16%construction reportedQ1 2026 filing
77units not bookedof 123 · Q1 2026 filing
31 Dec 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q4 2025 to Q1 2026

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

4 BHK Villas
123

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

10.5registered acres

11.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/050126/008381

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2030
Land area42,593 sq m (10.5 acres)
Homes registered123
Tower/wing entries1
Unit mix123 × 4 BHK Villas

In context

Density11.7 homes per acre
Density in context4th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units123Total inventory registered with K-RERA.
Official carpet area25,893 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area36,041 sqmUseful scale context when comparing density and project cost.
Registered land area42,593 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI0.759Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)123Separate filed counts; these categories may overlap and are not added together.
Covered-parking field123Separate filed counts; these categories may overlap and are not added together.
Open-parking field13Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberLAO/125/22-23Use this to match the sanctioned drawing set shown by the builder.
Plan approval date12-02-2024
Project start date01-01-2026

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK Villas123100%25,893 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
NVT A WONDERFUL WORLD PHASE I212312310.15 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 123 official flat/unit rows, matching the 123 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4 BHK123194.9-294.6 sqm154.6-374.0 sqm123

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
NVT A WONDERFUL WORLD PHASE I123194.9-294.6 sqm154.6-374.0 sqm123
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A1NVT A WONDERFUL WORLD PHASE I04 BHK214.8 sqm190.3 sqm1
A2NVT A WONDERFUL WORLD PHASE I04 BHK214.8 sqm190.3 sqm1
A3NVT A WONDERFUL WORLD PHASE I04 BHK214.8 sqm190.3 sqm1
A4NVT A WONDERFUL WORLD PHASE I04 BHK214.8 sqm190.3 sqm1
A5NVT A WONDERFUL WORLD PHASE I04 BHK214.8 sqm190.3 sqm1
A6NVT A WONDERFUL WORLD PHASE I04 BHK214.8 sqm190.3 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 23 compliance document slots are filed as Not Applicable; the remaining 22 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

7 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
KSPCB- PCB (10 Acres to 125 Acres)Approved03-10-2023KSPCB NOC Dtd-03102023 (JIGALA).pdf
KSPCB- MOEF (Above 50 Acres)Approved28-11-2023MOEF SEIAA Jigala Project Dtd 28112023.pdf
KPTCL- BESCOMApproved05-04-2024Bescom Noc Dtd -05042024.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantJawaha S Nagpal248411991Bengaluru Urban, Karnataka - 560009
EngineerPavan H KBCC/BL-3.6/SE-0175/2023-242023Bengaluru Urban, Karnataka - 560066
ArchitectS Sampath KumarCA/2011/512212011Bengaluru Urban, Karnataka - 560008
ContractorEmjay Engineering Company-2011Bengaluru Urban, Karnataka - 560071

Builder track record

RERA filing

Nvt Quality has 8 other K-RERA-registered projects in our records (average reported construction progress 28%). 6 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹13.90 Cr collected from buyers, ₹12.90 Cr withdrawn from the project's escrow account.

Construction progress6% → 16% (+10 pts)
Units sold/booked as registered46/123 (37%)
Buyer collections in available QPRs₹19.20 Cr
Escrow withdrawals in available QPRs₹12.90 Cr (0.67x collections)
  • Construction progress moved from 6% to 16% across the filed QPR window.
  • The builder has drawn 0.67x of buyer collections from escrow (about 67% of the ₹19 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹89.4 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA WHITEFIELD BRANCH ( 04456) IFSC Code : SBIN0004456 Pin Code : 560066. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City13 km
Bellandur–Marathahalli belt18 km
Whitefield IT hub20 km
MG Road / city centre27 km
Outer Ring Road / Manyata32 km
Kempegowda Int'l Airport45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Nvt Quality.
Nvt Quality has 9 projects registered in Bangalore.

Other projects by this builder in Bangalore

NVT Mystic Garden Phase 2
No filings
NVT Oikos
On track · 21% built · 52% sold
NVT Stopping BY THE Woods
No filings

Other RERA-registered projects in BEML Cooperative Society Layout

Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5

Major developers building in BEML Cooperative Society Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.