest under section 18(1) provision of RERA ACT. TO CANCEL THE COVID 19 EXTENSION,DIRECTION FROM AUTHORITY ON COMPLETEAUTHORITY30/09/2025
Seshagiri Raghavendran vs M/S.ALLAM INFINITE INDIA PVT LTDRefund of amount with interest and compensationAUTHORITY30/07/2025
RAMA KOTA vs ALLAM INFINITE INDIA PVT LTDKindly issue an order to sanction interest on delay period until delivery of possession is completedAUTHORITY30/01/2026
Jagan Kumar R Pandian vs GM Ambitious EnclaveTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY30/01/2026
MR SOUMENDRA CHANDRASHEKAR BISWAL vs M/S.ALLAM INFINITE INDIA PVT LTDInterest on delay periodAUTHORITY29/11/2024
MAJOR VISHWANATH J KAMBALIMATH vs M/S.ALAM INFINITE INDIAIn view of my withdrawal from the Flat and the Project due to huge delay in completion of the project and giving the possession of the Flat, I would request for the full refund of amount as per the RaAUTHORITY29/06/2026
Biswajeet Kumar Singh vs M/s. Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY29/06/2026
ADARSHA H M vs Allam Infinite India Pvt LtdProvide delay interest under Section 18 (1) Proviso of RERA Act. until possession, On receiving OC/ Possession sale deed to be executed in complainants name within 60 days.AUTHORITY29/06/2026
Niveditha V K vs M/S.ALAM INFINITE INDIADelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favorAUTHORITY29/06/2026
Juliee Kumari vs M/S.ALAM INFINITE INDIATo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act.AUTHORITY29/06/2026
Hari prasad j vs M/s. Allam Infinite India Private LimitedInterest on delay periodAUTHORITY29/06/2026
Nishant vs M/s. Allam Infinite India Private LimitedKindly issue an order to the promoter to pay interest on delay period till delivery of the possession is completed.AUTHORITY29/06/2026
Suresh A M vs M/S.ALAM INFINITE INDIATo complete the Project, obtain OC and handover the possession and also Delayed Interest compensationAUTHORITY29/06/2026
Surchand Sapam vs Allam Infinite India Pvt LtdDirect the developer to refund the full amount paid for Flat No. A3-08-30 at GM Ambitious Enclave without any deductions with interest on the total amount from the date of payment till date and comp.AUTHORITY29/06/2026
Gopal Chakraborty vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under RERA Act. To cancel the Covid-19 extension. On completion of project the sale deed to be executed in my nameAUTHORITY29/04/2026
Lokesh M vs Allam Infinite India Private LimitedTo complete the Project as per Sales deed, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act.AUTHORITY29/04/2026
Satya Sagar Korikana vs ALLAM INFINITE INDIA PVT LTDDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY29/04/2026
Vinod Kumar Singh vs Allam Infinite India Private Limitedseeking interest on delay period from promoter till Possession of flat is Handed over as Monthly PaymentsAUTHORITY29/04/2026
ASHOK KRISHNA PAHADIYA vs Allam Infinite India Private LimitedRefundAUTHORITY29/04/2026
Vinod Job vs Allam Infinite India Private LimitedProject completion, obtain OC and handover the property. Seeking Delayed Interest. On completion of project the sale deed to be executed in my/our name.AUTHORITY29/04/2026
Pooja Verma vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession, execute sale deed in my favor. To pay delay interest under Section 18 (1) Provision of RERA Act. To cancel the Covid-19 extension.AUTHORITY29/04/2026
Suraj Prakash Valimbe vs Allam Infinite India Private LimitedTo complete the Project as per Sales deed, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act.AUTHORITY28/04/2026
Shyam Sundar Shukla vs ALLAM INFINITE INDIA PVT LTDTo get delay interest from respondents, to direct the respondents to complete the project and obtain occupancy certificate, On completion of project the sale deed to be executed in our favorAUTHORITY28/01/2026
Ranjit Shukla vs gm abmitious enclaveTo get delay interest from respondents, to direct the respondents to complete the project and obtain occupancy certificate and sale deed to be executed in favor of complainantsAUTHORITY28/01/2026
Deb Prasad Bhattrai vs Allam Infinite India Private LimitedDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY27/04/2026
Jithin Mathew John vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY27/04/2026
B N Deepak vs Allam Infinite India Private Limitedinterest on delay periodAUTHORITY27/04/2026
Rishabh Kumar Jain vs ALLAM INFINITE INDIA PVT LTDDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY27/03/2026
Arjun Venugopal vs Allam Infinite India Pvt LtdTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. Sale deed to be executed in my favour after project completion.AUTHORITY27/03/2026
Naveen N Sherigar vs Allam Infinite India Private LimitedDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY27/03/2026
Akshath Ganesh vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our nameAUTHORITY27/03/2026
NEERAJ SHARMA vs ALLAM INFINITE INDIA PVT LTDInterest on INR 30,00,000/- for Delay Period commencing from 03/10/2023 till the date of actual handover of possession according to RERA rate and rules framed thereunder.AUTHORITY27/03/2026
DIGVIJAY BARAPATRE & POOJITHA KR vs M/S.ALLAM INFINITE INDIA PRIVATE LIMITEDRefund of the amount and delay compensationAUTHORITY27/03/2023
Raghavendra S vs Allam Infinite India Private LimiteKindly issue an order to the promoter to pay "interest on delay period.AUTHORITY27/02/2026
Alovi Kiho vs Allam Infinite India Private LimiteProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my name.AUTHORITY27/02/2026
Pamela Chakraborty vs Allam Infinite India Private LimitedDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY27/02/2026
Vaibhav B Pandhare vs ALLAM INFINITE INDIA PVT LTD(i) To complete the Project, obtain Occupancy Certificate and handover the possession of the Schedule Property at the earliest to the Complainants. (II) Delay interest and Execute Sale DeedAUTHORITY27/01/2026
Harishankar Moosath vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act.AUTHORITY27/01/2026
SUMAN MOHAPATRA vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deedAUTHORITY27/01/2026
ANOOP KUMAR PADINJARE THOPPIL vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension on completion of project the sale deed.AUTHORITY27/01/2026
Rashmi Kubusada vs ALLAM INFINITE INDIA PVT LTDPromoter to complete project obtain occupancy certificate and handover unit A2-08-31. Pay delay interest from Oct 3rd 2022 until possession reimburse Rs1 lakh for litigation and cancel Covid extensionAUTHORITY27/01/2026
Sunkireddy Sudhakar vs ALLAM INFINITE INDIA PVT LTDInterest on Delay PeriodAUTHORITY27/01/2026
Jisha Lenu George vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest. On completion of project the sale deed to be executed in my name.AUTHORITY27/01/2026
MR M.R.PRADEEP vs M/S.GM Ambitious Enclaveswift completion of the project and interest on delay period for the delay in project deliveryAUTHORITY27/01/2025
Rajeeb Banerjee and Riyanka Banerjee vs ALLAM INFINITE INDIA PVT LTDThe entire amount paid towards purchase of the flat i.e. Rs 3,75,000/- and compensation thereofAUTHORITY26/12/2024
MR.PRAVEEN RAIKOTE vs M/S.ALLAM INFINITE INDIA PVT LTDDirect the Respondents to pay delay compensation to the Complainants, execution of Sale Deed,AUTHORITY26/12/2023
K Ashwin Kumar vs GM AMBITIOUS ENCLAVETo complete the project at the earliest , to obtain the OC & possession of the schedule property with all facilities along with delayed interestAUTHORITY26/06/2025
