RERA Property Intelligence Report · Preview
Bhagyalakshmi Homes · · K-RERA PRM/KA/RERA/1250/301/PR/180627/001916
Report coverage
K-RERA registry & builder-record report
What this report covers
To confirm directly with the builder
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.
Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Official carpet area | 103,523 sqm | Regulator-disclosed project-level carpet area, not vision-derived room sums. |
| Registered land area | 196,472 sqm | The land area attached to this K-RERA registration. |
| Project start date | 01-01-2016 |
K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| Plots | 513 | 100% | 103,523 sqm |
🔒 Unit-by-unit guidance · Unit Guidance report
Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.
🔒 Full records — land title, amenities paperwork & document catalog · Compliance report
The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.
No litigation declared on this project's K-RERA filing.
1 of 15 compliance document slots are filed as Not Applicable; the remaining 14 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 30 Jun 2020, extended (Covid Extension) to 30 Mar 2021 — both dates have passed with no OC on file. An extension application filed on 20 Oct 2022 is pending with K-RERA — until it is approved, the registration stands lapsed.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA enforcement record (the regulator's own defaulter list & penalty orders)
1 K-RERA order on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.
K-RERA complaint orders (4 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| Deepak jagarlamudi vs Golden I R A | site handover with promised developments and compensation for delay | AUTHORITY | 21/06/2022 |
| Ranveer Kumar Singh vs BHAGYALAKSHMI HOMES LLP | Direction to the Developer to Restrain from seeking further payments. | AUTHORITY | 10/02/2026 |
| Swapnasarit Rout vs BHAGYALAKSHMI HOMES LLP | Directions as per order dated 05.11.2022 against Respondent No.1 to restrain themselves from seeking further payments. Second as against the Respondent No.2 to complete the project as ordered. | AUTHORITY | 10/02/2026 |
| Debashis Patnaik vs BHAGYALAKSHMI HOMES LLP | Direction as per order dated 05.11.2022 to restrain Respondent No.1 from collecting future payments and to Respondent No.2 to complete the project as per order dated 05.11.2022. | AUTHORITY | 10/02/2026 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (2 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/200107/0004991 07-01-2020 | Return of amount paid to promoter along with interest paid on the loan taken and compensation as the delivery date for completion of infrastructure and amenities has expired by more than 42 months | GOLDEN IRA | DISPOSED AO |
| CMP/200812/0006349 12-08-2020 | site handover due and compensation for delay with promised developments | GOLDEN IRA | DISPOSED AUTHORITY FULLBENCH |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.
RERA 70% project account is on file: HDFC Koramangala (IFSC HDFC0000053, a/c …0147). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
The nearest major job hub is ~29 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Kempegowda Int'l Airport | 20 km |
| Outer Ring Road / Manyata | 29 km |
| MG Road / city centre | 36 km |
| Whitefield IT hub | 42 km |
| Bellandur–Marathahalli belt | 42 km |
| Electronic City | 51 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
Should you buy in GOLDEN IRA?
This page is the free K-RERA filing summary. The full RERA Property Intelligence Report gives you buyer-complaint history, regulatory flags, builder track record, the official unit register, land title, NOCs, and (where the sanctioned plans support it) room-by-room unit data and an annotated site plan. See a real one first:
Sample: Sobha Silicon Oasis → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Built by Bhagyalakshmi Homes.
Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.
Own a unit in Golden IRA?
Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.
Last checked against the RERA register: 4 Jul 2026