Bangalore/Project record

K-RERA · the public record

Greenfinch Habitat

Anekal · GREENFINCH PROJECTS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

99%construction reportedQ1 2026 filing
31units not bookedof 298 · Q1 2026 filing
31 Mar 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Mar 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 BHK apartments
298

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.6registered acres

116.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/140322/004752

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2026
Land area10,340 sq m (2.6 acres)
Homes registered298
Tower/wing entries3
Unit mix298 × 2 BHK apartments

In context

Density116.6 homes per acre
Density in context89th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units298Total inventory registered with K-RERA.
Official carpet area15,881 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area30,003 sqmUseful scale context when comparing density and project cost.
Registered land area10,340 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~2.14Sanctioned floor-area ratio (≈22,080 sqm sanctioned FAR area ÷ 10,340 sqm land) — higher means a denser vertical build.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)328Separate filed counts; these categories may overlap and are not added together.
Covered-parking field281Separate filed counts; these categories may overlap and are not added together.
Open-parking field47Separate filed counts; these categories may overlap and are not added together.
Garage field328Separate filed counts; these categories may overlap and are not added together.
Approved plan numberSTRRPA/TP/CC/243/2020-21Use this to match the sanctioned drawing set shown by the builder.
Plan approval date20-03-2021
Project start date15-01-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK apartments298100%15,881 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Wing-A1212013240 m
Wing-B12485340 m
Wing-C1313014343 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 298 official flat/unit rows, matching the 298 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK29853.0-55.0 sqm31.0-32.0 sqm298

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Wing-C13053.0-55.0 sqm31.0-32.0 sqm130
Wing-A12053.0-55.0 sqm31.0-32.0 sqm120
Wing-B4853.0 sqm31.0 sqm48
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-001Wing-A12 BHK53.0 sqm31.0 sqm1
A-002Wing-A12 BHK55.0 sqm32.0 sqm1
A-003Wing-A12 BHK53.0 sqm31.0 sqm1
A-004Wing-A12 BHK53.0 sqm31.0 sqm1
A-005Wing-A12 BHK53.0 sqm31.0 sqm1
A-006Wing-A12 BHK55.0 sqm31.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

23 of 47 compliance document slots are filed as Not Applicable; the remaining 24 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved21-01-2021Panchayat NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved04-11-2021Kspcb NOC.pdf
KSPCB- MOEF (Above 50 Acres)Approved20-07-2020Seiaa NOC_compressed.pdf
KPTCL- BESCOMApproved08-02-2021Bescom NOC.pdf
Fire and SafetyApproved10-03-2021Fire Force Department NOC.pdf
Airport Authority of IndiaApproved22-02-2021Airport Authority of India NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantManoj Kumar Dungarwal5492602018Bengaluru Urban, Karnataka - 560095
EngineerManohar ConsultantsBCC/BL-3.6/E-4030/2014-151986Bengaluru Urban, Karnataka - 560030
ArchitectShilpa N GuggariCA/2005/362472009Bengaluru Urban, Karnataka - 560070
ContractorSelf- Greenfinch Projects Pvt Ltd-2012Bengaluru Urban, Karnataka - 560093

Builder track record

RERA filing

Greenfinch Projects has 2 other K-RERA-registered projects in our records (average reported construction progress 99%). 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹4.35 Cr collected from buyers, ₹4.35 Cr withdrawn from the project's escrow account.

Construction progress95% → 99% (+4 pts)
Units sold/booked as registered267/298 (90%)
Buyer collections in available QPRs₹25.06 Cr
Escrow withdrawals in available QPRs₹25.06 Cr (1.00x collections)
  • Construction progress moved from 95% to 99% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹17.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC 100 FEET ROAD INDIRANAGAR IFSC Code : HDFC0001755 Pin Code : 560038. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City15 km
Bellandur–Marathahalli belt20 km
Whitefield IT hub22 km
MG Road / city centre29 km
Outer Ring Road / Manyata34 km
Kempegowda Int'l Airport47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Greenfinch Projects.
Greenfinch Projects has 3 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

Greenfinch Meadows
On track · 99% built · 54% sold

Other RERA-registered projects in BEML Cooperative Society Layout

Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5

Major developers building in BEML Cooperative Society Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.