RERA Property Intelligence Report · Preview

Mantri Manyata Lithos

Mantri Technology Constellations · Bengaluru North · K-RERA PRM/KA/RERA/1251/309/PR/171201/000444

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
8
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

528
Registered units
₹359.9 Cr
Est. construction cost
Units profiled
40
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units528Total inventory registered with K-RERA.
Registered land area24,603 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings8Official tower/wing count in the K-RERA detail page.
Parking disclosed716 total (130 open) — 1.36 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date10-06-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
NOT WORKING00 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A2078108-
B187096-
C166274-
D145474-
E2078108-
F187096-
G166286-
H145474-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 528 official flat/unit rows, matching the 528 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2.5-BHK192111.6-116.7 sqm7.1-10.6 sqm192
2.0-BHK14090.2-94.1 sqm6.0-8.8 sqm140
3.0-BHK124120.7-122.5 sqm7.9-11.8 sqm124
2-BHK5690.2-93.3 sqm7.4-7.7 sqm56
P.H.16197.5-213.3 sqm12.8-18.7 sqm16

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A7891.0-213.3 sqm6.0-13.5 sqm78
E7891.0-213.3 sqm6.0-13.5 sqm78
B7090.2-204.5 sqm6.5-14.7 sqm70
F7090.2-204.5 sqm6.5-14.7 sqm70
C6290.2-204.5 sqm7.4-16.6 sqm62
G6290.2-204.5 sqm7.4-16.6 sqm62
D5494.1-197.5 sqm8.8-18.7 sqm54
H5494.1-197.5 sqm8.8-18.7 sqm54
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-101A12.0-BHK93.0 sqm6.1 sqm1
A-102A12.5-BHK111.6 sqm7.1 sqm1
A-103A12.0-BHK94.1 sqm6.1 sqm1
A-104A13.0-BHK122.5 sqm7.9 sqm1
A-201A22.0-BHK91.0 sqm6.0 sqm1
A-202A22.5-BHK112.6 sqm7.4 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~1,191 sqft — large-format homes (3BHK-and-up territory), not compact stock. This is a large, multi-tower township — 528 homes across 8 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 716 parking spaces for 528 homes (~1.4 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~9 sqm per home; across all 528 homes that is ~18% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

