Bangalore/Project record

K-RERA · the public record

Legacy Saviero

Bengaluru East · Chitrakut Estates

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

88%construction reportedQ1 2026 filing
54units not bookedof 96 · Q1 2026 filing
31 Mar 2020declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Mar 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK
51

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.7registered acres

57.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/171201/000906

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2020
Land area6,804 sq m (1.7 acres)
Homes registered96
Tower/wing entries1
Unit mix51 × 3 BHK

In context

Density57.1 homes per acre
Density in context25th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units96Total inventory registered with K-RERA.
Official carpet area5,952 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area6,804 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.13Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)106Separate filed counts; these categories may overlap and are not added together.
Open-parking field19Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date03-08-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK51100%5,952 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
LEGACY SAVIERO1196106-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 96 official flat/unit rows, matching the 96 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK701,260.0-1,271.0 sqft800.0-817.0 sqft80
2BHK26986.0-1,025.0 sqft627.0-671.0 sqft26

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
LEGACY SAVIERO96986.0-1,271.0 sqft627.0-817.0 sqft106
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A01LEGACY SAVIERO03BHK1,270.0 sqft813.0 sqft1
A02LEGACY SAVIERO03BHK1,263.0 sqft809.0 sqft1
A03LEGACY SAVIERO02BHK1,013.0 sqft662.0 sqft1
A04LEGACY SAVIERO03BHK1,260.0 sqft800.0 sqft1
B01LEGACY SAVIERO03BHK1,271.0 sqft813.0 sqft1
B02LEGACY SAVIERO02BHK1,025.0 sqft671.0 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 25 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

1 K-RERA order on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved24-02-2013Saveiro BWSSBNOC 1.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved08-01-2016Saveiro KSPCB 1.pdf
KPTCL- BESCOMApproved18-02-2013Saveiro Bescom NOC 1.pdf
Fire and SafetyApproved23-01-2013Saveiro FireNOC 1.pdf
Airport Authority of IndiaApproved07-01-2013Saveiro AAINOC 1.pdf
BSNL/Telecommunication DepartmentApproved07-01-2013Svaerio BSNLNOC 1.pdf

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.28 Cr collected from buyers, ₹0.28 Cr withdrawn from the project's escrow account.

Construction progress82% → 88% (+6 pts)
Units sold/booked as registered42/96 (44%)
Buyer collections in available QPRs₹8.91 Cr
Escrow withdrawals in available QPRs₹7.01 Cr (0.79x collections)
  • Construction progress moved from 82% to 88% across the filed QPR window.
  • The builder has drawn 0.79x of buyer collections from escrow (about 79% of the ₹9 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹46.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank M G Road (IFSC UTIB0000009, a/c …4665). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata5 km
MG Road / city centre8 km
Bellandur–Marathahalli belt10 km
Whitefield IT hub11 km
Electronic City20 km
Kempegowda Int'l Airport20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Chitrakut Estates.

Other RERA-registered projects in Horamavu

Major developers building in Horamavu

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Legacy Saviero?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026