Bangalore/Project record

K-RERA · the public record

Golden Panorama

Bengaluru South · GOLDEN GATE PROPERTIES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionK-RERA registration · read 20 Sep 2026
363registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 to 4 BHK
335

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

4.9registered acres

73.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/171014/000186

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2019
Land area19,990 sq m (4.9 acres)
Homes registered363
Tower/wing entries5
Unit mix335 × 2 to 4 BHK

In context

Density73.5 homes per acre
Density in context44th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units363Total inventory registered with K-RERA.
Official carpet area30,344 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area19,990 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.22Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries5Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)363Separate filed counts; these categories may overlap and are not added together.
Open-parking field65Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date02-06-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 to 4 BHK335100%30,344 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
5137878-
4137878-
3137878-
2137878-
1135151-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 363 official flat/unit rows, matching the 363 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK23371.0-83.0 sqm44.0-51.0 sqm233
3 BHK13081.0-110.0 sqm48.0-70.0 sqm130

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
27871.0-110.0 sqm44.0-70.0 sqm78
37871.0-110.0 sqm44.0-70.0 sqm78
47871.0-110.0 sqm44.0-70.0 sqm78
57871.0-110.0 sqm44.0-70.0 sqm78
15171.0-83.0 sqm44.0-51.0 sqm51
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
5011512 BHK75.0 sqm47.0 sqm1
5012512 BHK76.0 sqm47.0 sqm1
5013512 BHK74.0 sqm47.0 sqm1
5014513 BHK106.0 sqm68.0 sqm1
5015513 BHK110.0 sqm70.0 sqm1
5016513 BHK84.0 sqm52.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 22 compliance document slots are filed as Not Applicable; the remaining 21 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2019 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (11 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Srikanth Upadya vs golden gate properties ltda. Direct the Respondent to execute cancellation of sale deed with respect to schedule property ,refund 60,00,000/- paid under the sale deed dated 29.12.2021,Award Compensation to the Complainants.AUTHORITY29/05/2025
RAMARAO G vs GOLDEN GATE PROPERTIES LTDfinancial audit on project money flow and destination of money flow, Completion of the project and compensation for the delayAUTHORITY29/04/2026
Prarthana Kumari U vs GOLDEN GATE PROPERTIES LIMITEDCompensation for Delay and mental agony as prescribedAUTHORITY23/02/2023
Prajwal Kumar U vs M/S GOLDEN GATE PROPERTIES LTDCompensation for delay and mental agony as prescribedAUTHORITY23/02/2023
Uma Srinivas vs GOLDEN GATE PROPERTIES LIMITEDCompensation for delay and mental agony as prescribedAUTHORITY23/02/2023
MR SAUMITRA R BHVE AND ANOTHER vs M/S.GOLDEN GATE PROPERTIES LIMITEDInterest on Delay PeriodAUTHORITY21/10/2024
Nagendra Padiyara vs Golden Gate Properties LimitedDelay Compensation as per RERA, Project Completion must be before 31 March, 2022AUTHORITY21/03/2023
Rajashree Kamath vs Golden Gate Properties LimitedDelay compensation in order to cover our losses, and early completion of project.AUTHORITY21/03/2023
RUCHI MANAS BHAT vs GOLDEN PANORAMAComplainant prays for the refund of an amount of REFUND AN AMOUNT OF RS. 6,90,978/- ALONG WITH A COMPENSATION OF RS. 2,00,000/- AT THE RATE OF 9% P.A AND THE PENALTY OF RS. 1,35,000 (AT THE RATE OF RSAUTHORITY18/07/2024
Mahesh B S & MRS. ANUSHA K VENKATESH vs GOLDEN GATE PROPERTIES LIMITEDInterest for delay as prescribed under Section 18 + compensation for mental agony + compensation for loss caused due to default of Promoter to give NOC for availing bank loanAUTHORITY15/02/2023
Errol Vas Prabhu vs GOLDEN GATE PROPERTIES LTDDelay Compensation on the Delay of Amenities and other aspects of the Project completionAUTHORITY13/01/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (35 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190310/0002407
10-03-2019
Inordinate delay in handing over possession and completion of project - refund requestGolden Serenity (another project by this promoter)DISPOSED AO
CMP/190310/0002411
10-03-2019
Inordinate Delay in handing over possession and completion of project - Refund RequestGolden Serenity (another project by this promoter)DISPOSED AO
CMP/190310/0002412
10-03-2019
Inordinate delay in completion and handover of project-Refund requestedGolden Serenity (another project by this promoter)DISPOSED AO
CMP/190311/0002427
11-03-2019
Inordinate delays in completion and handover of project- Requesting refundGolden Serenity (another project by this promoter)DISPOSED AO
CMP/190317/0002448
17-03-2019
Inordinate Delay - Seeking RefundGolden Serenity (another project by this promoter)DISPOSED AO
CMP/190319/0002466
19-03-2019
Refund of booking amount for plot 193 at Golden Serenity LayoutGolden Serenity (another project by this promoter)DISPOSED AO
CMP/190320/0002469
20-03-2019
Delay in project delivery and no comitment of PlotGolden Serenity (another project by this promoter)DISPOSED AO
CMP/190321/0002485
21-03-2019
Refund of booking amount for plot 163 at Golden Serenity LayoutGolden Serenity (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 1 project professional/vendor row across Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ContractorBhuvana Infra Projects Pvt Ltd-2011No 218 Main 19th, Koramangala 6th Block

Builder track record

RERA filing

Golden Gate has 2 other K-RERA-registered projects in our records. 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹33.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Koramangala (IFSC HDFC0000053, a/c …0113). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre13 km
Electronic City14 km
Bellandur–Marathahalli belt17 km
Outer Ring Road / Manyata20 km
Whitefield IT hub25 km
Kempegowda Int'l Airport39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Golden Gate.
Golden Gate has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Golden Homes – Phase 3
No filings

Other RERA-registered projects in Subramanyapura

Major developers building in Subramanyapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Golden Panorama?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026