Sobha Neopolis Phase 4 - 3, 4, 8 & 9

SOBHA · Bengaluru East · K-RERA PRM/KA/RERA/1251/446/PR/220923/006283

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
130
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

374
Registered units
₹346.6 Cr
Est. construction cost
Units profiled
91
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units374Total inventory registered with K-RERA.
Official carpet area47,824 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area95,397 sqmUseful scale context when comparing density and project cost.
Registered land area20,288 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.99Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings4Official tower/wing count in the K-RERA detail page.
Parking disclosed374 total (600 covered, 38 open) — 1.00 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Approved plan numberBBMP/Addl.Dir/JDNORTH/0003/23-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date05-09-2023
Project start date01-04-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
ELECTRICAL ROOM21%0 sqm
4 BHK15240%22,805 sqm
3 BHK22259%25,018 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Wing 31811111157.6 m
Wing 418767657.6 m
Wing 81811111157.6 m
Wing 918767657.6 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 374 official flat/unit rows, matching the 374 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK222105.1-135.0 sqm39.1-52.9 sqm222
4 BHK152145.3-150.3 sqm56.7-60.3 sqm152

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Wing 3111105.1-135.0 sqm39.1-52.9 sqm111
Wing 8111105.1-135.0 sqm39.1-52.9 sqm111
Wing 476145.3-150.3 sqm56.7-60.3 sqm76
Wing 976145.3-150.3 sqm56.7-60.3 sqm76
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
3001Wing 303 BHK110.6 sqm41.4 sqm1
3002Wing 303 BHK135.0 sqm52.9 sqm1
3004Wing 303 BHK115.2 sqm45.8 sqm1
3005Wing 303 BHK115.2 sqm45.8 sqm1
3011Wing 313 BHK110.6 sqm41.4 sqm1
3012Wing 313 BHK135.0 sqm52.2 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~1,376 sqft — large-format homes (3BHK-and-up territory), not compact stock. This is a large, multi-tower township — 374 homes across 4 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 374 parking spaces for 374 homes (~1.0 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~51 sqm per home; across all 374 homes that is ~93% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

9 of 84 compliance document slots are filed as Not Applicable; the remaining 75 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (4 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
N Jayasankaran vs SOBHA LIMITEDwith regard to the complaint noted in facts section above, this is a sincere request to RERA to intervene in this matter and pass orders to Sobha record the cancellation and issue the refundAUTHORITY26/03/2025
Deepak Tiwari vs Sobha Neopolis Phase-4Direct the Sobha limited to refund complete booking amount (17,00,000/-) with interestAUTHORITY23/12/2025
Veeresh Patil vs Sobha NeopolisI request RERA authorities to direct Sobha Limited to issue a full refund of Rs. 15,00,000 (Fifteen Lakhs rupees only) + Interest (SBI MCLR + 2%) for the delay of over 3 months at the earlist.AUTHORITY23/07/2025
POLAMARASETTI VIKAS vs Sobha Neopalis Phase -4Cancellation of flat booking and recovery of booking amountAUTHORITY03/06/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (127 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190218/0002166
18-02-2019
Refund of booking amountSobha Dream Acres - Palm Springs Phase 17 Wing 54 (another project by this promoter)DISPOSED AO
CMP/190217/0002175
17-02-2019
Compensation for Delay of projectsSobha City - Casa Paradiso Block 4 (another project by this promoter)DISPOSED AO
CMP/190315/0002219
15-03-2019
About refund of booking amountSobha Dream Acres - Tropical Greens Phase 8 Wing 43 and 44 (another project by this promoter)DISPOSED AO
CMP/190225/0002263
25-02-2019
Refund of Advance amount-Sobha Arena - The Park ( Block 2 ) (another project by this promoter)DISPOSED AO
CMP/190308/0002322
08-03-2019
Promoter SL Demanding 38% payment of unit cost before entering the ATSSobha Arena - Pebble Court (Block 1) (another project by this promoter)DISPOSED AO
CMP/190610/0002334
10-06-2019
Cancellation of Sobha Silicon Oasis Unit - 10191Sobha Silicon Oasis Phase 5 Wing 10 & 11 (another project by this promoter)DISPOSED AO
CMP/190308/0002388
08-03-2019
Non-allotment of agreed units & RefundSobha Indraprastha (another project by this promoter)DISPOSED AO
CMP/190324/0002505
24-03-2019
Compensation against late deliverySobha City - Casa Paradiso Block 4 (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

3 of 4 applicable approvals are on file; still outstanding: KPTCL- BESCOM. Confirm each has been granted, not merely applied for, before booking.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved05-05-2023BWSSB NOC SNP 05052023.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved23-11-2022KSPCB CFE SNP 23112022.pdf
KPTCL- BESCOMApplied11-08-2025View NOC
Fire and SafetyApproved06-10-2022Fire NOC SNP 06102022.pdf

Project team & certifications

RERA filing

K-RERA names 5 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantBalaji D2173902016Bengaluru Urban, Karnataka - 560084
EngineerMr.HAREESH GOWDABCC/BL-3.6 SE-153/2013-141995Bengaluru Urban, Karnataka - 560095
EngineerBalakrishnan GF-124976-92019Bengaluru Urban, Karnataka - 560103
ArchitectGeetha K NairCA/93/156411993Bengaluru Urban, Karnataka - 560103
ContractorSobha Limited-1995Bengaluru Urban, Karnataka - 560103

Builder track record

RERA filing

Sobha has 130 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Sobha”) (average reported construction progress 64%). 60 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹65.01 Cr collected from buyers, ₹11.82 Cr withdrawn from the project's escrow account.

Construction progress15% → 33% (+18 pts)
Units sold/booked as registered297/374 (79%)
Buyer collections in available QPRs₹112.06 Cr
Escrow withdrawals in available QPRs₹41.60 Cr (0.37x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹92.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: KOTAK MAHINDRA BANK MG road IFSC Code : KKBK0008066 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bellandur–Marathahalli belt3 km
Whitefield IT hub6 km
Electronic City11 km
MG Road / city centre13 km
Outer Ring Road / Manyata16 km
Kempegowda Int'l Airport30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sobha. View Sobha's full track record →
Sobha has 124 projects registered in Bangalore, 23 completed.
272 complaints on the K-RERA register against Sobha in Bangalore.

Buyer reviews · MouthShut

★★☆☆☆ 1.6/5

337 reviews for Sobha in Bangalore
Read 337 reviews on MouthShut →

Other projects by this builder in Bangalore

Sobha Ayana At Dream Acres Wing 60 To 71
Filing overdue · 20% built · 58% sold
Sobha Crystal Meadows Phase 1 Wing 1 To 6
Filing overdue · 5% built · 0% sold
Sobha Crystal Meadows Phase 2 Wing 7 And 8
Filing overdue · 2% built · 0% sold
Sobha Crystal Meadows Phase 3 Wing 9 To 15
Filing overdue · 2% built · 0% sold
Sobha Crystal Meadows Phase 4 Wing 23 To 28
Filing overdue · 2% built · 0% sold
Sobha Crystal Meadows Phase 5 Wing 16 To 22
Filing overdue · 2% built · 0% sold

Other RERA-registered projects in Peenya

Classic Merusri Canaan Phase - II

Major developers building in Peenya

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Sobha Neopolis Phase 4 - 3, 4, 8 & 9?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026