K-RERA · the public record
Mantri Manyata Energia
Bengaluru North · BUOYANT TECHNOLOGY CONSTELLATIONS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Jun 2020
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
11.4registered acres
77.8registered units per acre
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project · Prestige Park Grove
A larger advertised area. Almost the same carpet area.
In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.
This illustrates the report format. These findings concern the named sample, not this project.
Read the sample report ↗
The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/309/PR/171014/000439
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
In context
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered units | 887 | Total inventory registered with K-RERA. |
| Registered land area | 46,134 sqm | The land area attached to this K-RERA registration. |
| Sanctioned FAR/FSI | 3.25 | Higher FAR generally means a denser vertical build, subject to site layout and open-space design. |
| Registered tower/wing entries | 6 | Official tower/wing count in the K-RERA detail page. |
| Parking total (reconciled) | 971 | Separate filed counts; these categories may overlap and are not added together. |
| Open-parking field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Project start date | 13-07-2015 |
Official inventory & towers
RERA filingK-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered tower / wing summary
| Tower/wing | Floors | Units | Parking | Height |
|---|---|---|---|---|
| A | 18 | 148 | 162 | - |
| B | 18 | 148 | 162 | - |
| C | 18 | 148 | 162 | - |
| H | 18 | 148 | 162 | - |
| I | 18 | 148 | 162 | - |
| J | 18 | 147 | 161 | - |
Official unit register
RERA filingK-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 887 official flat/unit rows, matching the 887 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.
By unit type
| Unit type | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| 2.5-BHK | 442 | 81.3-81.5 sqm | 5.9-6.3 sqm | 442 |
| 3-BHK (A) | 441 | 88.4 sqm | 6.4-6.8 sqm | 441 |
| 1.5-BHK | 4 | 63.2-63.2 sqm | 4.7-4.9 sqm | 4 |
By tower / wing
| Tower/wing | Rows | Carpet area | UDS | Parking lots |
|---|---|---|---|---|
| A | 148 | 63.2-88.4 sqm | 4.9-6.7 sqm | 148 |
| B | 148 | 63.2-88.4 sqm | 4.7-6.4 sqm | 148 |
| C | 148 | 81.3-88.4 sqm | 5.9-6.4 sqm | 148 |
| H | 148 | 81.3-88.4 sqm | 5.9-6.4 sqm | 148 |
| I | 148 | 63.2-88.4 sqm | 4.7-6.4 sqm | 148 |
| J | 147 | 63.2-88.4 sqm | 4.9-6.8 sqm | 147 |
Show sample official unit rows
| Unit | Tower | Floor | Type | Carpet | UDS | Parking |
|---|---|---|---|---|---|---|
| A-002 | A | 0 | 1.5-BHK | 63.2 sqm | 4.9 sqm | 1 |
| A-003 | A | 0 | 3-BHK (A) | 88.4 sqm | 6.7 sqm | 1 |
| A-005 | A | 0 | 2.5-BHK | 81.3 sqm | 6.2 sqm | 1 |
| A-006 | A | 0 | 2.5-BHK | 81.3 sqm | 6.2 sqm | 1 |
| A-007 | A | 0 | 3-BHK (A) | 88.4 sqm | 6.7 sqm | 1 |
| A-008 | A | 0 | 3-BHK (A) | 88.4 sqm | 6.7 sqm | 1 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
3 of 35 compliance document slots are filed as Not Applicable; the remaining 32 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 30 Jun 2020, extended (Section 6 Extension) to 30 Dec 2021 — both dates have passed with no OC on file. The extension on file was granted on 13 Dec 2021 (K-RERA extension no. EX/PRM/KA/RERA/1251/309/PR/211213/000439) — it has been used, its deadline has also passed, and no further extension is recorded.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA enforcement record (the regulator's own defaulter list & penalty orders)
⚠ Listed on K-RERA's official DEFAULTER list.