3 of 35 compliance document slots are filed as Not Applicable; the remaining 32 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 01 Jul 2019, extended (Section 6 Extension) to 01 Jul 2020 — both dates have passed with no OC on file. The extension on file was granted on 21 Dec 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/309/PR/221221/000444) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (16 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
ROBIN GHOSE & POOJA GHOSE vs M/S BUOYANT TECHNOLOGY CONSTELLATIONS PRIVATE LIMITED FORMERLY KNOWN AS M/S MANTRI TECHNOLOGY CONSTELLATIONS PRIVATE LIMITEDdirect the REspondent to execute and register sale deed and hand over possession in favour of the complainant by completing all amenitiesAUTHORITY27/11/2023
NATARAJAN RAMAN vs MANTRI TECHNOLOGY CONSTELLATIONS PVT. LTD.To handover possession with compensationAUTHORITY25/06/2022
PULKIL ARORA vs MANTRI MANYATA LITHOSCompensation for delay as per RERA.AUTHORITY25/05/2023
Kiron B Magal vs Mantri Technology Constellations Pvt. Ltd.It is most humbly prayed before Hon’ble RERA for directing the Builder/ promoter/ Respondent to pay compensation for the delay as per the RERA guidelines in the interest of justice and equity.AUTHORITY14/02/2024
GORAKHANATH KATHARE vs Mantri Manyat LithosDirect the Respondents to execute sale Deed registered in the names of complainants with Possession of an apartment bearing No G 902 by receiving the balance Consideration of Rs 83,15,819AUTHORITY13/04/2026
Ram Kumar Thakur vs Mantri Technology Constellations Pvt. Ltd.Possession handover and compensationAUTHORITY12/10/2022
Shashank Peddakotla vs Mantri Technology Constellations Pvt. Ltd.To handover the apartment and pay delay compensation as per RERA ActAUTHORITY12/10/2022
VENKAT RAO MARELLA & ANOTHER vs M/S MANTRI TECHNOLOLGY CONSTELLATIONS PRIVATE LIMITEDDelay compensation with possession or refund. complete relief mentioned in the facts of complaint due to lack of spaceAUTHORITY10/04/2024
ANANTHA KRISHNA SHIVRAM vs M/S MANTRI TECHNOLOGY CONSTELLATIONS PRIVATE LIMITED, & MANYATA REALTYRefund of Rs.33,00,000/- along with interest and compensation for delay.AUTHORITY07/11/2023
Manzar Imam & 4 others vs M/S BUOYANT TECHNOLOGY CONSTELLATIONS PRIVATE LIMITED & OTHERSINTERIM PRAYER: To direct the respondents to immediately & jointly register the respective Sale Deeds of the individual apartments & levy 5% penalty on respondentsAUTHORITY03/04/2023
Manzar Imam vs M/S BUOYANT TECHNOLOGY CONSTELLATIONS PRIVATE LIMITED & OTHERSview of the facts & grounds mentioned above, the complainant prays this Hon’ble RERA Authority be pleased allow this complaint &; i. Order the release of the deposit of Rs. 48,27,6 and other reliefsAUTHORITY03/04/2023
Smita Narendranth vs M/S BUOYANT TECHNOLOGY CONSTELLATIONS PRIVATE LIMITED & OTHERSTo levy Penalty of 5% on developer for non-compliance of AO orderAUTHORITY03/04/2023
Sreeram Reddy vs M/S BUOYANT TECHNOLOGY CONSTELLATIONS PRIVATE LIMITED & OTHERSINTERIM PRAYERS The Complainant humbly PRAYS that this Hon’ble RERA authority be pleased to grant an interim order by directing: The respondents, before filing their appearance for defending thisAUTHORITY03/04/2023
Satyakam Vashisth vs M/S BUOYANT TECHNOLOGY CONSTELLATIONS PRIVATE LIMITED & OTHERSINTERIM PRAYERS The Complainant humbly PRAYS that this Hon’ble RERA authority be pleased to grant an interim order by directing: i. The respondents, before filing their appearance for defending this sAUTHORITY03/04/2023
Kanthi Kiran Durga Venkata Narayanashetty vs M/S BUOYANT TECHNOLOGY CONSTELLATIONS PRIVATE LIMITED & OTHERSTo levy penalty of 5% of project cost on developerAUTHORITY03/04/2023
Rohit A vs Mantri Manyata LithosMantri should pay 18% p.a interest from Jul 2017 to date as they are charging me 18%. Mantri should facilitate registration of my apartment at the earliest.AUTHORITY02/09/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (96 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190213/0002123
13-02-2019
Delay in handing over, INTEREST AND COMPENSATIONMantri Manyata LithosDISPOSED AO
CMP/190219/0002210
19-02-2019
Delay in handing over, interest and compensationMantri Manyata LithosDISPOSED AO
CMP/190228/0002318
28-02-2019
Delay in possession, interest and compensationMantri Manyata LithosDISPOSED AO
CMP/190301/0002324
01-03-2019
Delay in possession, compensation, interest and other reliefsMantri Manyata LithosDISPOSED AO
CMP/190301/0002326
01-03-2019
delay in possession, interest & compensationMantri Manyata LithosDISPOSED AO
CMP/190318/0002456
18-03-2019
Delay in handing over apartmentMantri Manyata LithosDISPOSED AO
CMP/190325/0002512
25-03-2019
Delay in possession, interest, compensationMantri Manyata LithosDISPOSED AO
CMP/190329/0002535
29-03-2019
Delay in handing over possessionMantri Manyata LithosDISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectHadi Teherani Project Consultant India Pvt. Ltd.-NAPrimrose Road, Off MG Road
ContractorTATA PROJECTS LIMITED,-NA1-7-80 to 87, Prenderghast Road
Structural engineerInnotech Engineering Consult Pvt Ltd---

Builder track record

RERA filing

Mantri has 8 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Mantri Technology”). 8 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹68.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: PUNJAB NATIONAL BANK OF INDIA Cantonment Branch (IFSC PUNB0004000, a/c …6178). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Outer Ring Road / Manyata2 km
MG Road / city centre9 km
Bellandur–Marathahalli belt15 km
Whitefield IT hub17 km
Kempegowda Int'l Airport18 km
Electronic City24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mantri Technology. View Mantri Technology's full track record →

Other RERA-registered projects in Nagavara

Major developers building in Nagavara

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Mantri Manyata Lithos?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 27 Jul 2026