K-RERA · the public record
LGCL PUEBLO
Bengaluru South · LGCL Properties
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2019
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
3.5registered acres
16.9registered units per acre
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project · Prestige Park Grove
A larger advertised area. Almost the same carpet area.
In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.
This illustrates the report format. These findings concern the named sample, not this project.
Read the sample report ↗
The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/310/PR/171014/000286
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
In context
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered units | 59 | Total inventory registered with K-RERA. |
| Official carpet area | 2,858 sqm | Regulator-disclosed project-level carpet area, not vision-derived room sums. |
| Registered land area | 14,096 sqm | The land area attached to this K-RERA registration. |
| Sanctioned FAR/FSI | ~0.92 | Sanctioned floor-area ratio (≈12,975 sqm sanctioned FAR area ÷ 14,096 sqm land) — higher means a denser vertical build. |
| Registered tower/wing entries | 1 | Official tower/wing count in the K-RERA detail page. |
| Parking total (reconciled) | 87 | Separate filed counts; these categories may overlap and are not added together. |
| Open-parking field | 24 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Project start date | 02-06-2015 |
Official inventory & towers
RERA filingK-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| 4 BHK | 16 | 100% | 2,858 sqm |
Registered tower / wing summary
| Tower/wing | Floors | Units | Parking | Height |
|---|---|---|---|---|
| LGCL PUEBLO | 2 | 59 | 87 | - |
Official unit register
RERA filingK-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 59 official flat/unit rows, matching the 59 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.
By unit type
| Unit type | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| 3BHK | 59 | 151.6-210.9 sqm | 207.2-307.8 sqm | 87 |
By tower / wing
| Tower/wing | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| LGCL PUEBLO | 59 | 151.6-210.9 sqm | 207.2-307.8 sqm | 87 |
Show sample official unit rows
| Unit | Tower | Floor | Type | Carpet | UDS | Parking |
|---|---|---|---|---|---|---|
| 1 | LGCL PUEBLO | 0 | 3BHK | 175.7 sqm | 252.5 sqm | 2 |
| 2 | LGCL PUEBLO | 0 | 3BHK | 175.7 sqm | 252.5 sqm | 2 |
| 3 | LGCL PUEBLO | 0 | 3BHK | 175.7 sqm | 252.5 sqm | 2 |
| 4 | LGCL PUEBLO | 0 | 3BHK | 175.7 sqm | 252.5 sqm | 2 |
| 5 | LGCL PUEBLO | 0 | 3BHK | 175.7 sqm | 252.5 sqm | 2 |
| 6 | LGCL PUEBLO | 0 | 3BHK | 175.7 sqm | 252.5 sqm | 2 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
15 of 36 compliance document slots are filed as Not Applicable; the remaining 21 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 30 Jun 2019 — which has passed with no OC on file.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA enforcement record (the regulator's own defaulter list & penalty orders)
⚠ Listed on K-RERA's official DEFAULTER list.
K-RERA complaint orders (22 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| SANJEETH KUTTAN vs L G C L PROPERTIES | Compensation on interest from the builder | AUTHORITY | 28/09/2022 |
| DHIRAJSEN GUPTA vs LGCL Properties Pvt. Ltd. | Refund of the entire money collected by the builder from the bank and as well as this complainant along with interest and compensation for the damages incurred | AUTHORITY | 26/12/2024 |
| Ekta Eiran Vikram Agarwal and other Home Buyers vs LGCL Properties Pvt. Ltd. | completion and Handover of the house & project | AUTHORITY | 26/08/2022 |
| Rekha Chandrashekar vs LGCL Properties Pvt. Ltd. | completion and handover of the House & project | AUTHORITY | 26/08/2022 |
| Praveen Sadanadan vs LGCL Properties Pvt. Ltd. | Completion & handover of the House & project | AUTHORITY | 26/08/2022 |
| Santhosh Vaniamparambath MrsPayal agarwal vs LGCL Properties Pvt. Ltd. | completion & Handover of the house & project | AUTHORITY | 26/08/2022 |
| Soj Thomas MrsMarin grace vs LGCL Properties Pvt. Ltd. | completion and Handover of the house & project | AUTHORITY | 26/08/2022 |
| Mr Shibu KV And Mrs Suchitra Ravindran vs LGCL Properties Pvt. Ltd. | Completion and handover of the house & project | AUTHORITY | 26/08/2022 |
| Mr Haridas naidu Lovely Jacob vs LGCL Properties Pvt. Ltd. | Completion & handover of the house & project | AUTHORITY | 26/08/2022 |
| Rajashankar Sadasivam Lavanya sadasivam vs LGCL Properties Pvt. Ltd. | Completion & handover of the house & project | AUTHORITY | 26/08/2022 |
