RERA Property Intelligence Report · Preview

KRRISH VIHAR

GOPALRAO TUKARAM KUKDOLKAR · · K-RERA PRM/KA/RERA/1249/447/PR/170915/000189

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
2
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

40
Registered units
₹4.7 Cr
Est. construction cost
Units profiled
47
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units40Total inventory registered with K-RERA.
Official carpet area3,403 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area1,306 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.73Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings1Official tower/wing count in the K-RERA detail page.
Parking disclosed38 total (0 open) — 0.95 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date30-10-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
FLATS/COMMERCIAL39100%3,403 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
KRRISH VIHAR54038-

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

ParkingThe project declares 38 parking spaces for 40 homes (~0.9 per home) — about one space per home — adequate but tight if you have two cars.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 42 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 29 Oct 2018 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
MR CHETAN DESAI vs MR GOPIRAO TUKARAM KUKDOLKARInstruct builder to hand over all property documents as per sale deed executed like Khata, Property Tax, OC, Building Completion Certificate, Elec Meter Transfer, GST Paid Statement, etcAUTHORITY05/03/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectGOPALRAO TUKARAM KUKDOLKAR-1990CLUB ROAD, BELGAUM
Structural engineerVINAY BEHERE---

Builder track record

RERA filing

Gopalrao Tukaram has 2 other K-RERA-registered projects in our records. 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹11.8 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA PBB BRANCH TILAKWADI, BELGAUM. (IFSC SBIN0004165, a/c …8369). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 8 project-photo uploads.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata10 km
MG Road / city centre10 km
Bellandur–Marathahalli belt20 km
Whitefield IT hub25 km
Electronic City25 km
Kempegowda Int'l Airport26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Gopalrao Tukaram.
Gopalrao Tukaram has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Peenya

Classic Merusri Canaan Phase - II

Major developers building in Peenya

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Krrish Vihar?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 16 Jul 2026