2 K-RERA orders on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.
K-RERA complaint orders (47 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| SHARATH KUMAR MAHAJAN vs MANTRI TECHNOLOGY CONSTELLATIONS PRIVATE LIMITED & OTHERS | Direct to complete the project in another 6 months, handover fully furnished flat No. J-1706 , to pay delay period interest, if not respondents liable to pay claims of complainant claimed as in MOC | AUTHORITY | 30/04/2024 |
| Santhi Lakshmanan vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD | compensation, refund | AUTHORITY | 29/07/2022 |
| MR JOSEPH MATHIAS vs M/S.MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD | As prayed in the Facts of Complaint | AUTHORITY | 27/03/2023 |
| MR AMARJEET SINGH GILL vs M/S.MANTRI TECHNOLOGY CONSTELLATIONS | Request for the refund of the amount with interest | AUTHORITY | 25/05/2023 |
| MR SUJAY MEETHALE PURAYIL AND ANOTHER vs M/S.MANTRI TECHNOLOGY CONSTELLTIONS | Direct Developer 1.Refund amount paid by complainant towards sale consideration with interest 2.Pay loan outstanding amount directly to Bank 3.Pay Complainants all Pre-EMI/EMIs paid to Bank till date. | AUTHORITY | 22/07/2024 |
| Jai Sahani vs Mantri Technology Constructions Private Liited | full refund of their own contribution and the PRE-EMIs paid to the financial institute on account of the default of the Respondent | AUTHORITY | 22/06/2026 |
| MR.ARJUN R MENON vs M/S.MANTRI TECHNOLOGY CONSTELLATIONS | As prayed in the Facts of Complaint | AUTHORITY | 21/04/2023 |
| Fahmida Natankar Anwar vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD | As prayed in the Facts of Complaint | AUTHORITY | 20/01/2023 |
| H Anand vs MANTRI TECHNOLOGY CONSTELLATIONS PRIVATE LIMITED | As prayed in the Facts of Complaint | AUTHORITY | 19/10/2022 |
| Madhumathi A vs MANATRI TECHNOLOGY CONSTELLATIONS PVT LTD | As prayed in the Facts of Complaint | AUTHORITY | 19/10/2022 |
| Manish Prabhat Tigga vs MANTRI TECHNOLOGY CONSTELLATIONS | As prayed in the Facts of Complaint | AUTHORITY | 18/01/2023 |
| SMARAN THOMAS vs MANTRI TECHNOLOGY CONSTELLATIONS | As prayed in the Facts of Complaint | AUTHORITY | 18/01/2023 |
| Sudhindra R vs MANTRI TECHNOLOGY CONSTELLATIONS | As prayed in the Complaint | AUTHORITY | 18/01/2023 |
| Krishna Hegde vs MANTRI TECHNOLOGY CONSTELLATIONS | Please help me to get my House or Return my money with 18% PA interest till now. | AUTHORITY | 18/01/2023 |
| Sandeep Radhakrishnan vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD | Fast track completion within a period not extending a year. If builder cannot handle further, please take action to handover the project to any other reliable reputed builder and complete the project | AUTHORITY | 15/11/2022 |
| Lakshminarayana and Padma vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD | Relief as per the decision of the supreme court cited above | AUTHORITY | 15/11/2022 |
| SIDDANNA MARPALLE vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD | As prayed in the Facts of Complaint | AUTHORITY | 15/10/2022 |
| ANAND H P vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD | Delay in handling over possession and other relief (Including interest and penalty) | AUTHORITY | 15/10/2022 |
| GAGAN SHETTY & ANOTHER vs MANTRI TECHNOLOGY CONSTELLATIONS PVT. LTD., | Request for the refund of the amount with interest | AUTHORITY | 14/05/2024 |
| Prakash Mall vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD, MANYATA REALTY | As prayed for Facts of Complaint | AUTHORITY | 10/10/2022 |
| Hardikkumar Shah vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD, MANYATA INFRASTRUCTURE DEVELOPMENT PRIVATE LTD., MANYATA REALTY | As prayed in the Facts of Case | AUTHORITY | 10/10/2022 |
| Kandi Phani Kumar vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Complaint | AUTHORITY | 09/11/2022 |
| Rashmi Ranjan Mishra vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD | As prayed in the Facts of Complaint | AUTHORITY | 09/11/2022 |
| Vijayaraghavan S V vs Mantri Technology Constellations Pvt Ltd., | As prayed in the Facts of Case | AUTHORITY | 08/11/2022 |
| Prashant S Ghargi vs Mantri Technology Constellations Pvt Ltd | As prayed in the Facts of Complaint | AUTHORITY | 07/11/2022 |
| MR.VARUN RAVISHANKAR vs M/S.MANTRI TECHNOLOGY CONSTELLATIONS | As prayed in Facts of Complaint | AUTHORITY | 07/03/2023 |
| MR.N.V.RAGHAVAN vs M/S.MANTRI TECHNOLOGY CONSTELLATIONS | As prayed in the Facts of Complaint | AUTHORITY | 07/03/2023 |
| Harshil J Shah vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD(BUOYANT TECHNOLOGY CONSTELLATION PVT LTD), MANYATA REALTY | As prayed in the Facts of Complaint | AUTHORITY | 06/12/2022 |
| Jai Sahani vs 1. MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD. 2. MANYATA INFRASTRUCTURE DEVELOPMENT PVT LTD | As prayed in Facts of Complaint | AUTHORITY | 06/09/2022 |
| Shanthi Chandrababu vs 1.MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD. 2. GOKULAM SHELTERS PVT LTD | as prayed in the Facts of Complaint | AUTHORITY | 06/09/2022 |