| Mr Ananthula Vidya Sagar Ananthulla krishnaveni vs LGCL Properties Pvt. Ltd. | completion and Handover of the house & project | AUTHORITY | 26/08/2022 |
| Arun Shankar Iyer Bhagyalaxmi iyer vs LGCL Properties Pvt. Ltd. | Completion & handover of the house & project | AUTHORITY | 26/08/2022 |
| Ramkumar dhamodharan Ujwala dhamodaran vs LGCL Properties Pvt. Ltd. | Completion & handover of the house & project | AUTHORITY | 26/08/2022 |
| Rateesh Kumar K S Neeta Nair vs LGCL Properties Pvt. Ltd. | completion & handover of the House & project | AUTHORITY | 26/08/2022 |
| Mr Manmath Manjunath vs LGCL Properties Pvt. Ltd. | completion and Handover of the house & project | AUTHORITY | 26/08/2022 |
| Jayaramu vs LGCL Properties Pvt. Ltd. | Compensation for breach and completion of Project. | AUTHORITY | 07/11/2025 |
| Rajesh Narayanan vs LGCL Properties Pvt. Ltd. | Appropriate Compensation with interest for the delay caused in handing over possession and directing the developer to complete the project as per construction agreement. | AUTHORITY | 07/11/2025 |
| Rateesh kumar K S vs LGCL Properties Pvt. Ltd. | Delay compensation as per RERA | AUTHORITY | 07/11/2025 |
| Rajsadashivam vs LGCL Properties Pvt. Ltd. | Seeking for Delay compensation as per RERA for breach of agreement and default in not handing over the possession of the row house as per the agreed terms. | AUTHORITY | 07/11/2025 |
| Mr Chaitanya Rami Reddy Sidda vs LGCL Properties Pvt. Ltd. | Refund and Compensation | AUTHORITY | 07/11/2025 |
| Marian Ralph Vinod Mascarenhas vs LGCL Properties Pvt. Ltd. | Refund of full payment with interest and compensation | AUTHORITY | 07/11/2025 |
| Mridula Manu vs LGCL PUEBLO | Punish the promoter in terms of Sections 60 & 61 of the Act | AUTHORITY | 07/03/2024 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (32 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/190627/0003248 27-06-2019 | REFUND | LGCL Stonescape (another project by this promoter) | DISPOSED AO |
| CMP/190807/0003824 07-08-2019 | Delay and Compensation | LGCL Stonescape (another project by this promoter) | DISPOSED AO |
| CMP/191012/0004428 12-10-2019 | Seeking for delay compensation as per RERA provisions and direct respondent to handover possession within 6 months | LGCL PUEBLO | DISPOSED AO |
| CMP/200307/0005447 07-03-2020 | delay in handover | LGCL PUEBLO | DISPOSED AUTHORITY FULLBENCH |
| CMP/200327/0005798 27-03-2020 | The Home Buyers are awaiting for completion & Possession of the Project even after payment of 100 % of the Consideration amount towards the purchase of the house. | LGCL PUEBLO | DISPOSED AUTHORITY FULLBENCH |
| CMP/200713/0006155 13-07-2020 | Home Buyers are awaiting for completion & Possession of the Project even after payment of 100 % of the Consideration amount towards the purchase of the house. | LGCL PUEBLO | DISPOSED AUTHORITY FULLBENCH |
| CMP/200713/0006156 13-07-2020 | Home Buyers are awaiting for completion & Possession of the Project even after payment of 100 % of the Consideration amount towards the purchase of the house. | LGCL PUEBLO | DISPOSED AUTHORITY FULLBENCH |
| CMP/200713/0006157 13-07-2020 | Home Buyers are awaiting for completion & Possession of the Project even after payment of 100 % of the Consideration amount towards the purchase of the house. | LGCL PUEBLO | DISPOSED AUTHORITY FULLBENCH |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Project team & certifications
RERA filingK-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Architect | Mr. Andrew Bergmans A | - | 2011 | #12/1, Rest House Road |
| Contractor | M/s. S.G. Construction Projects | - | 2002 | 2nd floor, Rajajinagar |
| Structural engineer | Mr.Arunachala | - | - | - |
Builder track record
RERA filingLgcl Properties has 3 other K-RERA-registered projects in our records. 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filing⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
Declared construction cost ÷ registered units averages to ₹65.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.
RERA 70% project account is on file: ICICI Bank MG ROAD (IFSC ICIC0000002, a/c …6560). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Construction photo filings
RERA filingK-RERA has 1 project-photo upload.
These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.
Location & Connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Bellandur–Marathahalli belt | 6 km |
| MG Road / city centre | 7 km |
| Electronic City | 8 km |
| Whitefield IT hub | 14 km |
| Outer Ring Road / Manyata | 14 km |
| Kempegowda Int'l Airport | 32 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.