Darisa Supriya vs GM AMBITIOUS ENCLAVERefund and interest as per bank rate for paid amountAUTHORITY26/03/2025
Brajesh Kumar vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deedAUTHORITY26/02/2026
Pranay Prasad vs ALLAM INFINITE INDIA PVT LTDKindly issue and order to the promoter to pay interest on delay period to me as monthly payments till delivery of the possesion is completed.AUTHORITY26/02/2026
SHREE PRIYA J vs M/s. Allam Infinite India Private LimitedHandover of flat and sale deed registration to avoid bank legal action.AUTHORITY26/02/2026
GAGANDEEP G vs ALLAM INFINITE INDIA PVT LTDKINDLY ISSUE AN ORDER TO THE PROMOTER TO PAY INTEREST FOR THE DELAYED PERIOD UNTIL THE COMPLETED APARTMENT IS DELIVERED FOR POSSESSIONAUTHORITY25/03/2026
DHANDAPANI M vs Allam Infinite India Private LimitedTo complete the Project, Obtain OC and Handover the possession. To pay delay interest under Section 18(1)Provisio of RERA Act. to cancel the Covid -19 extension. On completion of project the sale deedAUTHORITY24/04/2026
LATHEESH KUMAR E vs M/s. Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY24/04/2026
Capt Jean Dominic vs Allam Infinite India Private LimitedInterest on Delay periodAUTHORITY24/04/2026
Capt Jean Dominic vs Allam Infinite India Private LimitedInterest on Delay periodAUTHORITY24/04/2026
kalyani konda vs M/S.ALLAM INFINITE INDIA PVT LTDinterest on delay periodAUTHORITY24/03/2026
Sachin Pandharinath Mali vs M/S.SACHIN PANDHARINTH MALL AND ANOTHERTo complete the project, Obtain OC and handover the posession. To pay delay interest under section 18(1)provison of RERA act, On completion of the project the sale deed. Requst for online hearingAUTHORITY24/03/2026
Makarand Prakash Mali vs M/S.ALLAM INFINITE INDIA PVT LTDTo Complete the Project, Obtain OC and handover the possession, To pay delay interest under section 18(1)provision of RERA Act, On completion of project the sale deed, Request for online hearing.AUTHORITY24/03/2026
MS.UZMA SULTANA vs /S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERRefund as per RERA Norms. Full Payment + Interest I've been paying for bank + RENTAUTHORITY24/03/2025
Revlon Oliver Dsouza vs gm ambitious enclaveOn Project completion, obtain OC and handover the flat to the complainant. Seeking Delayed Interest, On completion of the project Sale deed to be executed on Complainant’s name, Pass restraining orderAUTHORITY24/02/2026
Sikander Bakth vs gm ambitious enclaveTo complete the Project, obtain Occupancy Certificate and handover the possession of the Schedule Property to the Complainant and to issue an order to the promoter to pay interest on delay period.AUTHORITY24/02/2026
Mrs Meena Mohapatra vs ALLAM INFINITE INDIA PVT LTDPlease help me get my money paid so far refunded from builderAUTHORITY24/01/2023
Ranjith R K vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERinterest on delay periodAUTHORITY23/07/2025
Ankush Dhar vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHER1. I would like RERA to intervene and help us get our home quickly. 2. I would like to get "interest on delay period" caused by builder.AUTHORITY23/07/2025
Ashish Jain vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo pay the delay interest under section 18 (1) Proviso of RERA Act on payments made and to pay Rs.1,00,000/- towards the litigation expenses and to cancel Covid19 extension of 9 month until 31/07/2024AUTHORITY23/07/2025
Mohd Afroz Alam vs M/S.ALLAM INFINITE INDIA PVT LTDI requesting this Hon'ble Authority to direct the respondent to complete and handover the flat, registration of sale deed and to pay interest on delay period.AUTHORITY23/07/2025
Annamma Jacob vs M/s. Allam Infinite India Private LimitedRelief to seek delayed interest - Direction from the Authority - On completion of Project - Sale deed to be executed in our favour.AUTHORITY23/06/2026
HariKrishnanS vs M/S.ALLAM INFINITE INDIA PVT LTD AND OTHERSCompensation due to delay in project & increase in EMI ROIs & Inflations & RecessionsAUTHORITY23/04/2025
SATISH HONMUTE vs ALLAM INIFNITE INDIA PVT LTDDue to delay in possession I have to face many financial hardships by paying both Loan EMIs and House rents. So I pray to seek a complete Refund along with the Interest paid over the time till dateAUTHORITY22/07/2025
DIPAK SHAW vs allam infinite india pvt ltdDirect Builder to refund the amount paid as per RERA norms at the earliest .AUTHORITY22/07/2025
Mohammad Kashif vs M/S.ALLAM INFINITE INDIA PVT LTDI requesting this Hon'ble Authority to direct the respondent to complete and handover the flat, registration of sale deed and to pay interest on delay period.AUTHORITY22/07/2025
Anirban Sarkar vs MR.ANIRBAN SARKARTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY22/07/2025
Bhimi Ram vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deedAUTHORITY22/07/2025
Rajeev Ranjan vs M/s. Allam Infinite India Private LimitedCompletion of project as per the sale deed, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act.AUTHORITY22/06/2026
Nayan Prasad vs M/s. Allam Infinite India Private LimitedTo complete the project , obtain OC and handover the possession. To pay delay interest under section 18 (1) Provision of RERA Act.AUTHORITY22/06/2026
Biswajit Das vs M/s. Allam Infinite India Private LimitedInterest on delayed period as monthly payment - Relief to seek - Direction from the Authority - On completion - Sale deed to be executed in my favor followed by handover of allotted flat along with OCAUTHORITY22/06/2026
Arun Kumar Yadav R vs M/s. Allam Infinite India Private Limited(i) To complete the Project, obtain Occupancy Certificate and handover the possession of the Schedule Property at the earliest to the Complainants. (ii) To pay delay interest under Section 18 .AUTHORITY22/06/2026
Shibprasad Biswas vs ALLAM INFINITE INDIA PVT LTDRefund the amount paid along with interest for the cancellation of the booking.AUTHORITY22/06/2026
SIVANANTHAM RAJAN vs M/s. Allam Infinite India Private LimitedTo complete the Project,obtain OC and handover the possession.To pay delay interest under Section 18 (1) Provision of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY22/06/2026
Shyam Surendran vs M/s. Allam Infinite India Private LimitedKindly issue an order to the promoter to pay interest on delay period to me as monthly payment till delivery of the possession is completedAUTHORITY22/06/2026
SYED ZUBAIR AHMED vs M/s. Allam Infinite India Private LimitedProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY22/06/2026
Ramprasath vs M/s. Allam Infinite India Private LimitedKindly issue an order to the promoter to pay interest on delay period to me as monthly payments till delivery of the possession is completedAUTHORITY22/06/2026
SEEMA WAJID vs M/s. Allam Infinite India Private LimitedProject completion, obtain OC and handover the property. Seeking to pay Delayed Interest. On completion of project the sale deed to be executed in my/our name.AUTHORITY22/06/2026
Lupitha K U vs Allam Infinite India Private LimitedKindly issue an order to the promoter to interest on delay period to me as monthly payment till delivery of the possession is completedAUTHORITY22/04/2026
Naveen Kumar J vs GM AMBITIOUS ENCLAVESEEKING INTEREST ON DELAY PERIOD FORM PROMOTER TILL POSSESSION OF ALLOTTED APARTMENT IS COMPLETED AS MONTHLY PAYMENTSAUTHORITY22/01/2026
VINAY N vs ALLAM INFINITE INDIA PVT LTDi need to get my hard earn money with bank interestAUTHORITY22/01/2025