| Indrani N R vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD. CURRENTLY KNOWN AS BUOYANT TECHNOLOGY CONSTELLATIONS PVT LTD | As prayed in the Complaint | AUTHORITY | 05/09/2022 |
| Basawaraj Yallappa Hongal vs MANTRI TECHNOLOGY CONSTELLATIONS PVT LTD., CURRENTLY KNOWN AS BUOYANT TECHNOLOGY CONSTELLATIONS PVT LTD. | As prayed in the Facts of Complaint | AUTHORITY | 05/09/2022 |
| MALLIKARJUNA JS & KOMALA ASHOK vs MANTRI TECHNOLOGY CONSTELLATIKONS PVT. LTD., | Refund of advance sale consideration of Rs.10,00,000/- (Rupees Ten Lakh only) along with compensation calculated at Rs.4,00,000/- (Rupees Four Lakh only) at the rate of 24% p.a | AUTHORITY | 05/08/2024 |
| MR C.R.RENIL KUMAR & ANOTHER vs M/S.MANTRI TECHNOLOGY & OTHERS | Direct Developer to: 1.Refund sale consideration and Bank loan disbursed amount along with interest 2.Pay to Complainant Pre-EMIs & EMIs paid till date to bank, 3.Pay loan outstanding amount to Bank | AUTHORITY | 05/01/2024 |
| Amit Kumar Singh vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Complaint | AUTHORITY | 02/11/2022 |
| Shashank Aroor vs Mantri Manyata Energia | As prayed in the Facts of complaint | AUTHORITY | 02/11/2022 |
| Sriram and Anuradha R vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Complaint | AUTHORITY | 02/11/2022 |
| Kumaraswamy R S vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Complaint | AUTHORITY | 02/11/2022 |
| Anoop Kumar H S R vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Complaint | AUTHORITY | 02/11/2022 |
| Niveditha B K vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Complaint | AUTHORITY | 02/11/2022 |
| Ravi Tomal Raghavendra vs Mantri Technology Constellations Pvt. Ltd. | As prayed for in the Facts of complaint | AUTHORITY | 02/11/2022 |
| Vijaya S S vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Case | AUTHORITY | 02/11/2022 |
| Noor Ayesha vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Complaint | AUTHORITY | 02/11/2022 |
| Dr.Akshay Dwarakanath vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Complaint | AUTHORITY | 02/11/2022 |
| Mubeena Kausar vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Complaint | AUTHORITY | 02/11/2022 |
| Sukanta Kumar Nayak vs Mantri Technology Constellations Pvt. Ltd. | As prayed in the Facts of Complaint | AUTHORITY | 02/11/2022 |
| MR.SATHISH R THOPPEY vs M/S.MANTRI TECHNOLOGY CONSTELLATIONS | As prayed in the Facts of Complaint | AUTHORITY | 01/03/2023 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (96 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/190213/0002123 13-02-2019 | Delay in handing over, INTEREST AND COMPENSATION | Mantri Manyata Lithos (another project by this promoter) | DISPOSED AO |
| CMP/190219/0002210 19-02-2019 | Delay in handing over, interest and compensation | Mantri Manyata Lithos (another project by this promoter) | DISPOSED AO |
| CMP/190228/0002318 28-02-2019 | Delay in possession, interest and compensation | Mantri Manyata Lithos (another project by this promoter) | DISPOSED AO |
| CMP/190301/0002324 01-03-2019 | Delay in possession, compensation, interest and other reliefs | Mantri Manyata Lithos (another project by this promoter) | DISPOSED AO |
| CMP/190301/0002326 01-03-2019 | delay in possession, interest & compensation | Mantri Manyata Lithos (another project by this promoter) | DISPOSED AO |
| CMP/190318/0002456 18-03-2019 | Delay in handing over apartment | Mantri Manyata Lithos (another project by this promoter) | DISPOSED AO |
| CMP/190325/0002512 25-03-2019 | Delay in possession, interest, compensation | Mantri Manyata Lithos (another project by this promoter) | DISPOSED AO |
| CMP/190329/0002535 29-03-2019 | Delay in handing over possession | Mantri Manyata Lithos (another project by this promoter) | DISPOSED AO |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Project team & certifications
RERA filingK-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Architect | Edifice Consultants Pvt Ltd. | - | NA | 12 Museum Road, 12 Museum Road |
| Contractor | TATA PROJECTS LIMITED, | - | NA | 1-7-80 to 87, Prenderghast Road |
| Structural engineer | NAGESH CONSULTANTS | - | - | - |
Financials & Construction Progress
Financial disclosures
RERA filing⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
Declared construction cost ÷ registered units averages to ₹37.8 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.
RERA 70% project account is on file: HDFC Kasturba Road BranchI (IFSC HDFC0000009, a/c …7496). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Construction photo filings
RERA filingK-RERA has 1 project-photo upload.
These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.
Location & Connectivity
The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Outer Ring Road / Manyata | 2 km |
| MG Road / city centre | 9 km |
| Bellandur–Marathahalli belt | 15 km |
| Whitefield IT hub | 17 km |
| Kempegowda Int'l Airport | 18 km |
| Electronic City | 24 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.