Bangalore/Project record

K-RERA · the public record

MANA VISTA

Anekal · MANA PROJECTS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

12%construction reportedQ1 2026 filing
266units not bookedof 379 · Q1 2026 filing
31 Dec 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2BHK + STUDY - 2T
79
2BHK-2T
35
3BHK-3T
152
3BHK-2T
78
EWS
35

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

5.4registered acres

70.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/150325/007585

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2030
Land area21,752 sq m (5.4 acres)
Homes registered379
Tower/wing entries3
Unit mix79 × 2BHK + STUDY - 2T, 35 × 2BHK-2T, 152 × 3BHK-3T, 78 × 3BHK-2T, 35 × EWS

In context

Density70.5 homes per acre
Density in context43rd percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units379Total inventory registered with K-RERA.
Official carpet area29,177 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area33,875 sqmUseful scale context when comparing density and project cost.
Registered land area21,752 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)574Separate filed counts; these categories may overlap and are not added together.
Covered-parking field583Separate filed counts; these categories may overlap and are not added together.
Open-parking field8Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan number47/2024-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date15-01-2025
Project start date01-07-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2BHK + STUDY - 2T7921%5,465 sqm
2BHK-2T359%2,605 sqm
3BHK-3T15240%13,994 sqm
3BHK-2T7821%6,540 sqm
EWS359%573 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
TOWER 188415526.975 m
TOWER 287415526.975 m
TOWER 31422126444.975 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 379 official flat/unit rows, matching the 379 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK-3T15290.6-93.7 sqm34.2-1,147.9 sqm152
2BHK + STUDY - 2T7968.8-71.4 sqm36.5-38.0 sqm79
3BHK-2T7883.2-85.5 sqm44.0-45.4 sqm78
2BHK-2T3573.6-76.7 sqm39.0-42.0 sqm35
EWS3515.0-17.3 sqm8.0-9.0 sqm1 (34 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
TOWER 322168.8-93.7 sqm34.2-1,147.9 sqm221
TOWER 18415.0-92.8 sqm8.0-50.0 sqm66 (18 with 0)
TOWER 27416.3-93.4 sqm8.0-51.0 sqm58 (16 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1TOWER 102BHK-2T76.5 sqm40.0 sqm1
2TOWER 10EWS15.0 sqm8.0 sqm1
3TOWER 102BHK-2T74.8 sqm41.0 sqm1
4TOWER 10EWS16.1 sqm8.0 sqm0
5TOWER 103BHK-2T83.5 sqm44.0 sqm1
6TOWER 103BHK-2T83.5 sqm44.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

5 of 33 compliance document slots are filed as Not Applicable; the remaining 28 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (3 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200609/0005992
09-06-2020
Wall Cracks all over the wall of my house 8 times digged and rectified lost my wood work scratches ,mirror broken Charm gone ,Low quality of work demand CompensationMANA TROPICALE (another project by this promoter)DISPOSED AO
CMP/211119/0008604
19-11-2021
Modification of Flat against project plan /no emergency exit or ambulance way/ poor constructionMANA TROPICALE (another project by this promoter)DISPOSED AO
CMP/220324/0009249
24-03-2022
Change in flat structure without consent - Tower 4 C 1103UBER VERDANT - II (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved08-12-2021WATER NOC 08-12-2021.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved13-04-2022KSPCB 13-04-2022.pdf
KPTCL- BESCOMApproved15-07-2024BESCOM NOC 15-07-2024.pdf
Fire and SafetyApproved05-10-2024FIRE NOC 05-10-2024.pdf
Airport Authority of IndiaApproved07-04-2022Airport NOC 07-04-2022.pdf
BSNL/Telecommunication DepartmentApproved14-03-2022BSNL NOC 14-03-2022.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantKrishna Reddy Gundluri2342382014Bengaluru Urban, Karnataka - 560103
EngineerAmbrish GBCC/BL-3.6/SE-340/22-232015Bengaluru Urban, Karnataka - 560032
ArchitectGnanavel1253/20112011Bengaluru Urban, Karnataka - 560032
ContractorMANA PROJECTS PVT LTD-2000Bengaluru Urban, Karnataka - 560103

Builder track record

RERA filing

Mana Projects has 13 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Mana Projects”) (average reported construction progress 38%). 4 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹8.75 Cr collected from buyers, ₹7.59 Cr withdrawn from the project's escrow account.

Construction progress4% → 12% (+8 pts)
Units sold/booked as registered113/379 (30%)
Buyer collections in available QPRs₹30.70 Cr
Escrow withdrawals in available QPRs₹21.74 Cr (0.71x collections)
  • Construction progress moved from 4% to 12% across the filed QPR window.
  • The builder has drawn 0.71x of buyer collections from escrow (about 71% of the ₹31 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹46.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Karnataka Bank Ltd.. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City5 km
Bellandur–Marathahalli belt7 km
Whitefield IT hub12 km
MG Road / city centre15 km
Outer Ring Road / Manyata20 km
Kempegowda Int'l Airport36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mana Projects. View Mana Projects's full track record →
Mana Projects has 8 projects registered in Bangalore, 1 completed.
1 complaints on the K-RERA register against Mana Projects in Bangalore.

Other projects by this builder in Bangalore

Macasa Emerald
On track · 99% built · 61% sold
Mana Dale
On track · 52% built · 92% sold
Mana Dale South -1
On track · 35% built · 41% sold
Mana Verdant
On track · 8% built · 0% sold
Mana Verdant Terraces
On track · 2% built · 10% sold

Other RERA-registered projects in Gattahalli

Major developers building in Gattahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Mana Vista?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026