Sri M R Anantha Rao vs M/s. Allam Infinite India Private LimitedRefund of entire amount with interestAUTHORITY21/04/2026
Debi Prasad Das vs GM AMBITIOUS ENCLAVETo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act from 03 Oct 2022. On completion of project execute the sale deed.AUTHORITY21/01/2026
M U Subrahmanyam vs ALLAM INFINITE INDIA PVT LTDTo Cpmplete the Project, Obtain OC and handover the position To pay Delay Interest under section 18(1) provision of RERA act. To cancle the Covid -19 Extension Direction from the authority- on CompletAUTHORITY21/01/2026
Gopinath V vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY21/01/2026
Swaminathan Viswanathan vs M/S.ALLAM INFINITE INDIA PVT LTD & ANOTHERTo complete the Project, obtain Occupancy Certificate & Sale deed, handover the possession at the earliest. To pay delay interest under Section 18 (1) Provision of RERA Act on payments made by usAUTHORITY20/03/2026
Madhavi JR vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY20/03/2026
Rakesh Kumar Tiwari vs ALLAM INFINITE INDIA PVT LTDTo complete the project and obtain the occupancy certificate, then hand over possession to the buyer. To pay delayed interest per Section 18(1) of the RERA Act & execute the sale deed upon completion.AUTHORITY20/03/2026
Tamella naresh vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo Cpmplete the Project, Obtain OC and handover the position To pay Delay Interest under section 18(1) provision of RERA act. To cancle the Covid -19 Extension Direction from the authority- on CompletAUTHORITY20/03/2026
Nitesh Kumar Singh vs ALLAM INFINITE INDIA PVT LTDTo get paid delay Interest until OC received & request direction from the authority that on completion of the project sale deed to be executed in complainants favour.AUTHORITY20/03/2026
Siva Namachivayam vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deedAUTHORITY20/03/2026
Pradeep Kumar vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deedAUTHORITY20/03/2026
RAJ KUMAR PATHAK vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY20/03/2026
KALPANA GANGAM vs ALLAM INFINITE INDIA PVT LTDKindly issue an order to the promoter to pay the interest on delay period as monthly payments till the delivery of the possessions is completed.AUTHORITY20/03/2026
Leo Vijay vs ALLAM INFINITE INDIA PVT LTDinterest on delay periodAUTHORITY20/03/2026
Nazneen Yohan Bharucha vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY20/02/2026
P Preethi vs allam infinite india pvt ltdInterest on Delay PeriodAUTHORITY20/02/2026
Sumit Birajdar vs ALLAM INFINITE INDIA PVT LTDDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY20/02/2026
Rejo Thomas vs ALLAM INFINITE INDIA PVT LTDDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY20/02/2026
Priyanshu Mukherjee vs ALLAM INFINITE INDIA PVT LTDKindly issue an order to the promoter to pay me interest as monthly paymentAUTHORITY20/02/2026
Azimullah Beg vs ALLAM INFINITE INDIA PVT LTDTo complete the Project,obtain OC and handover the possession.To pay delay interest under RERA Act. To cancel the Covid-19 extension. On completion of project the sale deed to be executed in our name.AUTHORITY20/02/2026
PRAVEEN RAJ B vs ALLAM INFINITE INDIA PVT LTDDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favorAUTHORITY20/02/2026
Paritosh Tiwari vs ALLAM INFINITE INDIA PVT LTDTo complete the project, obtain OC and handover the possession. To pay delay interest under Section 18(1) Proviso RERA Act. On completion of the project, Sale Deed to be executed in my favor.AUTHORITY20/02/2026
MR ABHISHEK KAPOOR vs M/S.ALLAM INFINITE INDIA PVT LTDProject Handover as soon as possible and Interest on delay periodAUTHORITY19/03/2025
MR MOHAMMED FAISAL SHAH AND ANOTHER vs M/S.ALLAM INFINITE INDIA PVT LTDInterest on delay periodAUTHORITY19/03/2025
MR ALTAF HUSAIN SANADI vs M/S.ALLAM INFINITE INDIA PVT LTDReturn of the flat entire amount with interest or Ask the builder to pay the interest amount until the project is handed over to me.AUTHORITY19/03/2025
MR KASPA TARUN TEJA vs M/S.ALLAM INFINITE INDIA PVT LTDInterest on delay periodAUTHORITY19/03/2025
MR RAJAN KUMAR AND ANOTHER vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERSEEKING INTEREST ON DELAY PERIOD FROM PROMOTER TILL POSSESSION OF ALLOTTED APARTMENT IS COMPLETED AS MONTHLY PAYMENTSAUTHORITY19/03/2025
DEBAJIT DAS vs M/s. Allam Infinite India Private LimitedInterest on delay periodAUTHORITY18/06/2026
Mohan Kumar H N vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY18/03/2026
DEEPALI PATIL vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY18/03/2026
Sagar Goyal vs M/S ALLAM INFINITE INDIA PRIVATE LIMITEDCompensationAUTHORITY18/03/2025
ATUL ANAND vs GM AMBITIOUS ENCLAVEI need the refund of the amount paid to the builder and compensation of the interest paid to the banksAUTHORITY18/03/2025
Bibin Kurian Joy vs ALLAM INFINITE INDIA PVT LTDDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY18/02/2026
MR JAGDISH CHANDER GUPTA vs M/S.ALLAM INFINITE INDIA PVT LTDRefund of booking amount of Rs. 25000AUTHORITY18/02/2025
MS APURVA vs M/S.ALLAM INFINITE INDIA PVT LTDI want the builder to refund my 1lakh rupee booking amountAUTHORITY18/02/2025
MR HIMANSHU KUMAR vs M/S.ALLAM INFINITE INDIA PVT LTD1. Don't provide further extension and kindly include consumers voice before providing extension, 2. Help in expediting project completion and handoverAUTHORITY18/02/2025
MR ARVIND RAJAMANYA vs M/S.ALLAM INFINITE INDIA PVT LTDThat the Respondent to refund a sum of Rs 12,30,000/- along with interest to the Complainant from date of payment till date of realization.AUTHORITY18/02/2025
MR MANJUNATH.R vs M/S.ALLAM INFINITE INDIA PVT LTDIssue an order to the Builder to pay the interest on delay period to me as monthly payments until the delivery of possession is completed.AUTHORITY18/02/2025
Nikitha vs M/S.ALAM INFINITE INDIA PVT LTDI would like a compensation and full refund of the amount from the builder in the Amount of Rs 28 Lac/-AUTHORITY17/04/2025
Nitish Kumar vs ALLAM INFINITE INDIA PVT LTDNeed compensation for all the delays that has happened for more than 2 years now, as my investments are going in loss, and I am not able to take the possession of the same. Flat A1-03-16 & A2-04-03.AUTHORITY17/03/2026
Muzafferuddin VM vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY17/03/2026
Nandini P vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. Kindly issue order to Promoter to pay interest on delay periodAUTHORITY17/03/2026
Uma Shankar P vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. Kindly issue order to Promoter to pay interest as on delay period.AUTHORITY17/03/2026
Shamal AV vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain Occupancy Certificate and handover the possession of the Schedule Property at the earliest to the Complainants.AUTHORITY17/03/2026
Jithin N vs ALLAM INFINITE INDIA PVT LTDTo complete the project, obtain OC and handover the possession, To pay delay interest under section 18(1) Proviso of RERA Act. To cancel the Covid 19 extension. On completion of the sale deed.AUTHORITY17/03/2026
RIZWAN MOHAMMED vs ALLAM INFINITE INDIA PVT LTDInterest on delay periodAUTHORITY17/03/2026
Divya B vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my name.AUTHORITY17/03/2026
Shashi Anand Chakilam vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. On completion of project the sale deed to be executed in my/our name.AUTHORITY17/03/2026
