LGCL HIGH STREET

Bengaluru East · LGCL Properties

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2020declared completionK-RERA registration · read 20 Sep 2026
14registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 and 3 BHK
7

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.3registered acres

50.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/171015/000712

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2020
Land area1,112 sq m (0.3 acres)
Homes registered14
Tower/wing entries1
Unit mix7 × 2 and 3 BHK

In context

Density50.9 homes per acre
Density in context20th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units14Total inventory registered with K-RERA.
Official carpet area497 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area1,112 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~1.69Sanctioned floor-area ratio (≈1,874 sqm sanctioned FAR area ÷ 1,112 sqm land) — higher means a denser vertical build.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)17Separate filed counts; these categories may overlap and are not added together.
Open-parking field17Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date10-07-2017

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 and 3 BHK7100%497 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
LGCL HIGH STREET41417-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 14 official flat/unit rows, matching the 14 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK991.0-94.0 sqm68.7-95.2 sqm9
2BHK566.5-78.1 sqm59.8-67.6 sqm5

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
LGCL HIGH STREET1466.5-94.0 sqm59.8-95.2 sqm14
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1LGCL HIGH STREET02BHK78.1 sqm59.8 sqm1
2LGCL HIGH STREET03BHK91.0 sqm68.7 sqm1
101LGCL HIGH STREET12BHK66.5 sqm63.2 sqm1
102LGCL HIGH STREET13BHK94.0 sqm88.0 sqm1
103LGCL HIGH STREET13BHK91.0 sqm81.3 sqm1
201LGCL HIGH STREET22BHK66.5 sqm67.6 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

15 of 36 compliance document slots are filed as Not Applicable; the remaining 21 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2020, extended (Covid Extension) to 30 Sep 2021 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Complaints on this project's K-RERA page (32 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190627/0003248
27-06-2019
REFUNDLGCL Stonescape (another project by this promoter)DISPOSED AO
CMP/190807/0003824
07-08-2019
Delay and CompensationLGCL Stonescape (another project by this promoter)DISPOSED AO
CMP/191012/0004428
12-10-2019
Seeking for delay compensation as per RERA provisions and direct respondent to handover possession within 6 monthsLGCL PUEBLO (another project by this promoter)DISPOSED AO
CMP/200307/0005447
07-03-2020
delay in handoverLGCL PUEBLO (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200327/0005798
27-03-2020
The Home Buyers are awaiting for completion & Possession of the Project even after payment of 100 % of the Consideration amount towards the purchase of the house.LGCL PUEBLO (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200713/0006155
13-07-2020
Home Buyers are awaiting for completion & Possession of the Project even after payment of 100 % of the Consideration amount towards the purchase of the house.LGCL PUEBLO (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200713/0006156
13-07-2020
Home Buyers are awaiting for completion & Possession of the Project even after payment of 100 % of the Consideration amount towards the purchase of the house.LGCL PUEBLO (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200713/0006157
13-07-2020
Home Buyers are awaiting for completion & Possession of the Project even after payment of 100 % of the Consideration amount towards the purchase of the house.LGCL PUEBLO (another project by this promoter)DISPOSED AUTHORITY FULLBENCH

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectMr. Andrew Bergmans-2011No. 12/1, Rest House Road
Structural engineerMr. Arunachala---

Builder track record

RERA filing

Lgcl Properties has 3 other K-RERA-registered projects in our records. 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹46.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC RICHMOND ROAD (IFSC HDFC0000523, a/c …1301). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
MG Road / city centre4 km
Bellandur–Marathahalli belt6 km
Outer Ring Road / Manyata9 km
Whitefield IT hub12 km
Electronic City13 km
Kempegowda Int'l Airport27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Lgcl Properties.
Lgcl Properties has 4 projects registered in Bangalore.
35 complaints on the K-RERA register against Lgcl Properties in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Domlur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Lgcl High Street?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026