Bangalore/Project record

K-RERA · the public record

GODREJ TIARA

Bengaluru North · Godrej Properties

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15%construction reportedQ1 2026 filing
2units not bookedof 346 · Q1 2026 filing
31 May 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 May 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
260
4 BHK
86

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

4.9registered acres

70.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/110625/007817

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 May 2030
Land area19,964 sq m (4.9 acres)
Homes registered346
Tower/wing entries3
Unit mix260 × 3 BHK, 86 × 4 BHK

In context

Density70.1 homes per acre
Density in context44th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units346Total inventory registered with K-RERA.
Official carpet area46,349 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area103,758 sqmUseful scale context when comparing density and project cost.
Registered land area19,964 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.5Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)346Separate filed counts; these categories may overlap and are not added together.
Covered-parking field637Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Dir/JDSOUTH/0027/24-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date04-06-2025
Project start date04-06-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK26075%32,213 sqm
4 BHK8625%14,145 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A30114114102.85 m
Tower B30116116102.85 m
Tower C30116116102.85 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 346 official flat/unit rows, matching the 346 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK260116.2-139.2 sqm43.2-51.7 sqm260
4 BHK86164.5 sqm61.1 sqm86

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower B116116.2-164.5 sqm43.2-61.1 sqm116
Tower C116116.2-164.5 sqm43.2-61.1 sqm116
Tower A114116.2-164.5 sqm43.2-61.1 sqm114
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A0101Tower A14 BHK164.5 sqm61.1 sqm1
A0102Tower A13 BHK139.2 sqm51.7 sqm1
A0103Tower A13 BHK116.2 sqm43.2 sqm1
A0104Tower A13 BHK116.2 sqm43.2 sqm1
A0201Tower A24 BHK164.5 sqm61.1 sqm1
A0202Tower A23 BHK139.2 sqm51.7 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 1 of 30 compliance document slots are filed as under process / not yet usable: Organization Structure.

1 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (10 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200108/0005167
08-01-2020
Refund of Booking AmountGodrej Aqua (another project by this promoter)DISPOSED AO
CMP/210207/0007592
07-02-2021
Request for complete refund on cancellation of Sale Process with M/s. Godrej Properties Limited in respect of Apartment bearing Flat No: GDAQC104 at Godrej Aqua Project, BengaluruGodrej Aqua (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/211112/0008548
12-11-2021
AS NO BANK IS APPROVING THE PROJECT I HAVE NO CONFIDENCE TO FOR LOAN WITH LANDERS LIKE GODREJ HOUSING FINANCE / I WISH TO PROCEED WITH BANK ONLY FOR PLOT LOANGodrej Woodland (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220112/0008784
12-01-2022
COMPLAINT UNDER SECION 31 AND 14(2) IN FRONT OF THE ADJUDICATION AUTHORITYGodrej Aqua (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/220117/0008812
17-01-2022
To refund the Booking amount of Rs. 7,60,142.14Godrej Aqua (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/220222/0009039
22-02-2022
REFUND OF DEPOSIT AMOUNT AND COMPENSATIONGodrej Aqua (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/220510/0009445
10-05-2022
refund of the amount paidGODREJ PARK RETREAT (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/220510/0009449
10-05-2022
Refund of booking amount paid in march 2022, with interestGODREJ PARK RETREAT (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantBHAVESH D SHAH1216032009Mumbai City, Maharashtra - 400602
EngineerAkash Shahaji DalviPCMC/LE/0652/20172017Pune, Maharashtra - 411020
ArchitectShreyas MCA/2012/569572012Bengaluru Urban, Karnataka - 560076
ContractorGodrej Properties Limited-1985Bengaluru Urban, Karnataka - 560001

Builder track record

RERA filing

Godrej Properties has 29 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Godrej Properties”) (average reported construction progress 46%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹29.33 Cr collected from buyers, ₹40.96 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹40.96 Cr) exceeded buyer collections (₹29.33 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress4% → 15% (+11 pts)
Units sold/booked as registered344/346 (99%)
Buyer collections in available QPRs₹360.81 Cr
Escrow withdrawals in available QPRs₹134.40 Cr (0.37x collections)
  • 99% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • Construction progress moved from 4% to 15% across the filed QPR window.
  • The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.
  • The builder has drawn 0.37x of buyer collections from escrow (about 37% of the ₹361 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹139.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank M G Road IFSC Code : UTIB0000009 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata9 km
MG Road / city centre10 km
Bellandur–Marathahalli belt19 km
Whitefield IT hub24 km
Electronic City24 km
Kempegowda Int'l Airport26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Godrej Properties. View Godrej Properties's full track record →
Godrej Properties has 18 projects registered in Bangalore, 3 completed, 2 past RERA deadline.
33 complaints on the K-RERA register against Godrej Properties in Bangalore.

Other projects by this builder in Bangalore

Godrej Woodland
Past deadline · 88% built
Godrej Woodland Phase 2
Past deadline · 88% built
Boulevard At Godrej Woodscapes
No filings
Godrej Florenne Phase II
No filings
Godrej Lakeside Orchard
On track · 27% built · 86% sold

Other RERA-registered projects in Yeswanthpur

Major developers building in Yeswanthpur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Godrej Tiara?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026