Vamshi Anand Chakilam vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. To pay delay interest under Section 18 (1) Proviso of RERA Act. On completion of the project the sale deed to be executed in our name.AUTHORITY17/03/2026
GANESH LAXMAN KHARAT vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain Occupancy Certificate and handover the possession of the Schedule Property at the earliest and pay delay interest on payments made by the Complainants.AUTHORITY17/03/2026
Uday Pratap Singh vs ALLAM INFINITE INDIA PVT LTDDelayed interest- Relief to seek- Direction from Authority- On completion of project - sale deed to be executed in complainants favour.AUTHORITY17/02/2026
Ankita Kacholia vs M/S.ALLAM INFINITEDirect the builder to compensate me for the amount paid including interest and additional costs incurred due to delay.AUTHORITY17/02/2026
Umadevi S Sure vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act.AUTHORITY17/02/2026
Veeresh Babu P N vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY17/02/2026
K Sumit vs ALLAM INFINITE INDIA PVT LTDDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY17/02/2026
GOKUL A vs ALLAM INFINITE INDIA PVT LTDComplete the project in all aspects as agreed in the Agreement of Sale and construction agreement and Brochures along with OC and Delay period interestAUTHORITY17/02/2026
Abhijit Ghosh vs M/S.ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY16/08/2025
Vandana K vs M/S.ALLAM INFINITE INDIA PVT LTDInterest on delay periodAUTHORITY16/08/2025
Indranil Chakraborty vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deedAUTHORITY16/08/2025
Vijay Kumar vs M/S.ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act.To cancel the Covid-19 extension.On completion of project the sale deeAUTHORITY16/08/2025
Shirali Gowda vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY16/08/2025
NEHA VIJAYKUMAR ANTIN vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Provision of RERA Act. To cancel the Covid-19 extension.Sale deed to be executed in my favor.AUTHORITY16/08/2025
Debasmita Mazumdar vs M/S.ALLAM INFINITE INDIA PVT LTDinterest on delay periodAUTHORITY16/08/2025
Anurag Bansal vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY16/08/2025
KARIA NAIMISH RAMESHBHAI vs M/S.ALLAM INFINITE INDIA PVT LTDTo complete the Project obtain OC and handover the possession. To pay delay interest under Section 18 (1) Provision of RERA Act. To cancel the Covid-19 extension. Completion of project and sale deedAUTHORITY16/08/2025
Rajesh Balachandran vs M/S.ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. Request to have hearings done via Online Mode due to my disabilityAUTHORITY16/08/2025
Arpan Das vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY16/08/2025
Arvind Singh vs M/S.ALLAM INFINITE INDIA PVT LTDTo complete the Project obtain OC and handover the possession. To pay delay interest under Section 18 (1) Provision ofRERA Act. To cancel the Covid-19 extension. Completion of project and sale deedAUTHORITY16/08/2025
Sumita Bhattacharjee vs M/S.ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and hand over the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deeAUTHORITY16/08/2025
Feroze Khan Bahamany vs ALLAM INFINITE INDIATo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY16/01/2026
Priti Agarwal vs Dated 12th June 2026Direction of authority on completion of project - sale deed to be executed in my favour -interest on delayed deliveryAUTHORITY15/06/2026
Syed Danish Kamal vs Azeem InfiniteTo initiate complete refund of the amount paid till date as per consolidated payment receipt and to pay delay interest under Section 18 (1) Proviso of RERA Act and to pay the adequate compensationAUTHORITY15/06/2026
Abhishek Kumar vs M/s. Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY15/06/2026
Savita Singh vs GM AMBITIOUS ENCLAVEWanted Full Refund with interestAUTHORITY15/05/2025
Ravi Kumar Rai vs M/S.ALLAM INFINITE INDIA PVT LTD1) Interest on delay period (2) Clear & final commitment Date of possession (3). Proof of further RERA extension application (4) Pay off for Subsequent direct loss incurredAUTHORITY14/08/2025
Shafeeq Ur Rehman vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHER1. Seeking Interest on delayed period from promoter till possession of flat allotment. 2. Complete the project & handover the flatAUTHORITY14/08/2025
SOUMYA RANJAN PRIYADARSHI vs GM AMBITIOUS ENCLAVENEED REFUNDAUTHORITY14/03/2025
AGAMYA PRATAP SHUKLA vs ALLAM INFINITE INDIA PVT LTDNeed my booking amount (25000) refundAUTHORITY14/03/2025
AMIT SHARMA vs ALLAM INFINITE INDIA PVT LTDWe require a refund of our token amount of 50,000 Rs along with compensation,AUTHORITY14/03/2025
Mohammed Shafeeq MK vs gm ambitious enclaveRequesting RERA to get refund from the property along with interestAUTHORITY14/03/2025
Mr shaharukh Hasan Nadaf vs GM AMBITIOUS ENCLAVERefund entire money with interestAUTHORITY14/03/2024
Rashmi U vs M/S.ALLAM INFINITE AND OTHERSComplainant would like to Revoke the contract due to breach of material terms, pendency of bankruptcy and compensationAUTHORITY13/11/2025
MR.AVINASH BHASKAR RAO BHARDWAJ & ANOTHER vs M/S.ALLAM INFINITE INDIA PVT LTDCancel the Agreements and refund the entire amount of 19,61,674/- along with interest @ 12% and penal interest @ 2% and award damages of Rs. 19,00,000/-AUTHORITY13/11/2023
MR.SACHIN.M vs MS/.ALLAM INFINITE INDIA PVT LTDKindly get the advance amount of 25000 rupees refunded from builderAUTHORITY13/11/2023
MR MAHESH BABU.A vs M/S.ALLAM INFINITE INDIA PVT LTDRequest for the refund, amount i have paid along with interest which i paid to bank.AUTHORITY13/11/2023
Laxman Ubriomal Chawla vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERFor specific performance of agreement of sale dated 09/07/2019 with respect to the said property and direct the respondents to execute the sale deed and also pay interest @ 18% on delayed periodAUTHORITY13/10/2025
Suresh Kumar vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest. On completion of project the sale deed to be executed in my/our name.AUTHORITY13/07/2026
Praveen Kumar S vs ALLAM INFINITE INDIA PVT LTDCompensation - Interest for Delay in handoverAUTHORITY13/07/2026
Praveen Kumar Gupta vs Allam Infinite India Private LimitedInterest on delayed periodAUTHORITY13/07/2026
Manju Devi Purushottam Malpani vs gm ambitious enclavePossession of flat along with interest on delay and compensation for mental harrasemenetAUTHORITY13/07/2026
AMULYA K. MURTHY vs M/S ALLAM INFINITE INDIA PRIVATE LIMITEDPlease look into construction quality since each floor is constructed in 3-4 weeks. Also, I'm seeking RERA's help to instruct Promoter to demand remaining amount only by the end of 2021.AUTHORITY13/05/2024
PRASANNA KUMAR K S vs Allam Infinite India Private LimitedKindyy Issue an Order to a Promoters to Pay "Interest Delay Period" to us as monthly payments till delivery of the possession is completedAUTHORITY13/04/2026
John Kennady vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY13/04/2026
NANDAN MANISH PARAB vs Allam Infinite India Private LimitedKindly issue an order to the promoter to pay interest on delay period to me as monthly payments till delivery of the possession is completed.AUTHORITY13/04/2026
Anil Kumar vs Allam Infinite India Private LimitedSeeking the interest on the delay period from the promotor till the possession of allotted apartment is completed as monthly paymentAUTHORITY13/04/2026
