Bangalore/Project record

K-RERA · the public record

MANA VERDANT TERRACES

Bengaluru East · MANA PROJECTS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

2%construction reportedQ1 2026 filing
285units not bookedof 318 · Q1 2026 filing
31 Dec 2031declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Flats
318

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

8.7registered acres

36.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/041225/008303

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2031
Land area35,042 sq m (8.7 acres)
Homes registered318
Tower/wing entries2
Unit mix318 × Flats

In context

Density36.7 homes per acre
Density in context13th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units318Total inventory registered with K-RERA.
Official carpet area42,713 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area90,824 sqmUseful scale context when comparing density and project cost.
Registered land area35,042 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)693Separate filed counts; these categories may overlap and are not added together.
Covered-parking field671Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field279Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/CC/10594/2025-26,Use this to match the sanctioned drawing set shown by the builder.
Plan approval date04-11-2025
Project start date01-12-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Flats318100%42,714 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower 11915953460.45 m
Tower 21915915959.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 318 official flat/unit rows, matching the 318 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK318107.9-136.3 sqm44.4-66.2 sqm318

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower 1159107.9-136.3 sqm44.4-65.9 sqm159
Tower 2159107.9-136.3 sqm44.4-66.2 sqm159
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
T1-001Tower 103 BHK126.8 sqm65.0 sqm1
T1-002Tower 103 BHK126.8 sqm65.0 sqm1
T1-003Tower 103 BHK121.5 sqm63.1 sqm1
T1-004Tower 103 BHK127.2 sqm65.7 sqm1
T1-005Tower 103 BHK136.3 sqm65.9 sqm1
T1-006Tower 103 BHK126.1 sqm59.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

6 of 34 compliance document slots are filed as Not Applicable; the remaining 28 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (3 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200609/0005992
09-06-2020
Wall Cracks all over the wall of my house 8 times digged and rectified lost my wood work scratches ,mirror broken Charm gone ,Low quality of work demand CompensationMANA TROPICALE (another project by this promoter)DISPOSED AO
CMP/211119/0008604
19-11-2021
Modification of Flat against project plan /no emergency exit or ambulance way/ poor constructionMANA TROPICALE (another project by this promoter)DISPOSED AO
CMP/220324/0009249
24-03-2022
Change in flat structure without consent - Tower 4 C 1103UBER VERDANT - II (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved07-05-2025BWSSB NOC 07-05-2025.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved24-11-2022KSPCB NOC_compressed -24-11-2022.pdf
KPTCL- BESCOMApproved30-12-2024Bescom Noc and Fees Recepit -30-12-2024.pdf
Fire and SafetyApproved16-05-2025Fire NOC - Mana Province -16-05-2025.pdf
Airport Authority of IndiaApproved01-12-2022Airport NOC -1-12-2022.pdf
BSNL/Telecommunication DepartmentApproved16-09-2022BSNL NOC -16-09-2022.jpeg

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantKrishna Reddy Gundluri2342382014Bengaluru Urban, Karnataka - 560103
EngineerAmbrish GBCC/BL/3.6/SE/266/2017-182015Bengaluru Urban, Karnataka - 560032
Architectjayant Vaitha2007/409922012Bengaluru Urban, Karnataka - 560071
ContractorMANA PROJECTS PVT LTD-2000Bengaluru Urban, Karnataka - 560103

Builder track record

RERA filing

Mana Projects has 13 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Mana Projects”) (average reported construction progress 40%). 4 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹5.48 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress0% → 2% (+2 pts)
Units sold/booked as registered33/318 (10%)
Buyer collections in available QPRs₹7.79 Cr
  • Construction progress moved from 0% to 2% across the filed QPR window.
  • The builder has drawn 0.00x of buyer collections from escrow (about 0% of the ₹8 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹95.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank Corporate Banking Branch IFSC Code : UTIB0001541 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bellandur–Marathahalli belt3 km
Electronic City8 km
Whitefield IT hub9 km
MG Road / city centre13 km
Outer Ring Road / Manyata17 km
Kempegowda Int'l Airport32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mana Projects. View Mana Projects's full track record →
Mana Projects has 8 projects registered in Bangalore, 1 completed.
1 complaints on the K-RERA register against Mana Projects in Bangalore.

Other projects by this builder in Bangalore

Macasa Emerald
On track · 99% built · 61% sold
Mana Dale
On track · 52% built · 92% sold
Mana Dale South -1
On track · 35% built · 41% sold
Mana Verdant
On track · 8% built · 0% sold
Mana Vista
On track · 12% built · 30% sold

Other RERA-registered projects in Chikkakannalli

Major developers building in Chikkakannalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Mana Verdant Terraces?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026