Bangalore/Project record

K-RERA · the public record

NAVA VAJRA

Bengaluru East · NAVA JYOTHI SHELTERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

83%construction reportedQ1 2026 filing
112units not bookedof 388 · Q1 2026 filing
31 Mar 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Mar 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3 BHK Flats
200
2 BHK Flats
188

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

4.6registered acres

85.2registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/040524/006860

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2028
Land area18,437 sq m (4.6 acres)
Homes registered388
Tower/wing entries6
Unit mix200 × 3 BHK Flats, 188 × 2 BHK Flats

In context

Density85.2 homes per acre
Density in context66th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units388Total inventory registered with K-RERA.
Official carpet area379,032 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area53,436 sqmUseful scale context when comparing density and project cost.
Registered land area18,437 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries6Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)388Separate filed counts; these categories may overlap and are not added together.
Covered-parking field439Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberMDP 1045/23-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date15-04-2024
Project start date15-04-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK Flats20052%222,636 sqm
2 BHK Flats18848%156,396 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
NAVA VAJRA A Block3848414.4 m
NAVA VAJRA B Block3686814.4 m
NAVA VAJRA C Block3808014.4 m
NAVA VAJRA D Block3686814.4 m
NAVA VAJRA E Block3444414.4 m
NAVA VAJRA F Block3444414.4 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 388 official flat/unit rows, matching the 388 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK20091.5-118.8 sqm48.5-66.6 sqm200
2 BHK18872.0-82.6 sqm42.2-47.3 sqm188

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
NAVA VAJRA A Block8477.5-118.8 sqm42.4-65.9 sqm84
NAVA VAJRA C Block8074.0-111.7 sqm44.3-62.2 sqm80
NAVA VAJRA B Block6877.6-111.5 sqm45.0-66.6 sqm68
NAVA VAJRA D Block6877.4-101.5 sqm43.6-62.2 sqm68
NAVA VAJRA E Block4473.8-105.1 sqm42.4-58.3 sqm44
NAVA VAJRA F Block4472.0-107.4 sqm42.2-59.4 sqm44
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
001NAVA VAJRA A Block03 BHK99.2 sqm57.8 sqm1
002NAVA VAJRA A Block02 BHK77.5 sqm42.4 sqm1
003NAVA VAJRA A Block02 BHK77.5 sqm42.4 sqm1
004NAVA VAJRA A Block02 BHK77.5 sqm42.4 sqm1
005NAVA VAJRA A Block02 BHK77.5 sqm42.4 sqm1
006NAVA VAJRA A Block02 BHK77.5 sqm42.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

8 of 32 compliance document slots are filed as Not Applicable; the remaining 24 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved15-02-2024BWSSB NOC Self Attested.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved29-06-2024CFE KSPCB NOC_compressed.pdf
KSPCB- MOEF (Above 50 Acres)Approved29-11-2023SEIAA NOC.pdf
KPTCL- BESCOMApproved06-12-2023BESCOM NOC Self Attested.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantNIRMALA SREENIVASULU2179072010Bengaluru Urban, Karnataka - 560037
EngineerKUMAR CGBCC/BL-3.6/SE-0349/19-202019Bengaluru Urban, Karnataka - 560090
ArchitectVINOD KUMAR KCA /2015 /679822015Bengaluru Urban, Karnataka - 560043
ContractorChinnanarasanna-2020Bengaluru Urban, Karnataka - 560016

Builder track record

RERA filing

Nava Jyothi has 4 other K-RERA-registered projects in our records (average reported construction progress 2%). 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹143.05 Cr collected from buyers, ₹20.04 Cr withdrawn from the project's escrow account.

Construction progress67% → 83% (+16 pts)
Units sold/booked as registered276/388 (71%)
Buyer collections in available QPRs₹198.16 Cr
Escrow withdrawals in available QPRs₹75.15 Cr (0.38x collections)
  • Construction progress moved from 67% to 83% across the filed QPR window.
  • The builder has drawn 0.38x of buyer collections from escrow (about 38% of the ₹198 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹34.8 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank RAMAMURTHY NAGAR IFSC Code : UTIB0003569 Pin Code : 560016. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata5 km
MG Road / city centre9 km
Bellandur–Marathahalli belt12 km
Whitefield IT hub12 km
Kempegowda Int'l Airport18 km
Electronic City22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Nava Jyothi. View Nava Jyothi's full track record →
Nava Jyothi has 5 projects registered in Bangalore.

Other projects by this builder in Bangalore

Nava Vruksha
On track · 2% built · 8% sold

Other RERA-registered projects in Horamavu

Major developers building in Horamavu

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Nava Vajra?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026