Sreekanth Boya vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deedAUTHORITY13/04/2026
KISHOR MADHAVARAJ vs Allam Infinite India Private LimitedProject completion, obtain OC and handover the property. Seeking Delayed Interest. On completion of project the sale deed to be executed in my name.AUTHORITY13/04/2026
MS NEERAJ SHARMA vs Allam Infinite India Private LimitedThe Complainant seeks to avail the remedy of Interest on the Delay Period, computed on the Sale Consideration paid by her from the date 03/04/2022, in terms of S.18(1) of the RERA Act., 2016AUTHORITY13/04/2026
Divinder Kaur vs Allam Infinite India Private LimitedTo Complete the project, obtain OC and handover the possession. To pay delay interest under Section 18(1) Proviso of RERA Act. To Cancel Covid 19 Exentsion. On Completion of the project sale deed.AUTHORITY13/04/2026
SAJUJOHN BABYVARGHESE PALLATH vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA ActAUTHORITY13/04/2026
REJIL M R vs M/S. ALLAM INFINITE INDIA PRIVATE LIMITEDRefund of Rs.50000/- (Fifty thousand rupees) which is the booking amount.AUTHORITY13/03/2023
Isita Madanlal Mahajan vs Allam Infinite India Pvt LtdTo complete the Project as per Sales deed, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.AUTHORITY13/02/2026
Anil Furtado vs Allam Infinite India Pvt LtdSeeking relief in the form of interest on the delay period from the builder, with a directive from the Authority. Upon project completion, the sale deed must be executed in my favour.AUTHORITY13/02/2026
Krishna Teja Taduri vs Allam Infinite India Pvt LtdDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY13/02/2026
Mehul Srivastava vs ALLAM INFINITE INDIA PVT LTDDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY13/02/2026
Shaik Sumera Begum vs Allam Infinite India Pvt Ltd•To complete Project, obtain OC and handover the possession • To pay delay interest under Section 18 (1) Provision of RERA Act • The Sale deed to be executed in our favour • Online Hearing RequestedAUTHORITY13/02/2026
Ankuj Rana vs Allam Infinite India Pvt LtdTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension on completion of project the sale deed.AUTHORITY13/02/2026
Shivam Gopal vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERKindly issue an order to the promoter to pay Interest on delay period to me as monthly payments till delivery of the possession is completed.AUTHORITY12/08/2025
Mandar Anil Joshi vs M/S.ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act.AUTHORITY12/08/2025
Mayura P S vs M/S.ALLAM INFINITE INDIA PVT LTDi am expecting full refund with interestAUTHORITY12/08/2025
Shipra Yadav vs M/S.ALLAM INFINITE INDIA PVT LTDI need refund with all the interest I paid to bank and compensation.AUTHORITY12/08/2025
KRIJESH P V vs M/S.ALLAM INFINITE INDIA PVT LTD AND OTHERSDelayed period interest and possession of schedule propertyAUTHORITY12/08/2025
C NITHIN NAMBIAR vs M/S.ALLAM INFINITE INDIA PVT LTD AND OTHERSDelayed Period Interest and Possession of Schedule PropertyAUTHORITY12/08/2025
SREEJITH P vs M/S.ALLAM INFINITE INDIA PVT LTD AND OTHERSDelayed Period Interest and Possession of Schedule PropertyAUTHORITY12/08/2025
HARI SANKAR PATI vs M/S.ALLAM INFINITE INDIA PVT LTD AND OTHERSTotal amount including interest calculated as on 21/12/2024- Rs 5816200.96AUTHORITY12/08/2025
PRASHANTH B PILLAI vs M/s. Allam Infinite India Private LimitedInterest on delay periodAUTHORITY12/06/2026
A shalini vs M/s. Allam Infinite India Private LimitedDelay compensation & handover flat soon.AUTHORITY12/06/2026
ATUL ANAND vs M/s. Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Provison of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deedAUTHORITY12/06/2026
Mrs SHUBHANGI NAYAK S vs M/s. Allam Infinite India Private Limitedrefund of amount with interest and return the loan money to BankAUTHORITY12/06/2026
Vachanashree vs M/s. Allam Infinite India Private LimitedInterest on delay is expected from builder until actual possession date, as we are unable to pay both EMI of flat purchased and place where we are staying on rent due to builder's false promise.AUTHORITY12/06/2026
Prithviraj K vs M/s. Allam Infinite India Private LimitedProject completion, obtain OC and handover the property. Seeking Interest on Delay period. On completion of project the sale deed to be executed in our name.AUTHORITY12/06/2026
Agnes Pandiyan vs M/s. Allam Infinite India Private LimitedKindly issue an order to the promoter to pay interest on delay period to me as monthly payment till delivery of the possession is completed.AUTHORITY12/06/2026
ANUJ KUMAR SAHAY vs M/s. Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY12/06/2026
Jayshree Pillai vs GM AMBITIOUS ENCLAVEIn case if it is going to take morethan a year from today. I would request to compensate my complete amount pad to builder with the interest paid to bank , with complete closure of bank loan and theAUTHORITY12/03/2024
SHOBHIT SINGH vs Allam Infinite India Pvt LtdDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favour.AUTHORITY12/02/2026
Manroop Singh Sehmi vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY12/02/2026
Adnan Asif vs Allam Infinite India Pvt LtdTo complete the Project, obtain OC and handover the possession. To pay delay interest under RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed to be executed in my nameAUTHORITY12/02/2026
RAVI BHUSHAN TIWARY vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. Need delayed interest compensation and flat.AUTHORITY11/09/2025
MD Waseem Akthar vs GM AMBITIOUS ENCLOAVENothingAUTHORITY11/07/2022
Pradeep kumar vs Allam infinite India Pvt LtdTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deedAUTHORITY11/03/2026
Ankur Goel vs M/S.ALLAM INFINITE INDIA AND ANOTHERDirect Respondent to pay delay interest and hand over possession with Occupancy Certificate.AUTHORITY11/02/2026
Parul YAdav vs M/S.ALLAM INFINITE INDIA PVT LTDPlease help in providing interest on delay periodAUTHORITY10/11/2025
Remus Devasagayam vs ALLAM INFINITE PVT LTDKindly issue an order to the promotor to pay interest on delay period to me as monthly payment till delivery of the possession is completedAUTHORITY10/07/2026
Awadesh pawan tiwari vs M/s. Allam Infinite India Private LimitedInterest on delay period till flat handoverAUTHORITY10/06/2026
Muttanapalli venkata chaitanya sharma vs M/s. Allam Infinite India Private LimitedKindly issue and order to the promoter to pay interest on delay period till delivery of the possession is completedAUTHORITY10/06/2026
Pranavi Singh vs M/s. Allam Infinite India Private LimitedProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY10/06/2026
Iqbal K Jamadar vs M/s. Allam Infinite India Private LimitedKindly issue an order to the promoter to pay interest on delay period till delivery of the possession is completed.AUTHORITY10/06/2026
T J VIMALA RAO vs M/s. Allam Infinite India Private LimitedKindly issue an order to the promoter to pay interest on delay period to me as monthly payment till delivery of the possession is completed.AUTHORITY10/06/2026
Anjali C vs M/s. Allam Infinite India Private LimitedProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in our name.AUTHORITY10/06/2026
Subramani MA vs M/s. Allam Infinite India Private LimitedKindly issue an order to the promoter to pay interest on delay period to me as monthly payment till delivery of the possession is completed.AUTHORITY10/06/2026
