Bangalore/Project record

K-RERA · the public record

HIGHCLIFF

Bengaluru East · HIREN WAHEN BUILDTECH

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

82%construction reportedQ1 2026 filing
79units not bookedof 196 · Q1 2026 filing
22 Apr 2019declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

22 Apr 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

1 Bed + 1T
77

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.2registered acres

169.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/171031/001436

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion22 April 2019
Land area4,694 sq m (1.2 acres)
Homes registered196
Tower/wing entries3
Unit mix77 × 1 Bed + 1T

In context

Density169 homes per acre
Density in context98th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units196Total inventory registered with K-RERA.
Official carpet area3,060 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area4,694 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)249Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field229Separate filed counts; these categories may overlap and are not added together.
Project start date21-07-2017

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
1 Bed + 1T77100%3,060 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A137983-
B136583-
C135283-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 196 official flat/unit rows, matching the 196 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
1BHK7732.6-46.2 sqm158.2-204.5 sqm77
2 BHK3965.9-74.6 sqm278.3-340.8 sqm39
2.5 BHK3985.1-98.2 sqm365.4-429.4 sqm39
3 BHK39105.5-111.4 sqm463.7-487.5 sqm39
3BHK1131.2 sqm551.0 sqm1
4BHK1174.9 sqm749.8 sqm1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A7932.6-174.9 sqm158.2-749.8 sqm79
B6565.9-90.2 sqm278.3-374.5 sqm65
C5298.2-111.4 sqm429.4-487.5 sqm52
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A1-201A24BHK174.9 sqm749.8 sqm1
A2-202A23BHK131.2 sqm551.0 sqm1
A1-301A31BHK41.3 sqm184.2 sqm1
A2-302A31BHK32.6 sqm163.8 sqm1
A3-303A31BHK39.5 sqm167.0 sqm1
A4-304A31BHK39.3 sqm177.8 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 28 compliance document slots are filed as Not Applicable; the remaining 27 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

2 K-RERA orders on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (9 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
ANKUR S/O AJAY KUMAR CHOUDHARY vs M/S HIREN WAHEN BUILDTECH PRIVATE LIMITEDI want to refund the entire amount of RS.804413 with interest as per RERA provisionAUTHORITY30/09/2023
Akshat Daharwal vs HIREN WAHEN BUILDTECHInvestigate the builder's actions along with the project's progress. Enforce builder to pay compensation for the delay in possession which was supposed to be in Dec'2020.AUTHORITY28/04/2026
Abha Daharwal vs HIREN WAHEN BUILDTECHStop harassment and threats from builder. Force builder to re-initiate construction and complete as per RERA agreed schedule. Pay interest for the delay.AUTHORITY28/04/2026
SAURAV BHAUMICK vs HIREN WAHEN BUILDTECHRefund with compensationAUTHORITY27/04/2026
Vinay vs HIREN WAHEN BUILDTECH1.Direct the Developer to delivered & register flat within 2 months . 2.Direct the developer to pay the interest on delay period of 18% per annum from 6/4/2019 till the execution of the sale deed.AUTHORITY27/04/2026
Vinay vs HIREN WAHEN BUILDTECH1. Direct the Developer to delivered & register flat within 2 months. 2. Direct the developer to pay the interest on delay period of 18% per annum from 6/4/2019 till the execution of the sale deed.AUTHORITY27/04/2026
Vinay vs HIREN WAHEN BUILDTECH1. Direct the Developer to delivered & register flat within 2 months. 2. Direct the developer to pay the interest on delay period of 18% per annum from 6/4/2019 till the execution of the sale deed.AUTHORITY27/04/2026
VIKAS VITTHAL MASTUD vs NAREN BABU LALIT SINGH WAHEN (HIGHCLIFF)Full Refund + 18% Interest for Entire periodAUTHORITY13/10/2022
ANAND SIDDHARTH K & AKSHAYA H vs HIREN WAHEN BUILDTECH (2) WAHENGBAM LALIT SINGHCancellation of allotment, subject to the condition that the promoter refunds the entire amount of INR 25,00,000 with applicable interestAUTHORITY09/03/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (4 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190730/0003217
30-07-2019
Not refunding the amountHIGHCLIFFDISPOSED AO
CMP/190730/0003564
30-07-2019
Full Refund not InitiatedHIGHCLIFFDISPOSED AO
CMP/200820/0002147
20-08-2020
REFUND PENDING - Cancellation with No refund of Booking AmountHIGHCLIFFDISPOSED AUTHORITY BENCH4
CMP/211227/0008752
27-12-2021
Suppression of facts about the pending legal formalities ( RERA Approval and TDR ) and harassment by the promotorHIGHCLIFFDISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved22-10-20241 BWSSB NOC 22-10-2024.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved04-10-20242 PCB NOC-CFE Exp 04-10-2024.pdf
KSPCB- MOEF (Above 50 Acres)Approved08-03-20233 MOEF NOC 08-03-2023.pdf
KPTCL- BESCOMApproved17-04-20235 BESCOM NOC - 17- 04-2023.pdf
Fire and SafetyApproved28-05-20247 FIRE NOC-28-05-2024.pdf
Airport Authority of IndiaApproved31-05-20238 AIR PORT NOC 31-05-2023_compressed.pdf
BSNL/Telecommunication DepartmentApproved15-03-2024BSNL NOC Received as on 15-03-2024.pdf

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectVBT CONSORTIUM-2004SADASHIVANAGAR, BANGALORE
ContractorKNK GROUP-19704TH T BLOCK, ASHOKA PILLAR
Structural engineerPRASAD CONSULTANTS---

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹6.33 Cr collected from buyers, ₹4.43 Cr withdrawn from the project's escrow account.

Construction progress76% → 82% (+6 pts)
Units sold/booked as registered117/196 (60%)
Buyer collections in available QPRs₹27.03 Cr
Escrow withdrawals in available QPRs₹20.61 Cr (0.76x collections)
  • Construction progress moved from 76% to 82% across the filed QPR window.
  • The builder has drawn 0.76x of buyer collections from escrow (about 76% of the ₹27 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹30.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Kadubesanahalli, Marathahalli Junction (IFSC HDFC0003636, a/c …1780). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
MG Road / city centre3 km
Outer Ring Road / Manyata5 km
Bellandur–Marathahalli belt10 km
Whitefield IT hub15 km
Electronic City18 km
Kempegowda Int'l Airport24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Hiren Wahen.

Other RERA-registered projects in Fraser Town

Sobha Sentosa Phase 2 Wing 5 And 6
Sobha Sentosa Phase 3 Wing 3 And 4
Sobha Windsor Phase 3 Wing 6, 7 And 8

Major developers building in Fraser Town

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.