Vanapalli Dinesh vs M/s. Allam Infinite India Private LimitedKindly issue an order to the promoter to complete the project and to pay interest on delay period untill the handover of the flat.AUTHORITY10/06/2026
MR SUNIL MANOHAR BAJAJ vs M/s. Allam Infinite India Private LimitedComplainants are seeking Interest on Delay Period commencing from 03/10/2022 in terms of S.18 of the RERA Act,2016AUTHORITY10/06/2026
Rajeev Ranjan vs M/S.ALLAM INFINITE INDIA PVT LTD.Interest on Project delay periodAUTHORITY10/06/2025
Atul Kumar Sharan vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Provision of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deAUTHORITY10/04/2026
Dipan Kangsa Banik vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY10/04/2026
Sharath Singh vs Allam Infinite India Private Limited1. Possession of the flat; 2. Interest at 24% p.a. on total amount paid for the delay in delivery of possession; 3. Compensation of Rs. 3,07,56,688/- for the mental agony caused.AUTHORITY10/04/2026
PRADEEP ALAGILAVAADA MATADHA vs Allam Infinite India Private LimitedKindly issue on order to Promoter on: Project completion,Obtaiining OC, To pay interest on delay period to me on monthy paymeny till delivery of the pocession,The Sale deed to be executed in our name.AUTHORITY10/04/2026
Koel Basu vs ALLAM INFINITE INDIA PVT LTDDelay Interest - Relief to seek - On receiving occupancy certificate sale deed to be executed in Complaints favorAUTHORITY10/02/2026
SUJIT KUMAR vs M/S ALLAM INFINITE INDIA PRIVATE LIMITEDConfirmation for Final Date of Completion of the project or it will extend further . If it will extend further then I might face financial issues .AUTHORITY09/10/2023
Prasanta Kumar Sahoo vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession at the earliest to the Complainants.To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.AUTHORITY09/03/2026
M U SUBRAHMANYAM vs GM AMBITIOUS ENCLAVERTo Cpmplete the Project, Obtain OC and handover the position To pay Delay Interest under section 18(1) provision of RERA act. To cancle the Covid -19 Extension Direction from the authority- on CompletAUTHORITY09/03/2026
Ajay Venugopal vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. Sale deed to be executed in my favour after project completion.AUTHORITY09/03/2026
Arivupathi R vs Allam Infinite India Private LimitedTo complete the project, Obtain occupancy certificate and handover possession to the compliant, To pay delay Intrest as per RERA , pay litigation expenses and cancel Covid-19 extension.AUTHORITY09/03/2026
Rohit Ojha vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY09/03/2026
Mahesh P Naik vs GM AMBITIOUS ENCLAVETo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deedAUTHORITY09/03/2026
MOHAMMAD ABU SHARIQUE vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deedAUTHORITY09/03/2026
Dr PUNITH CARIAPPA vs ALLAM INFINITE INDIA PVT LTDTo complete the project, obtain OC and handover possession. To pay delay interest under section 18(1) proviso of RERA Act.AUTHORITY09/03/2026
Aditya S Varma vs ALLAM INFINITE INDIA PVT LTDThe respondent shall pay interest for the delay period until possession upon receiving the OC, and the sale deed shall be executed in favour of the complainantAUTHORITY09/03/2026
Chandra Shekhar Behera vs Allam Infinite India Pvt Ltd.,To complete the Project, obtain OC and handover the possession. Pay delay interest under Section 18(1) Provision of Rera Act. To cancel the covid-19 extension, on completion of project the sale deed.AUTHORITY09/03/2026
C Santhi vs GM AMBITIOUS ENCLAVEinterest on delay periodAUTHORITY09/03/2026
G V Manooj vs GM AMBITIOUS ENCLAVEinterest on delay periodAUTHORITY09/03/2026
Amish Adhikrao Sutar vs GM AMBITIOUS ENCLAVETo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deedAUTHORITY09/03/2026
Ajay Gopichand Dange vs Allam Infinite India Private LimitedKindly issue an order to the promoter to pay interest on delay period to me as monthly payment till delivery of the possession is completed.AUTHORITY09/03/2026
ROHIT VERMA vs ALLAM INFINITE INDIA PVT LTDTo complete Project, obtain OC and possession. To pay delay interest under Section 18 (1) of RERA Act. To cancel Covid-19 extn. On completion of Project - Sale deed to be executed in my favourAUTHORITY09/03/2026
Venkata Appa Rao Gajjarapu vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY09/03/2026
Venkata Appa Rao Gajjarapu vs Allam Infinite India Pvt Ltd.,Project completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY09/03/2026
AMIT VIJAYKUMAR DESAI vs ALLAM INFINITE INDIA PVT LTDTo complete the project obtain OC and handover the possession. To pay delay interest under Section18(1) Proviso of RERA Act. To cancel the Covid-19 extension. On competion of project the sale deed.AUTHORITY09/02/2026
Vaibhav S B vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY09/02/2026
Dilip Kumar Burman vs Allam Infinite India Pvt LtdTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY09/02/2026
M Sai Chaitra vs gm ambitious enclaveTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY09/02/2026
MS Kruthi Jayakumar vs ALLAM INFINITE INDIA PVT LTDRelief to seek- Direction from the Authority - on completion of project - sale deed to be executed in my favour-obtain OC and handover the possession.AUTHORITY09/02/2026
Govind Narayan vs GM AMBITIOUS ENCLAVEseeking interest on delay period from promoter till Possession of flat is Handed over as Monthly PaymentsAUTHORITY08/11/2024
Niranjan S vs M/s. Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY08/07/2026
Ruchi Roy vs M/s. Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deedAUTHORITY08/07/2026
YOGESH SAPALIGA vs GM Ambitious EnclaveProject completion, obtain OC and handover the property. Seeking Delayed Interest. On completion of project the sale deed to be executed in my/our name.AUTHORITY08/07/2026
Lakshmi Nagendra vs ALLAM INFINITE INDIA PVT LTDRefund of amounts paid with interestAUTHORITY08/07/2026
Ravikumar kubusada vs Allam Infinite India Private LimitedPromoter to complete project obtain Occupancy Certificate and hand over Unit A1-05-25. Pay delay interest from Oct-3-2022 until possession reimburse RS 1 Lack for litigation and cancel Covid extensionAUTHORITY08/04/2026
Balakarthikeyan B vs Allam Infinite India Private Limitedkindly issue an order to the promoter to pay interest on delay period to me as monthly payments.AUTHORITY08/04/2026
Vandana Rathod vs Allam Infinite India Private LimitedDirect the Promoters and the Builder to pay delay interest at the rate prescribed under RERA or as deemed appropriate by this Hon'ble Authority. And to complete the Project, obtain OC and handover.AUTHORITY08/04/2026
Sathish Kumar P vs Allam Infinite India Private LimitedDirect Respondents to complete the Project, obtain OC, handover possession of Unit A2-07-24, pay delay interest per Section 18(1) of RERA, and cancel the 9-month Covid-19 extension.AUTHORITY08/04/2026
A K Kaushik Annambhotla vs Allam Infinite India Private LimitedProject completion, obtain OC and handover the property. Seeking Delayed Interest. On completion of project the sale deed to be executed in my/our name.AUTHORITY08/04/2026
NIDHI RAHANGDALE vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY08/04/2026
ANKIT KAMRA vs M/S.ALAM INFINITE INDIA PVT LTD.To complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY07/07/2026
Sachin Gupta vs m/s.alam infinite indiaTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY07/07/2026
Bharath Kumar KN vs M/S.ALAM INFINITE INDIA PVT LTD.I request builder to pay all the monthly homeloan EMI I paid so far and pay 15,00,000/- as interest on delay period.AUTHORITY07/07/2026
patel rohitkumar chaturdas vs M/S.ALAM INFINITE INDIA PVT LTD.Project completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY07/07/2026
RAVI KANT SHARMA vs M/S.ALAM INFINITE INDIA PVT LTD.SEEKING REFUND OF DEPOSITED AMOUNT WITH INTEREST AGAINST FLAT CANCELLATIONAUTHORITY07/07/2026
Shubham Raj vs M/S.ALAM INFINITE INDIA PVT LTD.Project completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY07/07/2026
Ruby Bhati vs M/S.ALLAM INFINITE AND ANOTHERAsk builder give my flat possession and Interest for the delay periodAUTHORITY07/07/2026
PAZHANIYAPPAN RAJAN vs M/S.ALLAM INFINITE INDIA AND ANOTHERTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deedAUTHORITY07/07/2026
ASHISH KUMAR SHARAN vs ALLAM INFINITE INDIA PVT LTDTo complete the Project and obtain OC and handover the possession. To pay delay interest under Section 18 (1) Provison of RERA Act. To cancel the Covid-19 extension on completion of projectAUTHORITY07/04/2026
Kapil Mohan vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. To execute Sale deed in my name.AUTHORITY07/04/2026
Pattanjali Verma vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Provison of RERA Act.AUTHORITY07/04/2026
CHANDRALEKHA CHAKRABORTY vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY07/04/2026
Santhakumar Ramasamy vs Allam Infinite India Private LimitedProject completion, obtain OC and handover the property. seeking delayed interest on completion of the project and the sale deed to be executed in my/our nameAUTHORITY07/04/2026
Varsha A Joshi vs M/s.Allam Infinite India Pvt Ltd & anotherTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY06/10/2025
Bhabesh Lahkar vs M/s.Allam Infinite India Pvt Ltd & anotherInterst on Delay PeriodAUTHORITY06/10/2025
Santosh M vs M/s.Allam Infinite India Pvt Ltd & anotherTo pay delay interest under section 18 (1) proviso of RERA Act. To cancel the Covid 19 extension. On completion of the project,the sale deed to be executed in my favour.AUTHORITY06/10/2025
Jacob P A vs M/s.Allam Infinite India Pvt Ltd & anotherTo pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of the project, the sale deed to be executed in my favour.AUTHORITY06/10/2025
NAGENDRA C vs M/s.Allam Infinite India Pvt LtdDelayed Interest - Relief to Seek- Direction from Authority - on Completion of Project- Sale deed to be executed in my favourAUTHORITY06/10/2025
Dinesh CS vs M/s.Allam Infinite India Pvt Ltd & anotherDirect Respondents to complete the Project, obtain OC, handover possession of Unit A2-06-23, pay delay interest per Section 18(1) of RERA, and cancel the 9-month Covid-19 extension.AUTHORITY06/10/2025
Aditi Khanna vs M/s.Allam Infinite India Pvt Ltd & anotherProject completion, obtain Occupancy Certificate and pay delay interest on Rs. 28,89,375/- to be calculated from October 03, 2022 until the actual date of handover and possession of the Unit B2-10-19AUTHORITY06/10/2025
Mohammed Shadab Vaseem vs M/s.Allam Infinite India Pvt Ltd & anotherTo Complete the project Obtain Occupancy certificate hand over the possession , To pay delay Interest under Section 18(1) of rera act and to cancel Covid19 Extexecute sale deedonproject completionAUTHORITY06/10/2025
Halingali Vidyasagar Bharat vs M/s.Allam Infinite India Pvt Ltd & anotherTo complete Project obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act To cancel the Covid19 extension and on completion of the Project the sale deedAUTHORITY06/10/2025
CHANDRA MOHAN SIDDHA vs M/S.ALAM INFINITE INDIA PVT LTD.To complete the project , obtain OC and handover the possession . To pay delay interest under section 18 (1) provison of RERA Act.AUTHORITY06/07/2026
Sameer Bansal vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act.AUTHORITY06/04/2026
Srikrishna Yedavalli vs Allam Infinite India Private LimitedOversee completion of project as per specs, OC, sale deed to be executed in our favor, handover possession and to compensate with interest as per Sec 18(1) of RERA act, for the delayed timeAUTHORITY06/04/2026
Vivek Nagarajachar Venkatesh vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. On completion of project the sale deed.AUTHORITY06/04/2026
MAHESH M K vs Allam Infinite India Private LimitedKindly issue an order to the promoter to pay interest on delay period to me as monthly payment till delivery of the possession is completed.AUTHORITY06/04/2026
Remya Nair vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under RERA Act. On completion of project the sale deed to be executed my name.AUTHORITY06/03/2026
Rakesh Kumar vs Allam Infinite India Pvt LtdDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY06/03/2026
Elanthiraian Ramaraj vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deedAUTHORITY06/02/2026
PARIKH PRITESHKUMAR ISHVARBHAI & PARIKH RITA PRITESHKUMAR vs ALLAM INFINITE INDIA PVT LTDRefund of the amount of Rs. 30,81,645/- along with applicable interest and damages/compensation along with litigation cost.AUTHORITY06/02/2024
Ishtiaque Kabir Mondal vs M/s.Allam Infinite India pvt ltdRefund of entire paid amount with interest, plus additional compensation to be provided as per Prevailing market rate. (Purchased 37lacs flat in E.City is now 60 Lacs in Dec'24)AUTHORITY05/02/2026
Murali M C vs M/S.ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deeAUTHORITY05/02/2026
Rekha Bhusad vs ALLAM INFINITE INDIA PVT LTDPrays to help govern project to completetion and direct respondents to pay delay interest on payments made until the actual date of handover and possession of the Unit bearing No. A2-01-32AUTHORITY05/02/2026
Himanshu Kumar vs ALLAM INFINITE INDIA PVT LTDInterest on delayed periodAUTHORITY05/02/2026
Pooja Panthri vs ALLAM INFINITE INDIA PVT LTDComplete Project, obtain OC, handover possession. Pay delay interest under Section 18 (1) Proviso of RERA Act. Cancel Covid-19 extension. On completion of project sale deed to be executed in my favourAUTHORITY05/02/2026
Akhilesh S Varma vs ALLAM INFINITE INDIA PVT LTDThe respondent shall pay interest for the delay period until possession upon receiving the OC, and the sale deed shall be executed in favor of the complainant.AUTHORITY05/02/2026
ankit vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY05/02/2026
K Vijay vs ALLAM INFINITE INDIA PVT LTDDelayed interest- Relief to seek - Direction from Authority- On completion of project- Sale deed to be executed in my favourAUTHORITY05/02/2026
SUREKHA SATISH KALE vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY05/02/2026
Pavan DS vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Provision of RERA Act. To cancel the Covid19 extension on completion of the project sale deedAUTHORITY05/02/2026
PUSHPALATHA O vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in our name.AUTHORITY05/02/2026
MR KARTHIK ND AND ANOTHER vs M/S.ALLAM INFINITE INDIA PVT LTDInterest on delay period and handovering the flat as per the sale & construction agreementAUTHORITY04/12/2024
RUPAYAN NATH vs GM AMBITIOUS ENCLAVEI want my hard earned money to be refunded to me.AUTHORITY04/09/2024
JEAN DOMINIC vs GM AMBITIOUS ENCLAVETo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY04/08/2025
Apurba Gorai vs gm ambitious enclaveTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY04/03/2026
Sukumari P vs GM AMBITIOUS ENCLAVERDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY04/03/2026
Tilat Majid Motorwala vs M/s. Allam Infinite India Private LimitedRelief Sought For: To complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of prAUTHORITY04/03/2026
Shirajaahmed J Neeralgi vs GM AMBITIOUS ENCLAVE(i)To complete the Project (ii) To pay delay interest under Section 18 (1) Proviso of RERA Act (iii)To pay Rs. 1,00,000/- towards the legal expenses incurre by the ComplainantsAUTHORITY03/09/2025
CR PRADEEP vs M/s. Allam Infinite India Private LimitedKindly issue an order to the Promoter to pay Interest on delay PeriodAUTHORITY03/06/2026
HARPANAHALLI MAHESH BABU vs M/s. Allam Infinite India Private LimitedProject completion, Obtain OC and handover the property. Seeking Delayed Interest. On completion of the project, the sale deed to be executed in our nameAUTHORITY03/06/2026
Veda Prakash Sathyanarayana vs GM AMBITIOUS ENCLAVEwe are requesting to arrange entire amount with eligible interest in the project.AUTHORITY03/06/2025
Anitha Adiraj vs GM AMBITIOUS ENCLAVETo complete the project, obtain the (OC) and hand over possession,Delay interest under RERA Act to be paid, the sale deed should be executed in my name upon project completion, cancel the COVId extenAUTHORITY03/03/2026
ASHA K S vs GM AMBITIOUS ENCLAVETo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension. On completion of project the sale deedAUTHORITY03/03/2026
M Sai Chaitra vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deedAUTHORITY03/03/2026
Amit Kumar vs Allam Infinite India Private LimitedSeeking Delayed Interest.Project completion, obtain OC and handover the property.On completion of project the sale deed to be executed in my/our favour.AUTHORITY03/03/2026
Madivada Pallavi vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deedAUTHORITY03/03/2026
Indrani Naidu vs GM AMBITIOUS ENCLAVEDirection from the Authority for Complete Refund due to delayed project. Also, seeking Delayed Interest.AUTHORITY03/03/2026
firdous Jabeen I vs GM AMBITIOUS ENCLAVEinterest on delay periodAUTHORITY03/03/2026
Ajit V Mathapati vs gm ambitious enclaveKindly issue an order to the promoter to pay me the interest on delay period as monthly payments till delivery of possession is completedAUTHORITY03/03/2026
Anilsekhar Chandrasekharan vs gm ambitious enclaveSEEKING INTEREST ON DELAY PERIOD FROM PROMOTER TILL POSSESSION OF FLAT IS HANDED OVER AS MONTHLY PAYMENTSAUTHORITY02/12/2024
Chintakuntla Shravan Reddy vs TOWNS VILLESEEKING INTEREST ON DELAY PERIOD FROM PROMOTER TILL POSSESSION OF ALLOTTED APARTMENT IS COMPLETED AS MONTHLY PAYMENTSAUTHORITY02/12/2024
Jitendra Kumar vs Allam Infinite India Private LimitedProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY02/04/2026
RGirish vs M/S.ALLAM INFINITE INDIA PVT LTD AND ANOTHERPrays for help with Delay in Possession, Delay interest, Pre-EMI refund and incorrect demand note raisedAUTHORITY02/03/2026
DWAIPAYAN ROY vs GM AMBITIOUS ENCLAVETo complete the Project, obtain OC and handover the possession at the earliest to the Complainant.To pay delay interests under Section 18 (1) Proviso of RERA Act..AUTHORITY02/03/2026
Basappa vs Allam Infinite India Private LimitedTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deedAUTHORITY02/03/2026
Shreepada U vs Allam Infinite India Private LimitedDirect the Promoters and the Builder to pay Delay interest at the Rate prescribed under the Rera or as deemed appropriate by this Hon'ble Authority & to Complete the Project , obtain OC and HandoverAUTHORITY02/03/2026
Prashant Sharma vs ALLAM INFINITE INDIA PVT LTDDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favourAUTHORITY02/02/2026
SYED NAJAF IMAM vs ALLAM INFINITE INDIA PVT LTDSeeking interest on delay period from the promotor till possession of allotted apartment and an order to execute sales deed in my favour on completion of the projectAUTHORITY02/02/2026
Satheesh Kumar M vs ALLAM INFINITE INDIA PVT LTDDelayed interest - Relief to seek - Direction from the Authority - On completion of Project - Sale deed to be executed in my favorAUTHORITY02/02/2026
John Pullack Routray vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our nameAUTHORITY02/02/2026
Md Danish Reza vs ALLAM INFINITE INDIA PVT LTDTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY02/02/2026
Pramod Madhavan V C vs ALLAM INFINITE INDIA PVT LTDProject completion, obtain OC and handover the property. Seeking Delayed Interest.On completion of project the sale deed to be executed in my/our name.AUTHORITY02/02/2026
SYED BAQER IMAM vs ALLAM INFINITE INDIA PVT LTDSeeking interest on delay period from the promotor till possession of allotted apartment and an order to execute sales deed inmy favour on completion of the projectAUTHORITY02/02/2026
Abinash Sahoo vs GM AMBITIOUS ENCLAVERequesting to take necessary action against the builder and compensate buyer by providing the appropriate amount of interest paidAUTHORITY01/07/2025
Shashi Kant Danwar vs ALAM INFINITE INDIA PVT LTDCompletion of projects as soon as possible and interest on delay as per Agreement until possession is not provided.AUTHORITY01/07/2025
Asish Chakraborty vs Allam Infinite India Private LimitedSeeking interest on delay period from the promotor till possession of allotted apartment is completed as monthly paymentsAUTHORITY01/04/2026
Santosh Kumar vs Allam Infinite India Pvt LtdTo complete the Project, obtain OC and handover the possession. To pay delay interest under Section 18 (1) Proviso of RERA Act. To cancel the Covid-19 extension.On completion of project the sale deed.AUTHORITY01/04/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (28 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190211/0002102
11-02-2019
Fraudulent Cancellation of Booking and Misappropriation of Amount PaidGM AMBITIOUS ENCLAVEDISPOSED AO
CMP/190228/0002314
28-02-2019
IIFL bank has given more money as a pre emiGM AMBITIOUS ENCLAVEDISPOSED AO
CMP/190430/0002813
30-04-2019
Refund was promised when cancelling flatGM AMBITIOUS ENCLAVEDISPOSED AO
CMP/190607/0003250
07-06-2019
Refund of Booking Amount of Rs 25000GM AMBITIOUS ENCLAVEDISPOSED AO
CMP/190607/0003253
07-06-2019
Request for cancellation of booked flat and refund is not accepted by the builderGM AMBITIOUS ENCLAVEDISPOSED AO
CMP/190713/0003563
13-07-2019
Request for Return of Payment against the PropertyGM AMBITIOUS ENCLAVEDISPOSED AO
CMP/190721/0003596
21-07-2019
Refund of money paid on cancellation of Flat BookingGM AMBITIOUS ENCLAVEDISPOSED AO
CMP/190730/0003699
30-07-2019
Refund of the Amount PaidGM AMBITIOUS ENCLAVEDISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectMr.Jayaprakash Narayan-20015th A Block, Koramangala- 560095
ContractorGM Infinite Dwelling (India) Pvt Ltd-20071st Stage. 1st Phase, Bangalore-560068.
Structural engineerMr.B.E.Pruthviraja---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹29.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Nanik Motwani Marg, Fort Mumbai. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Electronic City2 km
Bellandur–Marathahalli belt13 km
MG Road / city centre18 km
Whitefield IT hub19 km
Outer Ring Road / Manyata25 km
Kempegowda Int'l Airport42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Allam Infinite.
Allam Infinite has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Electronic City

Major developers building in Electronic City

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.